817 N ANNAN TER 90042

Certificate Information: 817 N ANNAN TER 90042

Application / Permit
18014-10000-04307
Plan Check / Job No.
B18LA15705
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF EXISTING SINGLE FAMILY DWELLING. INCLUDING 2-STORY ADDITION OVER STORAGE ROOM AT THE REAR OF SFD.
Permit Issued
Issued on 1/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2018 APPLICANT
Green Plans Picked Up 8/13/2018 APPLICANT
Assigned to Plan Check Engineer 8/30/2018 CRISTINA SALAZAR
Corrections Issued 9/1/2018 CRISTINA SALAZAR
Quality Review Completed 9/5/2018 DAVID CHANG
Applicant returned to address corrections 10/29/2018 CRISTINA SALAZAR
Applicant returned to address corrections 11/14/2018 CRISTINA SALAZAR
Applicant returned to address corrections 12/12/2018 CRISTINA SALAZAR
Applicant returned to address corrections 1/9/2019 CRISTINA SALAZAR
Applicant returned to address corrections 1/23/2019 CRISTINA SALAZAR
Plan Check Approved 1/6/2020 CRISTINA SALAZAR
Plan Check Approved 1/15/2020 CRISTINA SALAZAR
Issued 1/16/2020 LADBS
Building Plans Picked Up 3/1/2021 APPLICANT
CofO in Progress 3/14/2023 CRAIG VAUGHAN
Permit Finaled 4/6/2023 DEROLD HAUFF
CofO Issued 4/6/2023 DEROLD HAUFF
Permit Finaled 4/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/12/2018 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/12/2018 CELINA MORENO
Permit Cleared 12/12/2018 CELINA MORENO
Sewer availability Cleared 12/12/2018 CELINA MORENO
Green Code Cleared 1/9/2019 KHEDER ALRAZAA
Housing rent stabilization Cleared 1/9/2019 STEVEN HOFSTAD
Low Impact Development Cleared 9/23/2019 MARTIN FRAGOSO
Disturb/Remove Protected Trees Cleared 10/11/2019 ADRIAN SANCHEZ
Address approval Cleared 11/18/2019 JEANIE LAM
GPI Written Notices Cleared 1/15/2020 CRISTINA SALAZAR
Roof/Waste drainage to street Cleared 1/15/2020 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Alvarado,, Carlos Humberto; Lic. No.: C19857 745 N WALNUTHAVEN DR      WEST COVINA, CA 91790
Engineer Lombera,, Raymundo A; Lic. No.: L7740 135 S JACKSON STREET #202      GLENDALE, CA 91205
Engineer Wong, Jim Chu Man; Lic. No.: C69393 PO BOX 91522      PASADENA, CA 91109

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/23/2020 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 5/21/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 5/21/2020 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 6/5/2020 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 6/5/2020 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 7/20/2020 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 7/20/2020 Partial Approval CRAIG VAUGHAN
Green Building Rough 7/20/2020 Not Ready for Inspection CRAIG VAUGHAN
Structural Steel Frame 7/20/2020 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 7/20/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 9/1/2020 Corrections Issued CRAIG VAUGHAN
Green Building Rough 9/1/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 9/1/2020 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 9/1/2020 Corrections Issued CRAIG VAUGHAN
Sewer 9/1/2020 Approved CRAIG VAUGHAN
Underground Mechanical 9/1/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 10/15/2020 Corrections Issued CRAIG VAUGHAN
Special/Order Compliance 10/15/2020 Partial Inspection CRAIG VAUGHAN
Special/Order Compliance 10/28/2020 Partial Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 11/10/2020 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 11/10/2020 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 11/10/2020 Approved CRAIG VAUGHAN
HVAC-Rough 11/10/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 11/10/2020 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 11/10/2020 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 11/10/2020 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 11/10/2020 Corrections Issued CRAIG VAUGHAN
Verify Sprinkler Sign Off 11/12/2020 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 12/14/2020 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 12/14/2020 Partial Approval CRAIG VAUGHAN
HVAC-Rough 12/14/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 1/15/2021 Approved CRAIG VAUGHAN
Shower Pan 1/15/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/14/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 5/14/2021 Partial Approval CRAIG VAUGHAN
HVAC-Rough 5/14/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/14/2021 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 5/14/2021 Approved CRAIG VAUGHAN
Insulation 5/25/2021 Approved THOMAS LOGRASSO
Drywall Nailing 6/14/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/14/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 2/15/2022 Corrections Issued CRAIG VAUGHAN
Wood Frame 2/15/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 2/28/2022 Corrections Issued CRAIG VAUGHAN
Gas Test 2/28/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 2/28/2022 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/28/2022 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 2/28/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 3/14/2022 Approved CRAIG VAUGHAN
Gas Test 3/14/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 3/14/2022 Approved CRAIG VAUGHAN
Smoke Detectors 3/14/2022 Approved CRAIG VAUGHAN
HVAC-Final 4/7/2022 Corrections Issued CRAIG VAUGHAN
HVAC-Final 4/15/2022 Approved CRAIG VAUGHAN
Final 3/7/2023 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 3/7/2023 Approved CRAIG VAUGHAN
Green Building Final 3/7/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Not Ready CRAIG VAUGHAN
Final 3/10/2023 Partial Approval KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Approved KATHRYN BUTTERWORTH