6306 S EILEEN AVE 90043

Certificate Information: 6306 S EILEEN AVE 90043

Application / Permit
18014-10000-04231
Plan Check / Job No.
B18LA15367
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED TWO STORY ADDITION (373.88 SQFT) TO (E) SFD.
Permit Issued
Issued on 10/31/2018
Issuing Office
Metro
Current Status
CofO Issued on 8/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2018 APPLICANT
Green Plans Picked Up 8/22/2018 APPLICANT
Assigned to Plan Check Engineer 9/6/2018 RAHEL BEYENE
Corrections Issued 9/25/2018 RAHEL BEYENE
Quality Review Completed 9/25/2018 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 10/2/2018 APPLICANT
Applicant returned to address corrections 10/25/2018 RAHEL BEYENE
Plan Check Approved 10/31/2018 RAHEL BEYENE
Issued 10/31/2018 LADBS
CofO in Progress 8/10/2023 ENRIQUE MIRELES
CofO in Progress 8/10/2023 ENRIQUE MIRELES
Permit Finaled 8/13/2023 DEROLD HAUFF
CofO Issued 8/13/2023 DEROLD HAUFF
Permit Finaled 8/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/11/2018 ADOLFO GUTIERREZ
Sewer availability Cleared 10/11/2018 ADOLFO GUTIERREZ
ZA Case Cleared 10/11/2018 IVORY CHAMBESHI
Green Code Cleared 10/17/2018 SARAH ABOULHOSN
Low Impact Development Cleared 10/17/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 10/17/2018 ADOLFO GUTIERREZ
Grading Pre-Inspection Cleared 10/25/2018 PATRICK MISCHLICH
GPI Written Notices Cleared 10/31/2018 RAHEL BEYENE

Contact Information

Contractor Owner-Builder       ,
Engineer Espino, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/18/2018 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 1/3/2019 Approved FREDDIE RIVERA
Deputy Reinf. Concrete 1/4/2019 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 2/8/2019 Partial Inspection FREDDIE RIVERA
Green Building Rough 2/8/2019 Not Ready for Inspection FREDDIE RIVERA
Drywall Nailing 2/21/2019 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/21/2019 Approved FREDDIE RIVERA
Green Building Rough 2/21/2019 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/26/2019 Conditional Approval FREDDIE RIVERA
Special/Order Compliance 9/9/2019 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/12/2019 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 9/12/2019 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 9/12/2019 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 9/12/2019 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 9/12/2019 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 9/18/2019 Approved FREDDIE RIVERA
HVAC-Rough 9/18/2019 Approved FREDDIE RIVERA
PLUMBING-Rough 9/18/2019 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/24/2019 Approved FREDDIE RIVERA
Green Building Rough 10/24/2019 Approved FREDDIE RIVERA
Insulation 10/24/2019 Approved FREDDIE RIVERA
Drywall Nailing 10/30/2019 Approved JOAQUIN GREENOUGH
Pre-Inspection 2/19/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 2/28/2020 Partial Approval FREDDIE RIVERA
ELECTRICAL-Final 7/13/2021 Approved FREDDIE RIVERA
HVAC-Final 7/13/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 7/13/2021 Not Ready for Inspection FREDDIE RIVERA
Final 4/17/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/17/2023 Approved ENRIQUE MIRELES
HVAC-Final 4/17/2023 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 4/17/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/17/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 4/17/2023 Approved ENRIQUE MIRELES
Final 4/26/2023 Corrections Issued ENRIQUE MIRELES
Final 8/9/2023 OK to Issue CofO ENRIQUE MIRELES