1648-1650 W 57TH ST 90062
Certificate Information: 1648-1650 W 57TH ST 90062
- Application / Permit
- 18014-10000-04213
- Plan Check / Job No.
- B18LA15277
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW PATIO ADDITION AT REAR OF EXISTING 1-STORY DUPLEX. SCOPE TO ALSO INCLUDE THE CONVERSION OF A CLOSET TO BATHROOM AND CONVERSION OF (E) BATHROOM TO BEDROOM. *** SEE COMMENTS ***
- Permit Issued
- Issued on 9/10/2018
- Issuing Office
- Metro
- Current Status
- Issued on 9/10/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2018 | AUNG SOE |
| Corrections Issued | 7/25/2018 | AUNG SOE |
| Issued | 9/10/2018 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2018 | STEVE MELGAR |
| Housing rent stabilization | Cleared | 9/10/2018 | STEVEN HOFSTAD |
| Roof/Waste drainage to street | Cleared | 9/10/2018 | STEVE MELGAR |
| Sewer availability | Cleared | 9/10/2018 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/30/2018 | Corrections Issued | VICTOR PUKHALSKY |
| PLUMBING-Rough | 12/4/2018 | Approved | VICTOR PUKHALSKY |
| Pre-Inspection | 8/9/2019 | Partial Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 10/1/2024 | Corrections Issued | CRAIG DAVIS |
| Insulation | 10/29/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 4/15/2025 | No Access for Inspection | BARRY HACHE |
| Smoke Detectors | 4/15/2025 | No Access for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 9/24/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| Final | 9/24/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 9/24/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 9/24/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 9/29/2025 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 9/29/2025 | Approved | BARRY HACHE |
| HVAC-Final | 9/29/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 9/29/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 9/29/2025 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 9/29/2025 | Corrections Issued | BARRY HACHE |
| Final | 11/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 11/24/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |