2607 N ARMSTRONG AVE 90039
Certificate Information: 2607 N ARMSTRONG AVE 90039
- Application / Permit
- 18014-10000-04187
- Plan Check / Job No.
- B18LA15154
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 33'X38'IRREGULAR ADDITION TO EXISTING SINGLE FAMILY DWELLING TO ADD (2) NEW BEDROOMS AND (2)BATHROOMS. RECONFIGURE LOWER LEVEL TO ADD (1) PARKING SPACE TO EXISTING ATTACHED GARAGE
- Permit Issued
- Issued on 6/3/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2018 | GEORGE ALVAREZ |
| Corrections Issued | 9/24/2018 | GEORGE ALVAREZ |
| Quality Review Completed | 9/26/2018 | MICHAEL PEREZ |
| Plan Check Approved | 6/3/2019 | GEORGE ALVAREZ |
| Issued | 6/3/2019 | LADBS |
| CofO in Progress | 6/10/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 7/2/2021 | DEROLD HAUFF |
| CofO Issued | 7/2/2021 | DEROLD HAUFF |
| Permit Finaled | 7/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 1/31/2019 | KHEDER ALRAZAA |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2019 | ZIXUAN CHEN |
| Hydrant and Access approval | Cleared | 2/14/2019 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 2/14/2019 | ZIXUAN CHEN |
| Sewer availability | Cleared | 2/14/2019 | ZIXUAN CHEN |
| Low Impact Development | Cleared | 3/13/2019 | MITESH PATEL |
| Excavation more than 5-ft deep | Cleared | 6/3/2019 | CALOSHA APPROVED |
Contact Information
| Architect | Formation, Association; Lic. No.: C35342 | 722 PARKMAN LOS ANGELES, CA 90026 |
| Contractor | Ruelas Anguiano Salvador; Lic. No.: 1029616-B | 3925 GUARDIA AVE LOS ANGELES, CA 90032 |
| Engineer | Ibarra,, Marco Antonio; Lic. No.: C74010 | 16 N MARENGON AVE STE 604 PASADENA, CA 91101 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/3/2019 | Corrections Issued | BRAD BESCOS |
| Footing/Foundation/Slab | 9/3/2019 | Not Ready for Inspection | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 9/17/2019 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 9/20/2019 | No Access for Inspection | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 10/16/2019 | Partial Approval | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 10/21/2019 | Partial Approval | BRAD BESCOS |
| Footing/Foundation/Slab | 10/25/2019 | Partial Approval | BRAD BESCOS |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2020 | Partial Approval | HORACE FULTZ |
| Deputy Wood Construction | 2/10/2020 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 3/11/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2020 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/31/2020 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Rough | 3/31/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/22/2020 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 4/22/2020 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 4/22/2020 | Conditional Approval | JOSEPH MCGARRY |
| Insulation | 4/30/2020 | Conditional Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 5/5/2020 | Corrections Issued | JOSEPH MCGARRY |
| Drywall Nailing | 5/7/2020 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/9/2020 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 7/14/2020 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 10/14/2020 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/14/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/12/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/15/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 1/15/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/1/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 2/23/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/27/2021 | Approved | JOSEPH MCGARRY |
| Final | 5/27/2021 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 5/27/2021 | Approved | JOSEPH MCGARRY |
| Green Building Final | 5/27/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 5/27/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 5/27/2021 | Approved | JOSEPH MCGARRY |
| Final | 6/8/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |