1352-1354 E 23RD ST 90011
Certificate Information: 1352-1354 E 23RD ST 90011
- Application / Permit
- 18014-10000-04074
- Plan Check / Job No.
- B18LA14652
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT 2 STORY SFD INTO 2 UNITS; ADD 519 SF ON GROUND FLOOR
- Permit Issued
- Issued on 5/16/2019
- Issuing Office
- Metro
- Current Status
- Issued on 5/16/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/18/2018 | APPLICANT |
| Green Plans Picked Up | 8/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2018 | MONICA RAMIREZ |
| Corrections Issued | 9/6/2018 | MONICA RAMIREZ |
| Quality Review Completed | 9/21/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 9/24/2018 | APPLICANT |
| Plan Check Approved | 1/3/2019 | MONICA RAMIREZ |
| Issued | 5/16/2019 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 10/4/2018 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2018 | STEVE MELGAR |
| Sewer availability | Cleared | 10/4/2018 | STEVE MELGAR |
| Green Code | Cleared | 12/19/2018 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 12/31/2018 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/31/2018 | JEANETTE VONG |
Contact Information
| Architect | , ; Lic. No.: C12562 | 1431 HUNTINGTON DR #201 SOUNTH PASADENA, CA 91030 |
| Contractor | Wray'S Electric & Construction Service; Lic. No.: 467678-B | P O BOX 50976 PASADENA, CA 91115 |
| Engineer | Yenjai, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
| Engineer | Zhong, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/25/2019 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/5/2019 | Approved | VICTOR PUKHALSKY |
| ELECTRICAL-Rough | 11/18/2019 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 11/18/2019 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 11/18/2019 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 12/13/2019 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2019 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 12/13/2019 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 12/13/2019 | Conditional Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 12/13/2019 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2019 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 12/18/2019 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 12/18/2019 | Conditional Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 12/18/2019 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/28/2020 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 6/18/2020 | Conditional Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 6/18/2020 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/22/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 6/22/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 7/13/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/13/2020 | Approved | SABAS ALONSO |
| Service/Power Release | 7/12/2021 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 11/9/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| HVAC-Final | 11/9/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/22/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 11/22/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 11/22/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 11/22/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 11/22/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/12/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Final | 7/12/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 7/12/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/12/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 7/12/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/23/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 1/23/2023 | Corrections Issued | BRENDAN MORELLI |
| Final | 1/23/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 1/23/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 1/23/2023 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/23/2023 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 1/23/2023 | Approved | BRENDAN MORELLI |
| Green Building Final | 4/4/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 4/4/2023 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 4/4/2023 | SGSOV Not Ready | BRENDAN MORELLI |
| Final | 4/13/2023 | No Access for Inspection | BRENDAN MORELLI |
| Green Building Final | 4/13/2023 | No Access for Inspection | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 4/13/2023 | SGSOV Not Ready | BRENDAN MORELLI |
| Final | 4/19/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Final | 4/19/2023 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Approved | BRENDAN MORELLI |
| Final | 5/7/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/7/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/21/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/21/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/26/2026 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 5/26/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/1/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/1/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/1/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/1/2026 | Approved | ALEJANDRO DE ARTOLA |