3916 N GLENRIDGE DR 91423
Certificate Information: 3916 N GLENRIDGE DR 91423
- Application / Permit
- 18014-10000-04022
- Plan Check / Job No.
- B18LA14450
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO SINGLE FAMILY DWELLING ON SINGLE STORY. ADD AND REMODEL 2 BEDROOMS, ADD 2 NEW BATHS, AND RELOCATE KITCHEN.
- Permit Issued
- Issued on 3/19/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2018 | APPLICANT |
| Green Plans Picked Up | 7/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2018 | KEVIN MORALES |
| Corrections Issued | 8/20/2018 | KEVIN MORALES |
| Quality Review Completed | 8/24/2018 | DAVID CHANG |
| Building Plans Picked Up | 8/27/2018 | APPLICANT |
| Applicant returned to address corrections | 9/26/2018 | KEVIN MORALES |
| Plan Check Approved | 2/20/2019 | KEVIN MORALES |
| Issued | 3/19/2019 | LADBS |
| CofO in Progress | 11/15/2024 | MISAEL ESPARZA |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
| CofO Issued | 1/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/1/2019 | JEANETTE VONG |
| Green Code | Cleared | 2/8/2019 | NEGAR NEJAD |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2019 | KARAN PATEL |
| Low Impact Development | Cleared | 2/19/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/19/2019 | KARAN PATEL |
| Grading Pre-Inspection | Cleared | 2/20/2019 | KEVIN MORALES |
Contact Information
| Contractor | J & A Construction; Lic. No.: 753365-B | 8993 BOWMAN AVE SOUTH GATE, CA 90280 |
| Engineer | Rahman, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 7/2/2019 | Conditional Approval | THOMAS FINNILA |
| Pre-Inspection | 6/4/2020 | Approved | CHARLES POWELL |
| Deputy Reinf. Concrete | 10/4/2022 | Conditional Approval | MISAEL ESPARZA |
| Deputy Reinf. Concrete | 10/17/2022 | Conditional Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 3/24/2023 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 5/12/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 5/12/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 5/12/2023 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 5/22/2023 | Corrections Issued | DAVID MATSON |
| PLUMBING-Rough | 5/22/2023 | Corrections Issued | DAVID MATSON |
| HVAC-Rough | 5/26/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 5/26/2023 | Approved | JOHN COLEMAN |
| Insulation | 9/8/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/8/2023 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 9/8/2023 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 9/19/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 10/6/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 10/11/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 10/11/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/12/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/12/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 8/12/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/12/2024 | Approved | MISAEL ESPARZA |
| Green Building Final | 8/12/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 8/12/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 8/12/2024 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 8/12/2024 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 8/12/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/21/2024 | Corrections Issued | MISAEL ESPARZA |
| Final | 10/21/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 10/21/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 10/21/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 10/21/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 10/21/2024 | Approved | MISAEL ESPARZA |
| Final | 10/30/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 11/14/2024 | OK to Issue CofO | MISAEL ESPARZA |