167 N MARTEL AVE 90036

Certificate Information: 167 N MARTEL AVE 90036

Application / Permit
18014-10000-04001
Plan Check / Job No.
B18LA14376
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 2ND STORY REC ROOM (438 SF) ON TOP OF (E) GARAGE.
Permit Issued
Issued on 3/26/2019
Issuing Office
Metro
Current Status
Issued on 3/26/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/13/2018 APPLICANT
Assigned to Plan Check Engineer 8/16/2018 DEVIN GORDON
Corrections Issued 8/20/2018 DEVIN GORDON
Quality Review Completed 8/22/2018 DAVID CHANG
Building Plans Picked Up 8/27/2018 APPLICANT
Green Plans Picked Up 8/27/2018 APPLICANT
Plan Check Approved 2/26/2019 DEVIN GORDON
Issued 3/26/2019 LADBS

Permit Application Clearance Information

HPOZ Cleared 12/7/2018 MICAELA TORRES-GIL
Miscellaneous Cleared 12/7/2018 MICAELA TORRES-GIL
Miscellaneous Cleared 12/7/2018 MICAELA TORRES-GIL
Miscellaneous Cleared 12/7/2018 MICAELA TORRES-GIL
CPC Cleared 1/25/2019 ANNA VAN
Eng Process Fee Ord 176,300 Cleared 1/25/2019 ZIXUAN CHEN
Roof/Waste drainage to street Cleared 1/25/2019 ZIXUAN CHEN
Abandoned oil well Cleared 2/8/2019 GEORGE SUCHAND
Abandoned oil well approval Cleared 2/8/2019 GEORGE SUCHAND
Sewer availability Cleared 2/8/2019 ZIXUAN CHEN
Green Code Cleared 2/14/2019 NEGAR NEJAD

Contact Information

Contractor Owner-Builder       ,
Engineer Li, Dacheng David; Lic. No.: C58075 23240 RIDGELINE DR      DIAMOND BAR, CA 91765

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/19/2020 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 6/19/2020 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/25/2020 Approved CHRIS CHRISTENSEN
METHANE-Barrier 6/25/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 6/25/2020 Approved CHRIS CHRISTENSEN
Deputy Wood Construction 10/16/2020 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 5/10/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/10/2021 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/21/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 5/21/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 5/21/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/21/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/4/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/10/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 6/10/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/10/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/30/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/28/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 2/28/2022 Approved CHRIS CHRISTENSEN
METHANE-Rough 2/28/2022 Approved CHRIS CHRISTENSEN
Sewer 4/26/2022 Approved ADAM ESCOTO
Insulation 7/15/2022 Approved ADAM ESCOTO
Drywall Nailing 8/5/2022 Approved MICHAEL LEWIS
Pre-Inspection 1/29/2024 Partial Inspection LILIANA PORTILLO
Shower Pan 1/31/2024 Partial Approval AMIR NAZARIAN
ELECTRICAL-Final 6/4/2024 Corrections Issued AMIR NAZARIAN
Insulation 6/21/2024 Approved AMIR NAZARIAN
Drywall Nailing 6/27/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 6/27/2024 Not Ready for Inspection AMIR NAZARIAN
Final 1/21/2025 Corrections Issued JOSE MACIAS
Green Building Final 1/21/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Approved JOSE MACIAS
Smoke Detectors 1/21/2025 Approved JOSE MACIAS
Final 2/21/2025 Corrections Issued JOSE MACIAS
Final 3/27/2025 Conditional Approval JOSE MACIAS
Pre-Inspection 5/30/2025 Partial Inspection RAUL BARAJAS
Special/Order Compliance 5/30/2025 Corrections Issued JOSE MACIAS