2811 W WAVERLY DR 90039
Certificate Information: 2811 W WAVERLY DR 90039
- Application / Permit
- 18014-10000-03973
- Plan Check / Job No.
- B18LA14255
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- 18' X 67'9" ADDITION AND MAJOR REMODEL TO (E) 2 STORY 6 UNIT APARTMENT BUILDING.
- Permit Issued
- Issued on 9/19/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 8/13/2018 | APPLICANT |
| Green Plans Picked Up | 8/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2018 | HERNAN ARREOLA |
| Corrections Issued | 8/27/2018 | HERNAN ARREOLA |
| Quality Review Completed | 9/7/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 9/11/2018 | APPLICANT |
| Plan Check Approved | 9/19/2019 | HERNAN ARREOLA |
| Issued | 9/19/2019 | LADBS |
| CofO in Progress | 9/22/2022 | JONATHAN QUACH |
| Permit Finaled | 9/22/2022 | ERNESTO CORRAL |
| CofO Issued | 9/22/2022 | ERNESTO CORRAL |
| Permit Finaled | 9/22/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 10/24/2018 | NEGAR NEJAD |
| Miscellaneous | Cleared | 10/24/2018 | YOVANA PEREZ |
| ZI | Cleared | 10/24/2018 | YOVANA PEREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2018 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 10/30/2018 | GEORGE SUCHAND |
| Sewer availability | Cleared | 10/30/2018 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 3/4/2019 | SOPHIE GABEL-SCHEINBAU |
| Low Impact Development | Cleared | 7/11/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/26/2019 | JEANETTE VONG |
| Miscellaneous | Cleared | 9/16/2019 | SARAH GOLDMAN |
Contact Information
| Architect | Williams, Gregory Keith; Lic. No.: C22965 | 1218 S LONGWOOD AVENUE LOS ANGELES, CA 90019 |
| Contractor | Owner-Builder | , |
| Engineer | Mani, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 11/12/2019 | Conditional Approval | GRANT WOODS |
| Piling/Pier/Caisson | 11/18/2019 | Corrections Issued | GRANT WOODS |
| Deputy Reinf. Concrete | 11/22/2019 | Approved | GRANT WOODS |
| Piling/Pier/Caisson | 11/22/2019 | Partial Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 12/17/2019 | Corrections Issued | GRANT WOODS |
| Deputy Reinf. Concrete | 12/18/2019 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 2/21/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Reinf. Masonry | 2/26/2020 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 3/3/2020 | Conditional Approval | DANIEL COLLINS |
| Green Building Rough | 3/3/2020 | Approved | DANIEL COLLINS |
| Verify Sprinkler Sign Off | 3/3/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Wood Frame | 3/3/2020 | Partial Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2020 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 3/20/2020 | Partial Approval | DANIEL COLLINS |
| Verify Sprinkler Sign Off | 3/20/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Wood Frame | 3/20/2020 | Partial Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2020 | Partial Approval | DANIEL COLLINS |
| Verify Sprinkler Sign Off | 3/31/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Wood Frame | 3/31/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Wood Construction | 4/1/2020 | Conditional Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2020 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 9/15/2020 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Insulation | 10/14/2020 | Approved | RUSSELL BONVOULOIR |
| Deputy Wood Construction | 10/19/2020 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Approved | RUSSELL BONVOULOIR |
| Verify Sprinkler Sign Off | 10/22/2020 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 10/22/2020 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 10/30/2020 | Approved | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 10/30/2020 | Approved | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 12/16/2020 | Approved | RUSSELL BONVOULOIR |
| Pre-Inspection | 3/18/2021 | Approved | RUSSELL BONVOULOIR |
| Piling/Pier/Caisson | 3/25/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Piling/Pier/Caisson | 4/19/2021 | Partial Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 6/7/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 8/4/2021 | Partial Approval | BRUCE CAMPBELL |
| Masonry Wall/Backfill | 8/19/2021 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Not Ready | TED RIES |
| Final | 4/29/2022 | Partial Inspection | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 4/29/2022 | Approved | BRUCE CAMPBELL |
| Green Building Final | 4/29/2022 | Approved | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV Not Required | BRUCE CAMPBELL |
| Smoke Detectors | 4/29/2022 | Partial Approval | BRUCE CAMPBELL |
| Structural Steel Frame | 4/29/2022 | Approved | BRUCE CAMPBELL |
| Final | 5/4/2022 | Corrections Issued | JONATHAN QUACH |
| Smoke Detectors | 5/4/2022 | Approved | JONATHAN QUACH |
| Final | 6/2/2022 | Partial Inspection | JONATHAN QUACH |
| Final | 9/22/2022 | OK to Issue CofO | JONATHAN QUACH |