3246-3248 N PRIMERA AVE 90068

Certificate Information: 3246-3248 N PRIMERA AVE 90068

Application / Permit
18014-10000-03958
Plan Check / Job No.
B18LA14216
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW ACCESORY DWELLING UNTIL ADDITION TO AN EXISTING 2-STORY SINGLE FAMILY RESIDENCE
Permit Issued
Issued on 4/11/2019
Issuing Office
Metro
Current Status
CofO Issued on 4/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2018 APPLICANT
Assigned to Plan Check Engineer 8/7/2018 ERIC WONG
Green Plans Picked Up 8/7/2018 APPLICANT
Corrections Issued 8/8/2018 ERIC WONG
Quality Review Completed 8/9/2018 GARO TELMI
Building Plans Picked Up 8/14/2018 APPLICANT
Plan Check Approved 2/20/2019 ERIC WONG
Issued 4/11/2019 LADBS
CofO in Progress 6/11/2021 BRIAN SULLIVAN
Permit Finaled 4/1/2023 DANIEL ORRANTE
CofO Issued 4/1/2023 DANIEL ORRANTE
Permit Finaled 4/1/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/16/2018 KARAN PATEL
Roof/Waste drainage to street Cleared 8/16/2018 KARAN PATEL
Sewer availability Cleared 8/16/2018 KARAN PATEL
Street width determination Cleared 8/16/2018 KARAN PATEL
Specific Plan Cleared 10/25/2018 DOMINICK ORTIZ
Grading Pre-Inspection Cleared 12/14/2018 ERIC WONG
Green Code Cleared 12/14/2018 NEGAR NEJAD
Address approval Cleared 2/8/2019 ADRIAN SANCHEZ

Contact Information

Contractor Best Builders & Development Inc; Lic. No.: 850444-B 15260 VENTURA BLVD STE 1200      SHERMAN OAKS, CA 91403
Engineer Russell,, Mark Lewis; Lic. No.: GE2393 2122 E WALNUT STREET STE 200      PASADENA, CA 91107
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/22/2019 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 5/31/2019 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/24/2019 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 6/28/2019 Partial Approval BRIAN SULLIVAN
Grading Pre-Inspection 6/28/2019 Partial Inspection BRIAN SULLIVAN
Masonry Wall/Backfill 6/28/2019 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 7/8/2019 Partial Approval BRIAN SULLIVAN
Masonry Wall/Backfill 7/8/2019 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 8/1/2019 Partial Inspection ROBERT CORNELL
Sewer 8/1/2019 Partial Inspection ROBERT CORNELL
Footing/Foundation/Slab 8/7/2019 Approved BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 9/20/2019 No Access for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 9/24/2019 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 9/24/2019 Corrections Issued BRIAN SULLIVAN
Green Building Rough 9/24/2019 Approved BRIAN SULLIVAN
MERV13>=Rough 9/24/2019 Approved BRIAN SULLIVAN
PLUMBING-Rough 9/24/2019 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 10/28/2019 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 10/28/2019 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 10/28/2019 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 12/4/2019 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 12/4/2019 Approved BRIAN SULLIVAN
PLUMBING-Rough 12/4/2019 Approved BRIAN SULLIVAN
Insulation 12/12/2019 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 12/12/2019 Approved BRIAN SULLIVAN
Shower Pan 12/12/2019 Approved BRIAN SULLIVAN
Drywall Nailing 12/16/2019 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 12/20/2019 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 2/20/2020 Approved BRIAN SULLIVAN
Final 2/20/2020 Corrections Issued BRIAN SULLIVAN
Green Building Final 2/20/2020 Not Ready for Inspection BRIAN SULLIVAN
MERV13>=Final 2/20/2020 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/20/2020 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 2/20/2020 Approved BRIAN SULLIVAN
Final 2/23/2021 Corrections Issued BRIAN SULLIVAN
Green Building Final 2/23/2021 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/23/2021 SGSOV Approved BRIAN SULLIVAN
Final 6/1/2021 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 6/1/2021 Not Ready for Inspection BRIAN SULLIVAN
Final 6/10/2021 OK to Issue CofO BRIAN SULLIVAN
Green Building Final 6/10/2021 Approved BRIAN SULLIVAN