413 W 105TH ST 90003

Certificate Information: 413 W 105TH ST 90003

Application / Permit
18014-10000-03801
Plan Check / Job No.
B18LA13683
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 10'-9" X 9'-10" TRELLIS AND CONVERT 24'-3" X 18'-1" GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 11/6/2018
Issuing Office
Metro
Current Status
CofO Issued on 12/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2018 APPLICANT
Assigned to Plan Check Engineer 8/2/2018 MICHAEL PEREZ
Corrections Issued 8/6/2018 MICHAEL PEREZ
Quality Review Completed 8/6/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 8/20/2018 APPLICANT
Green Plans Picked Up 8/20/2018 APPLICANT
Plan Check Approved 11/6/2018 RAHEL BEYENE
Issued 11/6/2018 LADBS
CofO in Progress 11/30/2020 ANSON MAGLASANG
Permit Finaled 12/2/2020 DEROLD HAUFF
CofO Issued 12/2/2020 DEROLD HAUFF
Permit Finaled 12/2/2020 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 10/29/2018 COLIN LOREDO
Address approval Cleared 10/30/2018 STEVE MELGAR
CPC Cleared 10/30/2018 DIANA JIMENEZ
Eng Process Fee Ord 176,300 Cleared 10/30/2018 STEVE MELGAR
Sewer availability Cleared 11/5/2018 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Noe,, Juan Gabriel; Lic. No.: C72822 390 E SAN YSIDRO BLVD PMB 26      SAN YSIDRO, CA 92173

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/30/2019 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 7/30/2019 Approved EUGENE CASSIDY
PLUMBING-Rough 8/5/2019 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 8/29/2019 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/23/2019 Not Ready for Inspection WILLIAM ROSE
Rough-Elec/Plmb/HVAC 10/23/2019 Partial Approval WILLIAM ROSE
Wood Frame 10/23/2019 Not Ready for Inspection WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 10/29/2019 Partial Approval WILLIAM ROSE
BUILDING-Rough-Frame 11/22/2019 Partial Approval WILLIAM ROSE
Green Building Rough 11/22/2019 Approved WILLIAM ROSE
MERV13>=Rough 11/22/2019 Approved WILLIAM ROSE
HVAC-Rough 12/4/2019 Conditional Approval WILLIAM ROSE
Insulation 12/4/2019 Conditional Approval WILLIAM ROSE
Interior/Exterior Lathing 12/4/2019 Not Ready for Inspection WILLIAM ROSE
Shower Pan 12/4/2019 Approved WILLIAM ROSE
HVAC-Rough 12/13/2019 Approved JOHN KLARIN
Drywall Nailing 12/30/2019 Approved JOHN KLARIN
Interior/Exterior Lathing 12/30/2019 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/18/2020 Approved JOHN KLARIN
Final 2/18/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 2/18/2020 Not Ready for Inspection JOHN KLARIN
MERV13>=Final 2/18/2020 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 2/18/2020 SGSOV Not Required JOHN KLARIN
Shower Pan 2/18/2020 Approved JOHN KLARIN
Smoke Detectors 2/18/2020 Not Ready for Inspection JOHN KLARIN
Final 9/22/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 9/22/2020 Corrections Issued EUGENE CASSIDY
MERV13>=Final 9/22/2020 Approved EUGENE CASSIDY
Smoke Detectors 9/22/2020 Approved EUGENE CASSIDY
Final 10/20/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 10/20/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 10/29/2020 Approved EUGENE CASSIDY
Final 10/29/2020 Corrections Issued EUGENE CASSIDY
Gas Test 10/29/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 10/29/2020 Approved EUGENE CASSIDY
HVAC-Final 10/29/2020 Approved EUGENE CASSIDY
PLUMBING-Final 10/29/2020 Approved EUGENE CASSIDY
Service/Power Release 10/29/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 11/6/2020 Approved EUGENE CASSIDY
Final 11/6/2020 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 11/6/2020 Approved EUGENE CASSIDY
PLUMBING-Final 11/6/2020 Corrections Issued EUGENE CASSIDY
Service/Power Release 11/6/2020 Not Ready for Inspection EUGENE CASSIDY
Final 11/13/2020 OK to Issue CofO EUGENE CASSIDY
PLUMBING-Final 11/13/2020 Approved EUGENE CASSIDY