6190 E ROY ST 90042
Certificate Information: 6190 E ROY ST 90042
- Application / Permit
- 18014-10000-03719
- Plan Check / Job No.
- B18LA13392
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 34' X 19'-6" (1) STORY ADDITION TO CREATE NEW BEDROOM AND BATHROOM AND REMODEL TO EXISTING DWELLING. WORK PER ENG.
- Permit Issued
- Issued on 11/1/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 7/2/2018 | APPLICANT |
Green Plans Picked Up | 7/13/2018 | APPLICANT |
Assigned to Plan Check Engineer | 8/2/2018 | MICHAEL PEREZ |
Corrections Issued | 8/6/2018 | MICHAEL PEREZ |
Quality Review Completed | 8/6/2018 | SIAVOSH POURSABAHIAN |
Building Plans Picked Up | 8/17/2018 | APPLICANT |
Plan Check Approved | 10/12/2018 | MICHAEL PEREZ |
Issued | 11/1/2018 | LADBS |
CofO in Progress | 2/22/2022 | COREY HUPP |
Permit Finaled | 3/2/2022 | DEROLD HAUFF |
CofO Issued | 3/2/2022 | DEROLD HAUFF |
Permit Finaled | 3/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
BHO/Hillside ordinance | Cleared | 8/23/2018 | STEVE MELGAR |
BHO/Hillside ordinance | Cleared | 8/23/2018 | STEVE MELGAR |
BHO/Hillside ordinance | Cleared | 8/23/2018 | STEVE MELGAR |
Sewer availability | Cleared | 8/23/2018 | STEVE MELGAR |
Green Code | Cleared | 9/25/2018 | DONALD CRICHLOW |
Excavation more than 5-ft deep | Cleared | 10/1/2018 | CALOSHA APPROVED |
GPI Written Notices | Cleared | 10/1/2018 | MICHAEL PEREZ |
Grading Pre-Inspection | Cleared | 10/1/2018 | MICHAEL PEREZ |
Eng Process Fee Ord 176,300 | Cleared | 10/9/2018 | CELINA MORENO |
Low Impact Development | Cleared | 10/9/2018 | MITESH PATEL |
Roof/Waste drainage to street | Cleared | 10/9/2018 | CELINA MORENO |
Contact Information
Contractor | Owner-Builder | , |
Inspector Information
CRAIG DAVIS, (213) 202-3124 | Office Hours: 7:00-8:00 AM MON-FRI |
DAVID WILLIAMS, (213) 202-3124 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Excavation/Setback/Form/Re-Bar | 5/24/2019 | Partial Approval | ENRIQUE MIRELES |
Piling/Pier/Caisson | 5/24/2019 | Approved | ENRIQUE MIRELES |
Footing/Foundation/Slab | 6/13/2019 | Partial Approval | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 12/13/2019 | Approved | ENRIQUE MIRELES |
Pre-Inspection | 12/13/2019 | Approved | ENRIQUE MIRELES |
Deputy Reinf. Concrete | 12/20/2019 | Approved | ENRIQUE MIRELES |
Footing/Foundation/Slab | 1/15/2020 | Approved | ENRIQUE MIRELES |
Deputy Reinf. Concrete | 1/24/2020 | Approved | ENRIQUE MIRELES |
Deputy Wood Construction | 3/24/2020 | Approved | ENRIQUE MIRELES |
Wood Frame | 3/26/2020 | Approved | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 4/30/2020 | Approved | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 5/8/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
Excavation/Setback/Form/Re-Bar | 5/12/2020 | Corrections Issued | ENRIQUE MIRELES |
Masonry Wall/Backfill | 5/28/2020 | No Access for Inspection | HAMIK HARTOUNIAN |
Masonry Wall/Backfill | 5/29/2020 | Partial Approval | CRAIG VAUGHAN |
Rough-Elec/Plmb/HVAC | 6/4/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
PLUMBING-Rough | 6/10/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
PLUMBING-Rough | 6/12/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
PLUMBING-Rough | 8/25/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
Floor/Roof Diaphrgm/Shear Wall | 9/1/2020 | Partial Approval | HAMIK HARTOUNIAN |
Underground Mechanical | 9/1/2020 | Approved | HAMIK HARTOUNIAN |
Floor/Roof Diaphrgm/Shear Wall | 9/15/2020 | Partial Approval | CRAIG VAUGHAN |
PLUMBING-Rough | 9/15/2020 | Partial Approval | CRAIG VAUGHAN |
Deputy Wood Construction | 10/7/2020 | No Access for Inspection | ELMER BLAND |
Green Building Rough | 11/30/2020 | Not Ready for Inspection | COREY HUPP |
Rough-Elec/Plmb/HVAC | 11/30/2020 | Corrections Issued | COREY HUPP |
ELECTRICAL-Rough | 12/7/2020 | Approved | COREY HUPP |
PLUMBING-Rough | 12/7/2020 | Approved | COREY HUPP |
BUILDING-Rough-Frame | 2/16/2021 | Approved | COREY HUPP |
Green Building Rough | 2/16/2021 | Approved | COREY HUPP |
Insulation | 2/25/2021 | Not Ready for Inspection | COREY HUPP |
Interior/Exterior Lathing | 2/25/2021 | Partial Approval | COREY HUPP |
Insulation | 3/4/2021 | Partial Approval | COREY HUPP |
Drywall Nailing | 4/3/2021 | Corrections Issued | JOAQUIN GREENOUGH |
Service/Power Release | 4/3/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
Shower Pan | 8/18/2021 | Corrections Issued | ASHLEY THOMPSON |
Interior/Exterior Lathing | 8/24/2021 | Approved | COREY HUPP |
Shower Pan | 8/24/2021 | Approved | COREY HUPP |
Drywall Nailing | 1/5/2022 | Approved | SCOTT FINNILA |
Final | 1/5/2022 | Corrections Issued | SCOTT FINNILA |
Green Building Final | 1/5/2022 | Approved | SCOTT FINNILA |
Reinforced Concrete Frame | 1/5/2022 | Approved | SCOTT FINNILA |
SGSOV-Seismic Gas S/O Valve | 1/5/2022 | SGSOV Approved | SCOTT FINNILA |
Smoke Detectors | 1/5/2022 | Corrections Issued | SCOTT FINNILA |
Final | 2/22/2022 | OK to Issue CofO | COREY HUPP |
Smoke Detectors | 2/22/2022 | Approved | COREY HUPP |