6523 W OLYMPIC BLVD 90048
Certificate Information: 6523 W OLYMPIC BLVD 90048
- Application / Permit
- 18014-10000-03545
- Plan Check / Job No.
- B18LA12697
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 18' X 18'-9" REAR ADDITION AND MAJOR INTERIOR REMODEL AT EXISTING 1-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 6/16/2020
- Issuing Office
- Current Status
- CofO Issued on 10/7/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2018 | APPLICANT |
| Green Plans Picked Up | 8/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2018 | YAQUB MIRZA |
| Corrections Issued | 8/22/2018 | YAQUB MIRZA |
| Quality Review Completed | 8/30/2018 | HERNAN ARREOLA |
| Building Plans Picked Up | 8/31/2018 | APPLICANT |
| Applicant returned to address corrections | 3/9/2020 | YAQUB MIRZA |
| Plan Check Approved | 4/17/2020 | SERGIO MUNIZ |
| Issued | 6/16/2020 | APPLICANT |
| CofO in Progress | 9/9/2020 | ARTHUR SARGSYAN |
| CofO in Progress | 9/9/2020 | ARTHUR SARGSYAN |
| Permit Finaled | 10/7/2020 | DEROLD HAUFF |
| CofO Issued | 10/7/2020 | DEROLD HAUFF |
| Permit Finaled | 10/7/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2018 | STEVE MELGAR |
| Sewer availability | Cleared | 9/17/2018 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 3/9/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 3/18/2020 | KHEDER ALRAZAA |
| HPOZ | Cleared | 4/10/2020 | JONATHAN KAPLAN |
Contact Information
| Contractor | Los Angeles Construction & Development; Lic. No.: 1035079-B | 6523 W OLYMPIC BLVD LOS ANGELES, CA 90048 |
| Engineer | Kim, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/22/2020 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 7/22/2020 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 7/22/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/29/2020 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 7/29/2020 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 7/29/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 7/29/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 7/29/2020 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 7/29/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 7/30/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 7/30/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/30/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 8/3/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 8/27/2020 | Corrections Issued | COREY HUPP |
| Green Building Final | 8/27/2020 | Approved | COREY HUPP |
| HVAC-Final | 8/27/2020 | Approved | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 8/27/2020 | SGSOV Not Ready | COREY HUPP |
| Smoke Detectors | 8/27/2020 | Not Ready for Inspection | COREY HUPP |
| Final | 9/9/2020 | OK to Issue CofO | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/9/2020 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 9/9/2020 | Approved | ARTHUR SARGSYAN |