1031 S BROADWAY 90015
Certificate Information: 1031 S BROADWAY 90015
- Application / Permit
- 18014-10000-03497
- Plan Check / Job No.
- B18LA12488
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- NEW APPROXIMATELY 2,008 S.F. BASKETBALL COURT & 2,700 S.F. ROOF DECK ON AN EXISTING 12-STORY OFFICE BUILDING + NEW ELEVATOR FROM 12TH FLOOR TO ROOF DECK & CORRIDOR EXTENSION TO ELEVATOR ON THE 12TH FLOOR. + NEW RESTROOM & STORAGE ROOM ADDITION
- Permit Issued
- Issued on 12/20/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 6/29/2018 | APPLICANT |
| Green Plans Picked Up | 7/5/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2018 | LARRY LEE |
| Corrections Issued | 7/23/2018 | LARRY LEE |
| Quality Review Completed | 7/23/2018 | CHARLES CHANG |
| Building Plans Picked Up | 7/24/2018 | APPLICANT |
| Applicant returned to address corrections | 8/1/2018 | LARRY LEE |
| Applicant returned to address corrections | 8/7/2018 | LARRY LEE |
| Plan Check Approved | 12/18/2018 | LARRY LEE |
| Issued | 12/20/2018 | LADBS |
| CofO in Progress | 8/19/2024 | LUIS CCAMACHO |
| CofO Issued | 11/8/2024 | ERNESTO CORRAL |
| Permit Finaled | 11/8/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 7/24/2018 | DIANA JIMENEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2018 | STEVE MELGAR |
| Highway dedication | Cleared | 7/24/2018 | STEVE MELGAR |
| Miscellaneous | Cleared | 7/24/2018 | DIANA JIMENEZ |
| Project located in CRA area | Cleared | 7/24/2018 | JIM URQUHART |
| Sewer availability | Cleared | 7/24/2018 | STEVE MELGAR |
| ZA Case | Cleared | 7/24/2018 | DIANA JIMENEZ |
| ZA Case | Cleared | 7/24/2018 | DIANA JIMENEZ |
| ZA Case | Cleared | 7/24/2018 | DIANA JIMENEZ |
| ZA Case | Cleared | 7/24/2018 | DIANA JIMENEZ |
| Green Code | Cleared | 7/25/2018 | COLIN LOREDO |
| Low Impact Development | Cleared | 7/25/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/25/2018 | NAZILA NOORIFAR |
| DAS Clearance | Cleared | 7/27/2018 | WAI LAU |
| Building over 3-story or 36-ft | Cleared | 8/7/2018 | CALOSHA APPROVED |
| Fire Marshall Fire Life Safety | Cleared | 12/14/2018 | WILLIAM JOHNS |
Contact Information
| Architect | Barany,, Donald Alec; Lic. No.: C12803 | 116 26TH ST SANTA MONICA, CA 90402 |
| Contractor | Owner-Builder | , |
| Engineer | Smith,, Chris Wayne; Lic. No.: S6106 | 35 CATAMARAN ST MARINA DEL REY, CA 90292 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BAZERKANIAN, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/25/2019 | Partial Approval | DANIEL COLLINS |
| METHANE-Barrier | 1/25/2019 | Approved | DANIEL COLLINS |
| METHANE-Subgrade | 1/25/2019 | Approved | DANIEL COLLINS |
| Green Building Rough | 3/8/2019 | Approved | DANIEL COLLINS |
| METHANE-Rough | 3/8/2019 | Approved | DANIEL COLLINS |
| Reinforced Concrete Frame | 3/8/2019 | Partial Approval | DANIEL COLLINS |
| Green Building Final | 9/1/2020 | Partial Inspection | DANIEL COLLINS |
| T-Bar Ceiling | 10/28/2020 | Partial Approval | DANIEL COLLINS |
| Pre-Inspection | 2/1/2024 | Partial Inspection | KATY RAMIREZ |
| Final | 2/14/2024 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 2/14/2024 | SGSOV Approved | KATY RAMIREZ |
| Final | 2/26/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Footing/Foundation/Slab | 2/26/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Green Building Final | 2/26/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Reinforced Concrete Frame | 2/26/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Smoke Detectors | 2/26/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 6/25/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Footing/Foundation/Slab | 6/25/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Green Building Final | 6/25/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Reinforced Concrete Frame | 6/25/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Smoke Detectors | 6/25/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 6/28/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Footing/Foundation/Slab | 6/28/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Green Building Final | 6/28/2024 | Approved | LUIS CCAMACHO |
| Reinforced Concrete Frame | 6/28/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Smoke Detectors | 6/28/2024 | Approved | LUIS CCAMACHO |
| Final | 7/10/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Footing/Foundation/Slab | 7/10/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Reinforced Concrete Frame | 7/10/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 8/19/2024 | OK to Issue CofO | LUIS CCAMACHO |
| Footing/Foundation/Slab | 8/19/2024 | Approved | LUIS CCAMACHO |
| Reinforced Concrete Frame | 8/19/2024 | Approved | LUIS CCAMACHO |