6855 S LA CIENEGA BLVD 90045

Certificate Information: 6855 S LA CIENEGA BLVD 90045

Application / Permit
18014-10000-03346
Plan Check / Job No.
B18LA12009
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
NEW 211' X 151'-3" (1) STORY TYPE VB - RETAIL BUILDING. NFPA SPRINKLERS THROUGHOUT. CORE AND SHELL ONLY
Permit Issued
Issued on 11/4/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2018 APPLICANT
Disabled Access Plans Picked Up 6/26/2018 APPLICANT
Green Plans Picked Up 7/2/2018 APPLICANT
Assigned to Plan Check Engineer 7/12/2018 MICHAEL PEREZ
Corrections Issued 7/18/2018 MICHAEL PEREZ
Quality Review Completed 7/20/2018 KESETE HAREGOT
Building Plans Picked Up 7/25/2018 APPLICANT
Plan Check Approved 10/28/2019 MICHAEL PEREZ
Issued 11/4/2019 LADBS
TCO Issued (Expire Date: 04-13-2021) 10/15/2020 HENRY BAGHDASSARIAN
CofO in Progress 2/26/2021 DERRICK SPENCER
Permit Finaled 2/26/2021 HENRY BAGHDASSARIAN
CofO Issued 2/26/2021 HENRY BAGHDASSARIAN
Permit Finaled 2/26/2021 HENRY BAGHDASSARIAN

Permit Application Clearance Information

CPC Cleared 8/6/2018 NORA DRESSER
CPC Cleared 8/6/2018 NORA DRESSER
Address approval Cleared 8/29/2018 ADOLFO GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/29/2018 ADOLFO GUTIERREZ
Sewer availability Cleared 8/29/2018 ADOLFO GUTIERREZ
Hydrant and Access approval Cleared 9/13/2018 ROBERT DUFF
Miscellaneous Cleared 9/26/2018 NORA DRESSER
Prkng lot landscape/Water mgmt Cleared 9/26/2018 NORA DRESSER
Site Plan review Cleared 9/26/2018 NORA DRESSER
Tract Map conditions Cleared 9/26/2018 NORA DRESSER
DAS Clearance Cleared 9/27/2018 SHINE LIN
Food Service Establishment Cleared 10/10/2018 RAMESHBHAIR PATEL
Food establishment approval Cleared 10/10/2018 LACDHS APPROVED
ZA Case Cleared 10/10/2018 NORA DRESSER
Grading Pre-Inspection Cleared 10/24/2018 PATRICK MISCHLICH
Miscellaneous Cleared 10/29/2018 NORA DRESSER
Specific Plan Cleared 12/12/2018 PEDRO AYALA
Green Code Cleared 4/15/2019 SARAH ABOULHOSN
Low Impact Development Cleared 4/18/2019 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 4/18/2019 ELAINE LEI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

VASIL MIHALEV, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/14/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 1/15/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 1/15/2020 Approved NICK LAROCCA
Footing/Foundation/Slab 1/15/2020 Partial Approval NICK LAROCCA
METHANE-Barrier 1/15/2020 Approved NICK LAROCCA
METHANE-Subgrade 1/15/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 1/16/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 1/17/2020 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 1/17/2020 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Masonry 1/21/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 1/22/2020 Approved NICK LAROCCA
Masonry Wall/Backfill 1/22/2020 Partial Approval NICK LAROCCA
Deputy Reinf. Masonry 1/23/2020 Approved TED RIES
Masonry Wall/Backfill 1/24/2020 Partial Approval NICK LAROCCA
Deputy Reinf. Masonry 1/27/2020 Approved NICK LAROCCA
Masonry Wall/Backfill 1/27/2020 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 1/28/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 1/28/2020 Approved NICK LAROCCA
Masonry Wall/Backfill 1/28/2020 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 1/29/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 1/29/2020 Approved NICK LAROCCA
Masonry Wall/Backfill 1/29/2020 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 1/30/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 1/30/2020 Approved NICK LAROCCA
Masonry Wall/Backfill 1/30/2020 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 1/31/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 1/31/2020 Approved NICK LAROCCA
Masonry Wall/Backfill 1/31/2020 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 2/3/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/3/2020 Approved NICK LAROCCA
Masonry Wall/Backfill 2/3/2020 Not Ready for Inspection NICK LAROCCA
Deputy Drilled-In Anchors 2/4/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/4/2020 Approved NICK LAROCCA
Masonry Wall/Backfill 2/4/2020 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 2/5/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/5/2020 Approved NICK LAROCCA
Masonry Wall/Backfill 2/5/2020 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 2/6/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/6/2020 Approved NICK LAROCCA
Masonry Wall/Backfill 2/6/2020 Not Ready for Inspection NICK LAROCCA
Deputy Drilled-In Anchors 2/7/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/7/2020 Approved NICK LAROCCA
Masonry Wall/Backfill 2/7/2020 Partial Inspection NICK LAROCCA
Deputy Drilled-In Anchors 2/10/2020 Approved DERRICK SPENCER
Deputy Reinf. Masonry 2/10/2020 Approved DERRICK SPENCER
Reinforced Masonry Frame 2/10/2020 Conditional Approval JEFF BYTHEWAY
Deputy Drilled-In Anchors 2/11/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/11/2020 Approved NICK LAROCCA
Green Building Rough 2/11/2020 Approved NICK LAROCCA
METHANE-Rough 2/11/2020 Approved NICK LAROCCA
Reinforced Masonry Frame 2/11/2020 Partial Inspection NICK LAROCCA
Verify Sprinkler Sign Off 2/11/2020 Not Ready for Inspection NICK LAROCCA
Deputy Drilled-In Anchors 2/12/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/12/2020 Approved NICK LAROCCA
Deputy Drilled-In Anchors 2/21/2020 Approved NICK LAROCCA
Deputy Drilled-In Anchors 2/28/2020 Approved NICK LAROCCA
Verify Sprinkler Sign Off 3/2/2020 Approved NICK LAROCCA
Wood Frame 3/2/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 3/4/2020 Partial Inspection NICK LAROCCA
Structural Steel Frame 3/4/2020 Not Ready for Inspection NICK LAROCCA
Light Gage Steel Frame 3/5/2020 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 3/20/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 3/20/2020 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 3/26/2020 Approved NICK LAROCCA
Deputy Steel/Welding 3/26/2020 Approved NICK LAROCCA
Light Gage Steel Frame 3/27/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 4/16/2020 Not Ready for Inspection NICK LAROCCA
Deputy Drilled-In Anchors 4/17/2020 Approved NICK LAROCCA
Light Gage Steel Frame 4/21/2020 Not Ready for Inspection NICK LAROCCA
Light Gage Steel Frame 4/30/2020 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 5/11/2020 Partial Approval TED RIES
Interior/Exterior Lathing 5/13/2020 Partial Approval NICK LAROCCA
Wood Frame 5/21/2020 Partial Approval NICK LAROCCA
Interior/Exterior Lathing 6/2/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 6/12/2020 Approved NICK LAROCCA
Footing/Foundation/Slab 6/17/2020 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 6/23/2020 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 6/26/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 7/1/2020 Partial Approval NICK LAROCCA
Insulation 7/2/2020 Partial Approval NICK LAROCCA
Masonry Wall/Backfill 7/6/2020 Partial Approval NICK LAROCCA
Light Gage Steel Frame 7/23/2020 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 8/24/2020 Corrections Issued NICK LAROCCA
Masonry Wall/Backfill 8/31/2020 Partial Approval NICK LAROCCA
Masonry Wall/Backfill 9/3/2020 Partial Approval NICK LAROCCA
T-Bar Ceiling 9/4/2020 Corrections Issued NICK LAROCCA
Pre-Inspection 9/11/2020 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/21/2020 Approved JOEY BUCHANAN
Drywall Nailing 9/22/2020 Approved NICK LAROCCA
Final 9/22/2020 Not Ready for Inspection NICK LAROCCA
Footing/Foundation/Slab 9/22/2020 Approved NICK LAROCCA
Green Building Final 9/22/2020 Approved NICK LAROCCA
Reinforced Masonry Frame 9/22/2020 Approved NICK LAROCCA
SGSOV-Seismic Gas S/O Valve 9/22/2020 SGSOV Approved NICK LAROCCA
Smoke Detectors 9/22/2020 Approved NICK LAROCCA
Structural Steel Frame 9/22/2020 Approved NICK LAROCCA
Wood Frame 9/22/2020 Approved NICK LAROCCA
Final 9/30/2020 Partial Inspection NICK LAROCCA
Final 10/8/2020 Partial Inspection NICK LAROCCA
Final 1/19/2021 Not Ready for Inspection PAUL DAVIDSON
Pre-Inspection 2/4/2021 Approved DERRICK SPENCER
Final 2/11/2021 OK to Issue CofO DERRICK SPENCER
Pre-Inspection 2/12/2021 Approved DERRICK SPENCER
Final 2/16/2021 Not Ready for Inspection DERRICK SPENCER