5434 S BRYNHURST AVE 90043

Certificate Information: 5434 S BRYNHURST AVE 90043

Application / Permit
18014-10000-03299
Plan Check / Job No.
B18LA11831
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) KITCHEN AND (N) 84 SF MASTER STUDY ADDITION
Permit Issued
Issued on 6/13/2018
Issuing Office
Metro
Current Status
CofO in Progress on 5/7/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/13/2018 APPLICANT
Assigned to Plan Check Engineer 6/13/2018 JAYDON NGUYEN
Corrections Issued 6/13/2018 JAYDON NGUYEN
Issued 6/13/2018 LADBS
CofO in Progress 5/7/2024 JOHN PARKER

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/13/2018 MICHAEL CASTILLO
Roof/Waste drainage to street Cleared 6/13/2018 MICHAEL CASTILLO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/3/2019 Approved FREDDIE RIVERA
PLUMBING-Rough 3/5/2020 Partial Approval KIM BEAUCHAMP
Insulation 4/3/2020 Partial Approval DANIEL GONZALEZ
Wood Frame 10/1/2020 Corrections Issued KIM BEAUCHAMP
BUILDING-Rough-Frame 10/29/2020 Corrections Issued KIM BEAUCHAMP
Green Building Rough 10/29/2020 Not Ready for Inspection KIM BEAUCHAMP
Wood Frame 10/29/2020 Corrections Issued KIM BEAUCHAMP
BUILDING-Rough-Frame 11/19/2020 Not Ready for Inspection KIM BEAUCHAMP
Green Building Rough 11/19/2020 Not Ready for Inspection KIM BEAUCHAMP
Floor/Roof Diaphrgm/Shear Wall 1/6/2021 Approved ANDEY CHAPARRO
Green Building Rough 1/6/2021 Not Ready for Inspection ANDEY CHAPARRO
ELECTRICAL-Rough 10/14/2022 Not Ready for Inspection ENRIQUE PREZA
PLUMBING-Rough 10/14/2022 Approved ENRIQUE PREZA
BUILDING-Rough-Frame 1/23/2023 Approved DANIEL GONZALEZ
ELECTRICAL-Rough 1/23/2023 Approved DANIEL GONZALEZ
Green Building Rough 1/23/2023 Approved DANIEL GONZALEZ
Insulation 1/24/2023 Approved DANIEL GONZALEZ
Drywall Nailing 4/25/2023 Approved ENRIQUE PREZA
Interior/Exterior Lathing 4/25/2023 Partial Approval ENRIQUE PREZA
Service/Power Release 5/18/2023 Approved JOHN PARKER
Shower Pan 5/18/2023 Approved JOHN PARKER
Shower Pan 7/3/2023 Approved JOHN PARKER
Final 3/13/2024 Partial Approval JOHN PARKER
Green Building Final 3/13/2024 Approved JOHN PARKER
SGSOV-Seismic Gas S/O Valve 3/13/2024 SGSOV Approved JOHN PARKER
Smoke Detectors 3/13/2024 Approved JOHN PARKER
Deck 5/3/2024 Not Ready for Inspection MICHAEL SERETTI
ELECTRICAL-Final 5/7/2024 Approved JOHN PARKER
Final 5/7/2024 OK to Issue CofO JOHN PARKER
HVAC-Final 5/7/2024 Approved JOHN PARKER
PLUMBING-Final 5/7/2024 Approved JOHN PARKER