1102 1/2 E M ST 90744

Certificate Information: 1102 1/2 E M ST 90744

Application / Permit
18014-10000-03249
Plan Check / Job No.
B18LA11619
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD SECOND STORY TO GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 1/14/2019
Issuing Office
Metro
Current Status
CofO Issued on 8/12/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2018 APPLICANT
Assigned to Plan Check Engineer 6/27/2018 ALFREDO JARA
Corrections Issued 7/3/2018 ALFREDO JARA
Quality Review Completed 7/11/2018 TIEN JEN WANG
Building Plans Picked Up 7/16/2018 APPLICANT
Green Plans Picked Up 8/7/2018 APPLICANT
Plan Check Approved 10/2/2018 ALFREDO JARA
Issued 1/14/2019 LADBS
CofO in Progress 7/31/2020 WILLIAM ROSE
Permit Finaled 8/12/2020 DEROLD HAUFF
CofO Issued 8/12/2020 DEROLD HAUFF
Permit Finaled 8/12/2020 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 8/1/2018 BRIAN CARR
Address approval Cleared 8/1/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 8/14/2018 CELINA MORENO
Sewer availability Cleared 8/14/2018 CELINA MORENO
Green Code Cleared 9/10/2018 NEGAR NEJAD
Low Impact Development Cleared 9/10/2018 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/10/2018 MICHAEL CASTILLO

Contact Information

Contractor Warys Construction; Lic. No.: 922756-B 1043 WATSON AVENUE      WILMINGTON, CA 90744
Engineer Singh, Jasbir; Lic. No.: C38767 15095 CALLE DEL ORO      CHINO HILLS, CA 91709

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/17/2019 Approved JOHN KLARIN
METHANE-Barrier 9/17/2019 Approved JOHN KLARIN
METHANE-Subgrade 9/17/2019 Approved JOHN KLARIN
PLUMBING-Rough 9/19/2019 Partial Inspection JOHN KLARIN
Green Building Rough 10/3/2019 Partial Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 1/24/2020 Approved JOHN KLARIN
Green Building Rough 1/24/2020 Not Ready for Inspection JOHN KLARIN
METHANE-Rough 1/24/2020 Approved JOHN KLARIN
PLUMBING-Rough 1/24/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/28/2020 Approved JOHN KLARIN
ELECTRICAL-Rough 2/28/2020 Approved JOHN KLARIN
Green Building Rough 2/28/2020 Approved JOHN KLARIN
Insulation 3/25/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 3/25/2020 Approved JOHN KLARIN
Drywall Nailing 4/6/2020 Approved BRIAN CHRISTIAN
Shower Pan 4/15/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 6/10/2020 Approved JOHN KLARIN
Final 6/10/2020 Corrections Issued JOHN KLARIN
Gas Test 6/10/2020 Approved JOHN KLARIN
Green Building Final 6/10/2020 Corrections Issued JOHN KLARIN
HVAC-Final 6/10/2020 Approved JOHN KLARIN
PLUMBING-Final 6/10/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 6/10/2020 SGSOV Approved JOHN KLARIN
Smoke Detectors 6/10/2020 Approved JOHN KLARIN
Green Building Final 7/2/2020 Approved JOHN KLARIN
Service/Power Release 7/2/2020 Not Ready for Inspection JOHN KLARIN
Final 7/23/2020 OK to Issue CofO JOHN KLARIN
Service/Power Release 8/5/2020 Approved JOHN KLARIN