10320 W OLYMPIC BLVD 90064
Certificate Information: 10320 W OLYMPIC BLVD 90064
- Application / Permit
- 18014-10000-03119
- Plan Check / Job No.
- B18LA11173
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- EXTERIOR RENOVATION TO EXISTING HOTEL AND NEW CANOPIES AT ENTRIES, NEW TRELLIS AT DECK AREA, NEW RAILINGS AT BALCONIES, AND NEW FACADE INCLUDING FURRED ARCHITECTURAL FEATURES.
- Permit Issued
- Issued on 12/24/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2018 | APPLICANT |
| Green Plans Picked Up | 6/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2018 | TEODORO DIAZ RODRIGUEZ |
| Corrections Issued | 7/6/2018 | TEODORO DIAZ RODRIGUEZ |
| Disabled Access Plans Picked Up | 7/10/2018 | APPLICANT |
| Quality Review Completed | 7/18/2018 | SIAVOSH POURSABAHIAN |
| Building Plans Picked Up | 7/23/2018 | APPLICANT |
| Applicant returned to address corrections | 9/26/2018 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 11/8/2018 | TEODORO DIAZ RODRIGUEZ |
| Issued | 12/24/2018 | LADBS |
| CofO in Progress | 9/6/2022 | PAUL DAVIDSON |
| Permit Finaled | 9/20/2022 | DAVID TSAU |
| CofO Issued | 9/20/2022 | DAVID TSAU |
| Permit Finaled | 9/20/2022 | DAVID TSAU |
Permit Application Clearance Information
| Encroachment in public way | Cleared | 8/31/2018 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2018 | ADRIAN SANCHEZ |
| Grading Pre-Inspection | Cleared | 8/31/2018 | PATRICK MISCHLICH |
| Highway dedication | Cleared | 8/31/2018 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/31/2018 | ADRIAN SANCHEZ |
| ZA Case | Cleared | 8/31/2018 | DANALYNN DOMINGUEZ |
| ZA Case | Cleared | 8/31/2018 | DANALYNN DOMINGUEZ |
| ZA Case | Cleared | 8/31/2018 | DANALYNN DOMINGUEZ |
| GPI Written Notices | Cleared | 9/26/2018 | TEODORO DIAZ RODRIGUEZ |
| Green Code | Cleared | 9/26/2018 | TEODORO DIAZ RODRIGUEZ |
| Specific Plan | Cleared | 9/27/2018 | JOHNATHAN YU |
| Low Impact Development | Cleared | 10/4/2018 | ORVAL HERNANDEZ-MARCI |
| DAS Clearance | Cleared | 11/1/2018 | EDDIE GARIN |
Contact Information
| Architect | Hill, John Steven; Lic. No.: C23553 | 3195B AIRPORT LOOP DRIVE COSTA MESA, CA 92626 |
| Contractor | Owner-Builder | , |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/4/2019 | Approved | PAUL DAVIDSON |
| Special/Order Compliance | 8/3/2020 | Partial Inspection | PAUL DAVIDSON |
| Pre-Inspection | 9/30/2020 | Approved | PAUL DAVIDSON |
| Pre-Inspection | 3/30/2021 | Partial Approval | PAUL DAVIDSON |
| Pre-Inspection | 9/7/2021 | Approved | PAUL DAVIDSON |
| Green Building Rough | 10/5/2021 | Approved | PAUL DAVIDSON |
| METHANE-Rough | 10/5/2021 | Approved | PAUL DAVIDSON |
| Wood Frame | 10/5/2021 | Partial Inspection | PAUL DAVIDSON |
| Special/Order Compliance | 10/12/2021 | Partial Inspection | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 10/21/2021 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 10/22/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| METHANE-Barrier | 10/22/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| METHANE-Subgrade | 10/22/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 10/26/2021 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 10/27/2021 | Approved | PAUL DAVIDSON |
| METHANE-Barrier | 10/27/2021 | Approved | PAUL DAVIDSON |
| METHANE-Subgrade | 10/27/2021 | Approved | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 10/28/2021 | Conditional Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 10/28/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 10/28/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Light Gage Steel Frame | 11/1/2021 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 11/10/2021 | Corrections Issued | PAUL DAVIDSON |
| Wood Frame | 11/10/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Special/Order Compliance | 11/15/2021 | Partial Inspection | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2021 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 11/19/2021 | Partial Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 11/29/2021 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 11/30/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 12/1/2021 | Conditional Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 12/2/2021 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 12/7/2021 | Partial Inspection | PAUL DAVIDSON |
| Deputy Steel/Welding | 12/17/2021 | Conditional Approval | PAUL DAVIDSON |
| Structural Steel Frame | 12/17/2021 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 12/21/2021 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 12/23/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Interior/Exterior Lathing | 12/28/2021 | Partial Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 1/12/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 1/13/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 1/13/2022 | Conditional Approval | PAUL DAVIDSON |
| Wood Frame | 1/20/2022 | Partial Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 1/25/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 1/26/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 1/27/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 2/7/2022 | Conditional Approval | PAUL DAVIDSON |
| Special/Order Compliance | 2/9/2022 | Partial Inspection | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 5/18/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 5/25/2022 | Conditional Approval | PAUL DAVIDSON |
| Final | 8/29/2022 | OK to Issue CofO | PAUL DAVIDSON |
| Green Building Final | 8/29/2022 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 8/29/2022 | Approved | PAUL DAVIDSON |
| Wood Frame | 8/29/2022 | Approved | PAUL DAVIDSON |