11359 N CLYBOURN AVE 91342

Certificate Information: 11359 N CLYBOURN AVE 91342

Application / Permit
18014-10000-03062
Plan Check / Job No.
B18LA11006
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 87 SF AT REAR OF 1-STORY SFD; REFRAME ROOF AT ADDITION AREA.
Permit Issued
Issued on 11/19/2020
Issuing Office
Current Status
CofO Issued on 4/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2018 APPLICANT
Assigned to Plan Check Engineer 6/1/2018 CAROLYNN NEPOMUCENO
Corrections Issued 6/6/2018 ARSALAN SHABESTARI
Applicant returned to address corrections 7/9/2020 AMIR DANAI
Applicant returned to address corrections 8/7/2020 SAMUEL GONZALEZ
Plan Check Approved 10/2/2020 AUNG SOE
Issued 11/19/2020 APPLICANT
Building Plans Picked Up 12/1/2020 APPLICANT
CofO in Progress 4/7/2023 MICHEL ABAJAN
CofO Issued 4/11/2023 RONALD MYRICK
Permit Finaled 4/11/2023 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/29/2019 CELINA MORENO
Roof/Waste drainage to street Cleared 7/29/2019 CELINA MORENO
Grading Pre-Inspection Cleared 8/27/2019 BARTON HOLMES
Specific Plan Cleared 6/10/2020 VINCENT QUITORIANO

Contact Information

Contractor Barron Marco Engineer Contractor Inc; Lic. No.: 834558-B 10172 TUJUNGA CANYON BLVD      TUJUNGA, CA 91042
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough-Elec/Plmb/HVAC 12/8/2020 Not Ready for Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 9/8/2022 Approved MICHEL ABAJAN
FLOOD-Elevation Certificate 9/15/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 9/15/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/6/2022 Not Ready for Inspection MICHEL ABAJAN
FLOOD-Proofing Certificate 10/6/2022 Approved MICHEL ABAJAN
Green Building Rough 10/6/2022 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Rough 10/6/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/25/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 10/25/2022 Approved MICHEL ABAJAN
Green Building Rough 10/25/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 10/25/2022 Approved MICHEL ABAJAN
Insulation 11/1/2022 Not Ready for Inspection CALEB MEISTER
Interior/Exterior Lathing 11/1/2022 Not Ready for Inspection CALEB MEISTER
Insulation 11/7/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/7/2022 Approved MICHEL ABAJAN
Drywall Nailing 11/9/2022 Approved ROBERT GOLD
ELECTRICAL-Final 3/29/2023 Approved MICHEL ABAJAN
Final 3/29/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 3/29/2023 Approved MICHEL ABAJAN
HVAC-Final 3/29/2023 Approved MICHEL ABAJAN
MERV13>=Final 3/29/2023 Approved MICHEL ABAJAN
PLUMBING-Final 3/29/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 3/29/2023 Approved MICHEL ABAJAN
Final 4/7/2023 OK to Issue CofO MICHEL ABAJAN