2611-2613 N HYPERION AVE 90027

Certificate Information: 2611-2613 N HYPERION AVE 90027

Application / Permit
18014-10000-02577
Plan Check / Job No.
B18LA09252
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 1496 SQFT. UNIT ADDITION TO EXISTING SINGLE FAMILY BUILDING TO CONVERT TO DUPLEX.
Permit Issued
Issued on 11/9/2018
Issuing Office
Metro
Current Status
CofO Issued on 4/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2018 APPLICANT
Assigned to Plan Check Engineer 6/21/2018 RACHEL BEYENE
Corrections Issued 7/6/2018 RACHEL BEYENE
Quality Review Completed 7/11/2018 TIEN JEN WANG
Building Plans Picked Up 7/17/2018 APPLICANT
Green Plans Picked Up 8/2/2018 APPLICANT
Applicant returned to address corrections 8/21/2018 RACHEL BEYENE
Plan Check Approved 9/24/2018 RAHEL BEYENE
Issued 11/9/2018 LADBS
CofO in Progress 4/15/2021 JOSEPH MCGARRY
Permit Finaled 4/27/2021 DEROLD HAUFF
CofO Issued 4/27/2021 DEROLD HAUFF
Permit Finaled 4/27/2021 DEROLD HAUFF

Permit Application Clearance Information

"D" conditions Cleared 8/2/2018 BRIAN CARR
Address approval Cleared 8/2/2018 CARLA VALLADARES
Specific Plan Cleared 8/2/2018 BRIAN CARR
ZA Case Cleared 8/2/2018 BRIAN CARR
ZA Case Cleared 8/2/2018 BRIAN CARR
ZA Case Cleared 8/2/2018 BRIAN CARR
Eng Process Fee Ord 176,300 Cleared 8/13/2018 STEVE MELGAR
Sewer availability Cleared 8/13/2018 STEVE MELGAR
Green Code Cleared 8/16/2018 NEGAR NEJAD
Low Impact Development Cleared 9/11/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 9/11/2018 MICHAEL CASTILLO

Contact Information

Architect Williams, Gregory Keith; Lic. No.: C22965 1218 S LONGWOOD AVENUE      LOS ANGELES, CA 90019
Contractor Owner-Builder       ,
Engineer Mani, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 1/15/2019 Corrections Issued BRAD BESCOS
Special/Order Compliance 1/17/2019 Corrections Issued BRAD BESCOS
Special/Order Compliance 1/22/2019 Approved ROBERT MINASSIANS
Footing/Foundation/Slab 3/29/2019 Partial Approval BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 4/4/2019 Corrections Issued BRAD BESCOS
BUILDING-Rough-Frame 5/9/2019 Corrections Issued BRAD BESCOS
ELECTRICAL-Rough 5/9/2019 Corrections Issued BRAD BESCOS
Green Building Rough 5/9/2019 Not Ready for Inspection BRAD BESCOS
BUILDING-Rough-Frame 5/15/2019 Partial Approval BRAD BESCOS
ELECTRICAL-Rough 5/15/2019 Not Ready for Inspection BRAD BESCOS
Green Building Rough 5/15/2019 Approved BRAD BESCOS
Insulation 5/17/2019 Approved BRAD BESCOS
BUILDING-Rough-Frame 6/4/2019 Not Ready for Inspection BRAD BESCOS
Drywall Nailing 6/4/2019 Not Ready for Inspection BRAD BESCOS
Final 6/4/2019 Not Ready for Inspection BRAD BESCOS
Footing/Foundation/Slab 6/4/2019 Not Ready for Inspection BRAD BESCOS
Green Building Final 6/4/2019 Not Ready for Inspection BRAD BESCOS
SGSOV-Seismic Gas S/O Valve 6/4/2019 SGSOV Not Ready BRAD BESCOS
Smoke Detectors 6/4/2019 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 9/11/2019 Corrections Issued BRAD BESCOS
Footing/Foundation/Slab 9/16/2019 Corrections Issued BRAD BESCOS
Pre-Inspection 9/18/2019 Partial Inspection RAUL BARAJAS
BUILDING-Rough-Frame 9/24/2019 Partial Approval BRAD BESCOS
BUILDING-Rough-Frame 11/21/2019 Corrections Issued BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 11/21/2019 Not Ready for Inspection BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 11/26/2019 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/3/2019 Corrections Issued BRAD BESCOS
BUILDING-Rough-Frame 12/24/2019 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Rough 12/24/2019 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 12/24/2019 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 1/8/2020 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Rough 1/8/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 1/8/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 1/9/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 1/9/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 1/9/2020 Approved ARTHUR SARGSYAN
Insulation 1/14/2020 Not Ready for Inspection COREY HUPP
Interior/Exterior Lathing 1/14/2020 Not Ready for Inspection COREY HUPP
Insulation 1/16/2020 Corrections Issued JOSEPH MCGARRY
Insulation 1/30/2020 Corrections Issued JOSEPH MCGARRY
Interior/Exterior Lathing 1/30/2020 Not Ready for Inspection JOSEPH MCGARRY
Insulation 1/31/2020 Not Ready for Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 1/31/2020 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 2/14/2020 Approved JOSEPH MCGARRY
Insulation 2/14/2020 Not Ready for Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 2/14/2020 Partial Inspection JOSEPH MCGARRY
Shower Pan 2/14/2020 Approved JOSEPH MCGARRY
Special/Order Compliance 2/14/2020 Partial Approval JOSEPH MCGARRY
Insulation 2/21/2020 Corrections Issued JOSEPH MCGARRY
Insulation 3/3/2020 Corrections Issued JOSEPH MCGARRY
Insulation 3/13/2020 Partial Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 3/13/2020 Approved JOSEPH MCGARRY
Special/Order Compliance 3/17/2020 Partial Inspection JOSEPH MCGARRY
Drywall Nailing 3/18/2020 Partial Inspection JOSEPH MCGARRY
PLUMBING-Rough 3/18/2020 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 3/23/2020 Partial Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 4/24/2020 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 6/2/2020 Approved JOSEPH MCGARRY
Drywall Nailing 6/2/2020 Approved JOSEPH MCGARRY
Final 6/2/2020 Not Ready for Inspection JOSEPH MCGARRY
Green Building Final 6/2/2020 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Final 6/2/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 6/2/2020 SGSOV Not Ready JOSEPH MCGARRY
Smoke Detectors 6/2/2020 Approved JOSEPH MCGARRY
ELECTRICAL-Final 7/8/2020 Approved CHRIS CHRISTENSEN
Final 7/8/2020 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 7/8/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 7/8/2020 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/8/2020 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 7/29/2020 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Final 4/13/2021 Approved JOSEPH MCGARRY
Final 4/13/2021 OK to Issue CofO JOSEPH MCGARRY
Service/Power Release 4/13/2021 Not Required JOSEPH MCGARRY