1320 N DAVIES DR 90210
Certificate Information: 1320 N DAVIES DR 90210
- Application / Permit
- 18014-10000-02503
- Plan Check / Job No.
- B18LA09028
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SINGLE STORY, 906 SF, TYPE VB, R3-OCC ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. SEE COMMENTS FOR CLEARANCES CONDITIONS.
- Permit Issued
- Issued on 6/15/2021
- Issuing Office
- Current Status
- CofO Issued on 8/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2018 | APPLICANT |
| Green Plans Picked Up | 6/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2018 | SERGIO GUTIERREZ |
| Corrections Issued | 6/26/2018 | DEVIN GORDON |
| Quality Review Completed | 7/5/2018 | KESETE HAREGOT |
| Applicant returned to address corrections | 5/23/2019 | SERGIO GUTIERREZ |
| Plan Check Approved | 7/18/2019 | SERGIO GUTIERREZ |
| Issued | 6/15/2021 | APPLICANT |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| CofO in Progress | 8/16/2024 | SEAN HAUPT |
| Permit Finaled | 8/17/2024 | RICHARD STEINBACH |
| CofO Issued | 8/17/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/17/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/13/2018 | KAREN LE |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2018 | KAREN LE |
| Green Code | Cleared | 9/13/2018 | KHEDER ALRAZAA |
| Hydrant and Access approval | Cleared | 9/13/2018 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 9/13/2018 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 9/14/2018 | KRISTEN LY |
| GPI Written Notices | Cleared | 5/23/2019 | DEVIN GORDON |
| Grading Pre-Inspection | Cleared | 5/23/2019 | DEVIN GORDON |
| Private street | Cleared | 6/11/2019 | LATANYA ROUX |
| ZA Case | Cleared | 6/11/2019 | LATANYA ROUX |
| BHO/Hillside ordinance | Cleared | 7/18/2019 | OSCAR GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 7/18/2019 | OSCAR GUTIERREZ |
Contact Information
| Architect | C, + P Design; Lic. No.: C31357 | 3300 AIRPORT AVE SUITE 4 SANTA MONICA, CA 90405 |
| Contractor | David Diaz; Lic. No.: 467015-B | 5108 CORBINA WAY OXNARD, CA 93035 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
| Engineer | Black,, Ian Robert; Lic. No.: S5505 | 19401 OLANA LN HUNTINGTON BEACH, CA 92646 |
| Engineer | Miyamoto,, Yoshiaki Wayne; Lic. No.: L4825 | 4396 MENTONE AVE CULVER CITY, CA 90230 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/14/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 9/22/2021 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 9/24/2021 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 10/21/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 10/21/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 11/16/2021 | Partial Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 12/1/2021 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 1/19/2022 | Approved | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 1/21/2022 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 2/2/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 2/2/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Drilled-In Anchors | 5/9/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Wood Construction | 6/13/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 8/30/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 8/30/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 8/30/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 8/30/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/30/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 12/15/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 12/15/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 12/29/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 12/29/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 1/31/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 1/31/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 1/31/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 2/7/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 2/7/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 2/7/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Masonry Wall/Backfill | 6/13/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/10/2023 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 10/10/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 10/10/2023 | Corrections Issued | BRENDAN LOONEY |
| Drywall Nailing | 10/17/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 10/17/2023 | Approved | BRENDAN LOONEY |
| Final | 10/17/2023 | Corrections Issued | BRENDAN LOONEY |
| Gas Test | 10/17/2023 | Approved | BRENDAN LOONEY |
| Green Building Final | 10/17/2023 | Approved | BRENDAN LOONEY |
| HVAC-Final | 10/17/2023 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 10/17/2023 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 10/17/2023 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 10/17/2023 | Approved | BRENDAN LOONEY |
| Structural Steel Frame | 10/17/2023 | Approved | BRENDAN LOONEY |
| Final | 7/24/2024 | Corrections Issued | SEAN HAUPT |
| Final | 8/15/2024 | OK to Issue CofO | SEAN HAUPT |