1846 S CLYDE AVE 90019
Certificate Information: 1846 S CLYDE AVE 90019
- Application / Permit
- 18014-10000-02492
- Plan Check / Job No.
- B18LA09000
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION AND REMODEL OF (E) SFD. ADD THREE 3/4 BATHROOMS, 1/2 BATHROOM, LAUNDRY ROOM AND TWO NEW BEDROOMS. REMODEL (E) BEDROOMS, LIVING ROOM, AND KITCHEN.
- Permit Issued
- Issued on 10/9/2019
- Issuing Office
- San Pedro
- Current Status
- Issued on 10/9/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2018 | CRISTINA SALAZAR |
| Corrections Issued | 5/8/2018 | CRISTINA SALAZAR |
| Plan Check Approved | 10/23/2018 | JEFFREY MACHADO |
| Issued | 10/9/2019 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 8/31/2018 | MICHAEL CASTILLO |
| Low Impact Development | Cleared | 10/23/2018 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/23/2018 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero, Fidencio Jr; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 9/8/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Approved | JOSE AVILA |
| Deputy Wood Construction | 9/13/2022 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 9/20/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 9/20/2022 | Approved | JOSE AVILA |
| Wood Frame | 9/22/2022 | Approved | JOSE AVILA |
| Insulation | 9/26/2022 | Approved | JOSE AVILA |
| Shower Pan | 9/26/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 9/29/2022 | Partial Approval | JOSE AVILA |
| Green Building Rough | 9/29/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 9/29/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/2/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Drywall Nailing | 6/2/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 6/2/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 6/2/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 6/2/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 6/2/2025 | SGSOV Not Ready | ARTHUR NEGRETE |
| Smoke Detectors | 6/2/2025 | Not Ready for Inspection | ARTHUR NEGRETE |