13420 W VENTURA BLVD 91423

Certificate Information: 13420 W VENTURA BLVD 91423

Application / Permit
18014-10000-02460
Plan Check / Job No.
B18LA08911
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
(1)CHANGE OF USE FROM "RETAIL' TO "RESTAURANT" (2)ADDITION OF 163SF (3)INTERIOR REMODEL <<per Comments under ZA2018-1775-CUB-SPP, DO NOT ISSUE C OF O until City Planning approval for 15% Landscaping>>
Permit Issued
Issued on 6/2/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2018 APPLICANT
Green Plans Picked Up 6/12/2018 APPLICANT
Disabled Access Plans Picked Up 6/18/2018 APPLICANT
Assigned to Plan Check Engineer 6/28/2018 DEAN LEE
Corrections Issued 7/6/2018 DEAN LEE
Quality Review Completed 7/10/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 7/11/2018 APPLICANT
Applicant returned to address corrections 7/31/2018 DEAN LEE
Applicant returned to address corrections 9/24/2018 DEAN LEE
Plan Check Approved 11/6/2019 DEAN LEE
Issued 6/2/2020 LADBS
CofO in Progress 8/16/2023 CAMERON CHABAN
Permit Finaled 4/26/2024 JEFFREY DURAN
CofO Issued 4/26/2024 JEFFREY DURAN
Permit Finaled 4/26/2024 JEFFREY DURAN

Permit Application Clearance Information

ZA Case Cleared 7/18/2018 SOPHIE GABEL-SCHEINBAU
Hydrant and Access approval Cleared 7/20/2018 JOHN DALLAS
Eng Process Fee Ord 176,300 Cleared 7/24/2018 EDUARDO PEDROZA
Sewer availability Cleared 7/24/2018 EDUARDO PEDROZA
Food establishment approval Cleared 9/18/2018 LACDHS APPROVED
Food Service Establishment Cleared 9/27/2018 PAWAN VERMA
DAS Clearance Cleared 10/21/2019 WAI LAU
Specific Plan Cleared 10/23/2019 SARAH GOLDMAN
ZA Case Cleared 10/23/2019 SARAH GOLDMAN
Green Code Cleared 10/25/2019 VIVIAN LAO

Contact Information

Architect Fry,, Jimmy D; Lic. No.: C26710 11672 ERWIN STREET      NORTH HOLLYWOOD, CA 91606
Contractor Keystone Construction Inc; Lic. No.: 797889-B 269 S WESTERN AVE 286      LOS ANGELES, CA 90004
Engineer Khanjian,, Hovik J; Lic. No.: C51609 326 S. SPARKS STREET      BURBANK, CA 91506

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/3/2020 Approved ROBERT DAVIS
Deputy Drilled-In Anchors 6/23/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 6/29/2021 Corrections Issued ANDREW DORSO
Deputy Drilled-In Anchors 10/27/2021 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 11/2/2021 Approved ROBERT DAVIS
Green Building Rough 11/30/2021 Not Ready for Inspection JONATHAN QUACH
Wood Frame 11/30/2021 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 12/2/2021 Partial Approval CAMERON CHABAN
Drywall Nailing 12/10/2021 Partial Inspection ANDREW DORSO
Drywall Nailing 12/22/2021 Partial Inspection ANDREW DORSO
Insulation 1/27/2022 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 2/1/2022 Approved DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 2/14/2022 Conditional Approval CAMERON CHABAN
Green Building Rough 3/15/2022 Not Ready for Inspection JEFFREY FULTON
Wood Frame 3/15/2022 Corrections Issued JEFFREY FULTON
Drywall Nailing 3/30/2022 Approved DANIEL VARNUM
Green Building Rough 3/30/2022 Approved DANIEL VARNUM
Wood Frame 3/30/2022 Approved DANIEL VARNUM
Insulation 4/5/2022 Approved CAMERON CHABAN
Drywall Nailing 5/6/2022 Approved CAMERON CHABAN
Interior/Exterior Lathing 6/1/2022 Approved CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 7/28/2022 Approved DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 9/16/2022 Approved CAMERON CHABAN
Final 7/18/2023 Partial Inspection CAMERON CHABAN
Green Building Final 7/18/2023 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 7/18/2023 SGSOV Approved CAMERON CHABAN
SUSMP-Std. Urban Storm Water 7/18/2023 Partial Inspection CAMERON CHABAN
Smoke Detectors 7/18/2023 Approved CAMERON CHABAN
Final 8/16/2023 OK to Issue CofO CAMERON CHABAN
Green Building Final 8/16/2023 Approved CAMERON CHABAN
SUSMP-Std. Urban Storm Water 8/16/2023 Approved CAMERON CHABAN
Special/Order Compliance 4/23/2024 Partial Inspection ROBERT DAVIS
Special/Order Compliance 4/25/2024 Partial Inspection ROBERT DAVIS