3200 S MOTOR AVE 90064

Certificate Information: 3200 S MOTOR AVE 90064

Application / Permit
18014-10000-02331
Plan Check / Job No.
B18LA08433
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(21) Theater
Work Description
REMODEL/ ADDITION AND CHANGE OF USE FROM (E) SYNAGOGUE BUILDING ON THE CAMPUS OF AN EXISTING RESIDENTIAL SCHOOL FACILITY TO THEATRE AND CLASSROOMS (+ 13 YRS OF AGE)
Permit Issued
Issued on 11/2/2018
Issuing Office
Metro
Current Status
CofO Issued on 7/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2018 APPLICANT
Green Plans Picked Up 5/16/2018 APPLICANT
Assigned to Plan Check Engineer 5/24/2018 HERNAN ARREOLA
Disabled Access Plans Picked Up 6/1/2018 APPLICANT
Corrections Issued 6/4/2018 HERNAN ARREOLA
Quality Review Completed 6/12/2018 BILL STUTSMAN
Building Plans Picked Up 6/12/2018 APPLICANT
Plan Check Approved 10/10/2018 HERNAN ARREOLA
Issued 11/2/2018 LADBS
CofO in Progress 7/8/2021 SORIN CIRSTOIU
Permit Finaled 7/15/2021 TED RIES
CofO Issued 7/15/2021 TED RIES
Permit Finaled 7/15/2021 TED RIES

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/25/2018 JOHN CONNEALLY
Specific Plan Cleared 8/28/2018 EDER ROMERO
Eng Process Fee Ord 176,300 Cleared 9/13/2018 ADOLFO GUTIERREZ
Sewer availability Cleared 9/13/2018 ADOLFO GUTIERREZ
CPC Cleared 9/17/2018 EDBER MACEDO
Green Code Cleared 9/24/2018 KHEDER ALRAZAA
DAS Clearance Cleared 9/25/2018 ELIZABETH TOMS
ZA Case Cleared 10/2/2018 EDBER MACEDO
ZA Case Cleared 10/2/2018 EDBER MACEDO
ZA Case Cleared 10/2/2018 EDBER MACEDO
Fire Marshall Fire Life Safety Cleared 10/4/2018 MENOA AGHAJANI
Low Impact Development Cleared 10/4/2018 ORVAL HERNANDEZ-MARCI
GPI Written Notices Cleared 10/5/2018 HERNAN ARREOLA
Roof/Waste drainage to street Cleared 10/5/2018 JEANETTE VONG

Contact Information

Architect Wickersham, Brian; Lic. No.: C32742 6142 BUENA VISTA TERRACE      LOS ANGELES, CA 90042
Contractor Turelk Inc; Lic. No.: 372562-B P O BOX 93101      LONG BEACH, CA 90809
Engineer , ; Lic. No.: C36079 1041 S GARFIELD AVE   210    ALHAMBRA, CA 91801
Engineer , ; Lic. No.: GE2476 14428 HAMLIN ST   200    LOS ANGELES, CA 91401
Engineer , ; Lic. No.: S5853 527 WEST 7TH ST   701    LOS ANGELES, CA 90014

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/23/2019 Approved JOHN DODGE
Footing/Foundation/Slab 3/4/2019 Conditional Approval JOHN DODGE
Deputy Reinf. Concrete 3/7/2019 Conditional Approval JOHN DODGE
Footing/Foundation/Slab 3/18/2019 Partial Approval JOHN DODGE
Deputy Reinf. Concrete 3/20/2019 Conditional Approval JOHN DODGE
Excavation/Setback/Form/Re-Bar 4/1/2019 Partial Approval JOHN DODGE
Deputy Reinf. Concrete 4/3/2019 Conditional Approval JOHN DODGE
Special/Order Compliance 4/17/2019 Approved JOHN DODGE
Footing/Foundation/Slab 4/19/2019 Partial Approval JOHN DODGE
Deputy Reinf. Concrete 4/22/2019 Conditional Approval JOHN DODGE
Footing/Foundation/Slab 4/26/2019 Partial Approval JOHN DODGE
Deputy Reinf. Concrete 4/29/2019 Conditional Approval JOHN DODGE
Excavation/Setback/Form/Re-Bar 5/29/2019 Not Ready for Inspection JOHN DODGE
Excavation/Setback/Form/Re-Bar 9/6/2019 Partial Inspection JASON BORUTA
Footing/Foundation/Slab 10/28/2019 Partial Approval JASON BORUTA
Excavation/Setback/Form/Re-Bar 11/4/2019 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 11/5/2019 Conditional Approval JASON BORUTA
Deputy Other (see comments) 1/22/2020 Conditional Approval JASON BORUTA
Deputy Drilled-In Anchors 1/31/2020 Approved JASON BORUTA
Reinforced Concrete Frame 1/31/2020 Partial Approval JASON BORUTA
Deputy Reinf. Concrete 2/3/2020 Conditional Approval JASON BORUTA
Deputy Other (see comments) 2/10/2020 Conditional Approval JASON BORUTA
Deputy Other (see comments) 2/14/2020 Conditional Approval JASON BORUTA
Footing/Foundation/Slab 2/24/2020 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 2/26/2020 Conditional Approval SORIN CIRSTOIU
Special/Order Compliance 2/26/2020 Approved TED RIES
Deputy Steel/Welding 4/1/2020 Conditional Approval SORIN CIRSTOIU
Green Building Rough 5/26/2020 Partial Inspection SORIN CIRSTOIU
Wood Frame 5/26/2020 Partial Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 5/27/2020 Approved SORIN CIRSTOIU
Deputy Wood Construction 5/27/2020 Approved SORIN CIRSTOIU
Deputy Other (see comments) 6/8/2020 Approved SORIN CIRSTOIU
Footing/Foundation/Slab 6/8/2020 Partial Inspection SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 6/9/2020 Partial Inspection SORIN CIRSTOIU
Deputy Other (see comments) 6/11/2020 Approved SORIN CIRSTOIU
Footing/Foundation/Slab 6/11/2020 Partial Approval SORIN CIRSTOIU
Deputy Other (see comments) 6/12/2020 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 6/12/2020 Approved SORIN CIRSTOIU
Deputy Other (see comments) 6/17/2020 Approved SORIN CIRSTOIU
Insulation 6/17/2020 Partial Approval SORIN CIRSTOIU
Deputy Other (see comments) 6/18/2020 Approved SORIN CIRSTOIU
Footing/Foundation/Slab 6/18/2020 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 6/19/2020 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 6/19/2020 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 6/22/2020 Approved SORIN CIRSTOIU
Deputy Other (see comments) 6/25/2020 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 6/25/2020 Partial Inspection SORIN CIRSTOIU
Deputy Drilled-In Anchors 6/29/2020 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 6/29/2020 Conditional Approval SORIN CIRSTOIU
Footing/Foundation/Slab 7/15/2020 Partial Approval SORIN CIRSTOIU
Deputy Shotcrete 7/23/2020 Conditional Approval JOHN DODGE
Footing/Foundation/Slab 7/23/2020 Not Ready for Inspection JOHN DODGE
Deputy Shotcrete 7/24/2020 Conditional Approval SORIN CIRSTOIU
Reinforced Concrete Frame 7/24/2020 Partial Approval JOHN DODGE
Footing/Foundation/Slab 8/21/2020 Not Ready for Inspection SORIN CIRSTOIU
Deputy Other (see comments) 8/25/2020 Conditional Approval SORIN CIRSTOIU
Deputy Other (see comments) 8/26/2020 Approved SORIN CIRSTOIU
Footing/Foundation/Slab 8/26/2020 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 8/27/2020 Partial Approval SORIN CIRSTOIU
Deputy Other (see comments) 8/28/2020 Approved SORIN CIRSTOIU
Deputy Reinf. Masonry 9/2/2020 Conditional Approval SORIN CIRSTOIU
Reinforced Masonry Frame 9/2/2020 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 9/8/2020 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 9/10/2020 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 9/15/2020 Partial Approval SORIN CIRSTOIU
Deputy Wood Construction 9/18/2020 Approved SORIN CIRSTOIU
Green Building Rough 9/18/2020 Partial Approval SORIN CIRSTOIU
Reinforced Masonry Frame 9/18/2020 Partial Approval SORIN CIRSTOIU
Wood Frame 9/18/2020 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 9/19/2020 Partial Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/14/2020 Conditional Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Partial Inspection SORIN CIRSTOIU
Insulation 10/20/2020 Partial Inspection SORIN CIRSTOIU
Deputy Wood Construction 10/28/2020 Approved SORIN CIRSTOIU
Drywall Nailing 10/28/2020 Partial Approval SORIN CIRSTOIU
Green Building Rough 10/28/2020 Partial Inspection SORIN CIRSTOIU
Wood Frame 10/28/2020 Partial Approval SORIN CIRSTOIU
Drywall Nailing 11/9/2020 Partial Inspection SORIN CIRSTOIU
Green Building Rough 11/9/2020 Partial Inspection SORIN CIRSTOIU
Wood Frame 11/9/2020 Partial Inspection SORIN CIRSTOIU
Drywall Nailing 11/16/2020 Partial Approval SORIN CIRSTOIU
Green Building Rough 11/16/2020 Partial Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 11/23/2020 Partial Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 11/24/2020 Partial Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 11/25/2020 Partial Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 11/30/2020 Not Ready for Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 12/2/2020 Not Ready for Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 12/3/2020 Partial Inspection SORIN CIRSTOIU
Insulation 12/4/2020 Partial Inspection SORIN CIRSTOIU
Green Building Rough 12/8/2020 Partial Inspection SORIN CIRSTOIU
Insulation 12/8/2020 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 12/8/2020 Partial Approval SORIN CIRSTOIU
Wood Frame 12/8/2020 Partial Inspection SORIN CIRSTOIU
Insulation 12/10/2020 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 12/16/2020 Partial Approval SORIN CIRSTOIU
T-Bar Ceiling 12/21/2020 Partial Approval SORIN CIRSTOIU
Green Building Rough 1/14/2021 Partial Approval SORIN CIRSTOIU
Wood Frame 1/14/2021 Partial Inspection SORIN CIRSTOIU
Deputy Other (see comments) 1/25/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/26/2021 Conditional Approval JOHN DODGE
Footing/Foundation/Slab 1/26/2021 Approved JOHN DODGE
Deputy Reinf. Concrete 1/27/2021 Conditional Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 1/27/2021 Pending Review
Light Gage Steel Frame 2/3/2021 Conditional Approval JOHN DODGE
Deputy Other (see comments) 2/9/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 2/9/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Other (see comments) 2/11/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Other (see comments) 2/12/2021 Conditional Approval LEOPOLDO MENDOZA
Reinforced Concrete Frame 2/12/2021 Partial Approval LEOPOLDO MENDOZA
Grading Pre-Inspection 2/17/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Deputy Other (see comments) 3/5/2021 Conditional Approval LEOPOLDO MENDOZA
Reinforced Concrete Frame 3/13/2021 Partial Approval ALAN NOVAK
Drywall Nailing 3/22/2021 Approved LEOPOLDO MENDOZA
Final 3/22/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Final 3/22/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Rough 3/22/2021 Approved LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 3/22/2021 SGSOV No Gas LEOPOLDO MENDOZA
Smoke Detectors 3/22/2021 Approved LEOPOLDO MENDOZA
Wood Frame 3/22/2021 Approved LEOPOLDO MENDOZA
Deputy Other (see comments) 3/23/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Other (see comments) 4/1/2021 Conditional Approval LEOPOLDO MENDOZA
Green Building Final 4/9/2021 Corrections Issued LEOPOLDO MENDOZA
Green Building Final 4/28/2021 Approved NICK LAROCCA
Final 5/6/2021 Partial Inspection SORIN CIRSTOIU
Final 5/13/2021 Partial Inspection SORIN CIRSTOIU
Final 7/6/2021 Partial Inspection SORIN CIRSTOIU
Final 7/8/2021 Conditional Approval SORIN CIRSTOIU