1660 N CASALE ROAD 90272
Certificate Information: 1660 N CASALE ROAD 90272
- Application / Permit
- 18014-10000-02163
- Plan Check / Job No.
- B18LA07800
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Building (to permitted use)
- Work Description
- DETACHED ACCESSORY TRELLIS STRUCTURE. 3 OF 5.
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Current Status
- CofO Issued on 1/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2018 | APPLICANT |
| Green Plans Picked Up | 5/3/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2018 | JOE VO |
| Corrections Issued | 5/21/2018 | JOE VO |
| Quality Review Completed | 5/23/2018 | GARO TELMI |
| Applicant returned to address corrections | 3/18/2021 | JOE VO |
| Applicant returned to address corrections | 3/22/2021 | JOE VO |
| Plan Check Approved | 6/9/2021 | JOE VO |
| Issued | 6/10/2021 | APPLICANT |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| CofO in Progress | 1/12/2026 | KEVIN SARGSYAN |
| Permit Finaled | 1/15/2026 | RICHARD STEINBACH |
| CofO Issued | 1/15/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/15/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Green Code | Cleared | 6/19/2018 | COLIN LOREDO |
Contact Information
| Contractor | Aragon Fine Homes Inc; Lic. No.: 992249-B | 766 NORTH WORKMAN STREET SAN FERNANDO, CA 91340 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/8/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/11/2023 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Final | 5/13/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 6/3/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 6/5/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 1/8/2026 | Approved | KEVIN SARGSYAN |
| Final | 1/8/2026 | OK to Issue CofO | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/8/2026 | Approved | KEVIN SARGSYAN |
| Green Building Final | 1/8/2026 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 1/8/2026 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Approved | KEVIN SARGSYAN |
| Service/Power Release | 1/8/2026 | Not Required | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 1/8/2026 | Approved | KEVIN SARGSYAN |