2433 N BIRKDALE ST 90031
Certificate Information: 2433 N BIRKDALE ST 90031
- Application / Permit
- 18014-10000-01955
- Plan Check / Job No.
- B18LA07109
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- RENOVATION AND IMPROVEMENT OF BUILDING. CHANGE OF USE FROM WAREHOUSE TO OFFICE. DEMO PORTION OF WAREHOUSE BUILDING, ADD (N) MEZZANINE SPACE, (N) RESTROOMS, (N) WINDOWS, (N) NON-BEARING PARTITIONS, (N) PLATFORM FOR MECHANICAL EQUIPMENT. change of construction from type III to type VB "COMPLY WITH DEPARTMENT ORDER effective date 05/27/2015. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 682166.
- Permit Issued
- Issued on 8/5/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2018 | DEAN RYAN REYES |
| Corrections Issued | 6/7/2018 | DEAN RYAN REYES |
| Disabled Access Plans Picked Up | 6/13/2018 | APPLICANT |
| Green Plans Picked Up | 6/13/2018 | APPLICANT |
| Quality Review Completed | 6/21/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 6/25/2018 | APPLICANT |
| Applicant returned to address corrections | 8/20/2018 | DEAN RYAN REYES |
| Applicant returned to address corrections | 12/31/2018 | DEAN RYAN REYES |
| Applicant returned to address corrections | 1/30/2019 | DEAN RYAN REYES |
| Applicant returned to address corrections | 5/3/2019 | DEAN RYAN REYES |
| Plan Check Approved | 5/22/2019 | DEAN RYAN REYES |
| Issued | 8/5/2019 | LADBS |
| CofO in Progress | 4/5/2023 | GREGORY POMISH |
| Permit Finaled | 4/5/2023 | TERRY HERR |
| CofO Issued | 4/5/2023 | TERRY HERR |
| Permit Finaled | 4/5/2023 | TERRY HERR |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/3/2018 | DIANA JIMENEZ |
| Miscellaneous | Cleared | 7/3/2018 | DIANA JIMENEZ |
| Permit | Cleared | 7/3/2018 | NAZILA NOORIFAR |
| ZA Case | Cleared | 7/3/2018 | DIANA JIMENEZ |
| ZA Case | Cleared | 7/3/2018 | DIANA JIMENEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2018 | JEANETTE VONG |
| Sewer availability | Cleared | 10/16/2018 | JEANETTE VONG |
| DAS Clearance | Cleared | 10/26/2018 | WAI LAU |
| "Q" conditions | Cleared | 11/2/2018 | ANNA VAN |
| Prkng lot landscape/Water mgmt | Cleared | 11/2/2018 | ANNA VAN |
| ZI | Cleared | 11/2/2018 | ANNA VAN |
| ZI | Cleared | 11/2/2018 | ANNA VAN |
| Green Code | Cleared | 12/3/2018 | SARAH ABOULHOSN |
| Low Impact Development | Cleared | 4/2/2019 | RYAN HUDSON |
| Construction near power lines | Cleared | 4/19/2019 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 5/7/2019 | ADRIAN SANCHEZ |
Contact Information
| Architect | Rios,, Mark William; Lic. No.: C15744 | 639 N LARCHMONT BLVD SUITE 100 LOS ANGELES, CA 90004 |
| Contractor | Hopkins George C Construction Co Inc; Lic. No.: 397266-B | 919 W GLENOAKS BLVD GLENDALE, CA 91202 |
| Engineer | Dennis, Boratynec; Lic. No.: GE2770 | , |
| Engineer | Kathuria,, Deepansh; Lic. No.: S5572 | 707 WILSHIRE BLVD STE 5100 LOS ANGELES, CA 90017 |
| Engineer | Kawamura,, James Hiroshi; Lic. No.: C30560 | 31412 OLD SAN JUAN RD SAN JUAN CAPISTRANO, CA 92675 |
| Engineer | Zellmer, Brad T; Lic. No.: GE2618 | 635 W BAKER APT U202 COSTA MESA, CA 92626 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 9/4/2019 | Corrections Issued | JEFFREY FULTON |
| Pre-Inspection | 11/22/2019 | Partial Inspection | JEFFREY FULTON |
| Piling/Pier/Caisson | 11/25/2019 | Partial Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 12/24/2019 | No Access for Inspection | ERNESTO CORRAL |
| Piling/Pier/Caisson | 12/24/2019 | Not Ready for Inspection | ERNESTO CORRAL |
| Piling/Pier/Caisson | 1/2/2020 | Partial Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 1/3/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/6/2020 | Conditional Approval | ERNESTO CORRAL |
| Footing/Foundation/Slab | 1/8/2020 | Partial Inspection | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 1/9/2020 | Conditional Approval | ERNESTO CORRAL |
| Footing/Foundation/Slab | 1/17/2020 | Partial Inspection | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 1/21/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 1/23/2020 | Conditional Approval | RONALD PACHECO |
| Reinforced Concrete Frame | 1/23/2020 | Partial Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 1/28/2020 | Conditional Approval | RONALD PACHECO |
| Reinforced Masonry Frame | 1/28/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 1/29/2020 | Conditional Approval | RONALD PACHECO |
| Reinforced Masonry Frame | 1/30/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 2/5/2020 | Conditional Approval | RONALD PACHECO |
| Drywall Nailing | 2/7/2020 | Not Ready for Inspection | RONALD PACHECO |
| Final | 2/7/2020 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Final | 2/7/2020 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Rough | 2/7/2020 | Not Ready for Inspection | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 2/7/2020 | SGSOV Not Ready | RONALD PACHECO |
| Smoke Detectors | 2/7/2020 | Not Ready for Inspection | RONALD PACHECO |
| Special/Order Compliance | 2/7/2020 | Not Ready for Inspection | RONALD PACHECO |
| Structural Steel Frame | 2/7/2020 | Not Ready for Inspection | RONALD PACHECO |
| Wall Anchors | 2/7/2020 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 2/7/2020 | Not Ready for Inspection | RONALD PACHECO |
| Deputy Steel/Welding | 2/13/2020 | No Access for Inspection | LANNY MERRICK |
| Footing/Foundation/Slab | 2/13/2020 | Partial Approval | RONALD PACHECO |
| Reinforced Concrete Frame | 2/13/2020 | Partial Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 2/14/2020 | Conditional Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 2/18/2020 | Partial Approval | RONALD PACHECO |
| Reinforced Concrete Frame | 2/20/2020 | Partial Approval | RONALD PACHECO |
| Excavation/Setback/Form/Re-Bar | 2/24/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Steel/Welding | 2/28/2020 | Approved | LANNY MERRICK |
| Footing/Foundation/Slab | 2/28/2020 | Partial Approval | RONALD PACHECO |
| Light Gage Steel Frame | 2/28/2020 | Conditional Approval | RONALD PACHECO |
| Excavation/Setback/Form/Re-Bar | 3/2/2020 | Partial Inspection | ERNESTO CORRAL |
| Deputy Steel/Welding | 3/6/2020 | Conditional Approval | LANNY MERRICK |
| Reinforced Concrete Frame | 3/6/2020 | Conditional Approval | RONALD PACHECO |
| Drywall Nailing | 4/17/2020 | Partial Approval | RONALD PACHECO |
| Green Building Rough | 4/17/2020 | Not Ready for Inspection | RONALD PACHECO |
| Insulation | 4/17/2020 | Not Ready for Inspection | RONALD PACHECO |
| Light Gage Steel Frame | 4/17/2020 | Conditional Approval | RONALD PACHECO |
| Insulation | 4/27/2020 | Partial Approval | RONALD PACHECO |
| Interior/Exterior Lathing | 4/27/2020 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 5/6/2020 | Partial Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 5/6/2020 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Rough | 5/6/2020 | Approved | RONALD PACHECO |
| Insulation | 5/6/2020 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 5/8/2020 | Partial Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 5/8/2020 | Partial Approval | RONALD PACHECO |
| Insulation | 5/12/2020 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 5/14/2020 | Not Ready for Inspection | RONALD PACHECO |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Not Ready for Inspection | RONALD PACHECO |
| Reinforced Masonry Frame | 5/14/2020 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 5/20/2020 | Not Ready for Inspection | RONALD PACHECO |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2020 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 5/21/2020 | Not Ready for Inspection | RONALD PACHECO |
| Insulation | 5/21/2020 | Not Ready for Inspection | RONALD PACHECO |
| Drywall Nailing | 6/2/2020 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 6/4/2020 | Approved | RONALD PACHECO |
| Insulation | 6/4/2020 | Partial Approval | RONALD PACHECO |
| Reinforced Concrete Frame | 6/4/2020 | Partial Approval | RONALD PACHECO |
| Pre-Inspection | 6/17/2020 | Partial Inspection | RONALD PACHECO |
| Final | 9/29/2020 | Corrections Issued | RONALD PACHECO |
| Footing/Foundation/Slab | 9/29/2020 | Approved | RONALD PACHECO |
| Green Building Final | 9/29/2020 | Not Ready for Inspection | RONALD PACHECO |
| Insulation | 9/29/2020 | Approved | RONALD PACHECO |
| Pre-Inspection | 9/29/2020 | Approved | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 9/29/2020 | SGSOV Not Ready | RONALD PACHECO |
| Smoke Detectors | 9/29/2020 | Not Ready for Inspection | RONALD PACHECO |
| Structural Steel Frame | 9/29/2020 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 9/29/2020 | Approved | RONALD PACHECO |
| Final | 12/1/2020 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Final | 12/1/2020 | Not Ready for Inspection | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 12/1/2020 | SGSOV Not Ready | RONALD PACHECO |
| Smoke Detectors | 12/1/2020 | Not Ready for Inspection | RONALD PACHECO |
| Structural Steel Frame | 12/1/2020 | Not Ready for Inspection | RONALD PACHECO |
| Final | 9/19/2022 | Conditional Approval | MARK FERRARI |
| Green Building Final | 9/19/2022 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV No Gas | MARK FERRARI |
| Smoke Detectors | 9/19/2022 | Approved | MARK FERRARI |
| Structural Steel Frame | 9/19/2022 | Approved | MARK FERRARI |
| Final | 9/28/2022 | Conditional Approval | MARK FERRARI |
| Pre-Inspection | 9/28/2022 | Partial Approval | MARK FERRARI |
| Final | 12/5/2022 | Conditional Approval | MARK FERRARI |
| Final | 2/13/2023 | Conditional Approval | RAFAEL CORTES |
| Final | 2/27/2023 | Not Ready for Inspection | RAFAEL CORTES |