3865 N FILION ST 90065

Certificate Information: 3865 N FILION ST 90065

Application / Permit
18014-10000-01679
Plan Check / Job No.
B18LA06107
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD NEW ROOF DECK WITH CONVERED PATIO AT REAR OF SFD.
Permit Issued
Issued on 6/18/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2018 APPLICANT
Assigned to Plan Check Engineer 4/19/2018 MENA WASSEF
Corrections Issued 5/7/2018 MENA WASSEF
Quality Review Completed 5/8/2018 STEVEN KIM
Building Plans Picked Up 6/15/2018 APPLICANT
Green Plans Picked Up 10/22/2018 APPLICANT
Applicant returned to address corrections 12/26/2018 RODNEY SAMIIAN
Plan Check Approved 6/11/2019 RODNEY SAMIIAN
Issued 6/18/2019 LADBS
CofO in Progress 12/30/2021 HAMIK HARTOUNIAN
Permit Finaled 4/6/2022 RONALD MYRICK
CofO Issued 4/6/2022 RONALD MYRICK
Permit Finaled 4/6/2022 RONALD MYRICK

Permit Application Clearance Information

Green Code Cleared 1/24/2019 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 3/14/2019 ELAINE LEI
Grading Pre-Inspection Cleared 3/14/2019 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 3/14/2019 ELAINE LEI
Supp. Use District POD/CDO/TDO Cleared 5/15/2019 NICOLE SANCHEZ
ZI Cleared 5/15/2019 NICOLE SANCHEZ

Contact Information

Contractor Geoworks Engineering Group Inc; Lic. No.: 983141-A 5158 COCHRAN STREET      SIMI VALLEY, CA 93063
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 7/11/2019 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 7/15/2019 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/15/2019 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 9/18/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Structural Steel Frame 9/18/2019 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 9/27/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Structural Steel Frame 9/27/2019 Partial Approval HAMIK HARTOUNIAN
Deputy Steel/Welding 9/30/2019 Conditional Approval HAMIK HARTOUNIAN
Pre-Inspection 10/30/2019 Partial Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/24/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 1/24/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Structural Steel Frame 1/24/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 1/24/2020 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/7/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 10/7/2020 Approved HAMIK HARTOUNIAN
Wood Frame 10/7/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/15/2020 Approved HAMIK HARTOUNIAN
Final 4/12/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/12/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 4/12/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/12/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 4/12/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Structural Steel Frame 4/12/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Final 4/29/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/29/2021 Approved HAMIK HARTOUNIAN
Green Building Final 4/29/2021 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/29/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 4/29/2021 Approved HAMIK HARTOUNIAN
Structural Steel Frame 4/29/2021 Approved HAMIK HARTOUNIAN
Final 7/26/2021 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/26/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Final 8/30/2021 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/30/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Final 9/8/2021 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/8/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Final 11/5/2021 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/5/2021 SGSOV Approved HAMIK HARTOUNIAN
Special/Order Compliance 11/5/2021 Partial Inspection ALIZAH MAYAGOITIA
Special/Order Compliance 11/5/2021 Partial Inspection AMY COLIN
Final 12/30/2021 OK to Issue CofO HAMIK HARTOUNIAN