3434 N GARDENSIDE LANE 90039

Certificate Information: 3434 N GARDENSIDE LANE 90039

Application / Permit
18014-10000-01584
Plan Check / Job No.
B18LA05765
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Add 6'-3" x 14'-6" to (E) One-Story Single Family Dwelling.
Permit Issued
Issued on 7/20/2021
Issuing Office
Current Status
CofO Issued on 3/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 OMID HEDAYAT
Corrections Issued 4/16/2018 OMID HEDAYAT
Quality Review Completed 4/17/2018 CHON CHIO KUO
Building Plans Picked Up 4/24/2018 APPLICANT
Applicant returned to address corrections 6/19/2018 OMID HEDAYAT
Applicant returned to address corrections 7/5/2018 OMID HEDAYAT
Plan Check Approved 7/5/2018 OMID HEDAYAT
Issued 7/20/2021 APPLICANT
CofO in Progress 2/24/2023 HAMIK HARTOUNIAN
Permit Finaled 3/2/2023 DEROLD HAUFF
CofO Issued 3/2/2023 DEROLD HAUFF
Permit Finaled 3/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/1/2018 MICHAEL CASTILLO
Sewer availability Cleared 5/1/2018 MICHAEL CASTILLO
Low Impact Development Cleared 5/15/2018 MATTHEW JIMENEZ
Green Code Cleared 6/6/2018 DONALD CRICHLOW
Roof/Waste drainage to street Cleared 7/5/2018 MICHAEL CASTILLO

Contact Information

Architect Lee, Joong H; Lic. No.: C26271 3130 WILSHIRE BLVD # 301      LOS ANGELES, CA 90010
Contractor Owner-Builder       ,
Engineer Park, Juntae; Lic. No.: C65104 1444 HI POINT ST      LOS ANGELES, CA 90035

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/17/2021 Partial Inspection RICHARD STEINBACH
Footing/Foundation/Slab 9/28/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/5/2021 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 11/18/2021 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/8/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/8/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 2/8/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 2/8/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/4/2022 Partial Approval AMY COLIN
Green Building Rough 3/4/2022 Not Ready for Inspection AMY COLIN
HVAC-Rough 3/4/2022 Not Ready for Inspection AMY COLIN
Deputy Wood Construction 3/11/2022 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/14/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 3/14/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 3/14/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/29/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 4/5/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/5/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 4/28/2022 Approved CHARLES BOGHOSKHAN
Insulation 4/28/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 5/9/2022 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 9/7/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 9/7/2022 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 9/7/2022 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 11/23/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 11/23/2022 Not Ready for Inspection RICHARD DOCKUS
HVAC-Final 11/23/2022 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Final 11/23/2022 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Final 12/28/2022 Corrections Issued HAMIK HARTOUNIAN
Final 12/28/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/28/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 12/28/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 12/28/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 1/4/2023 Approved HAMIK HARTOUNIAN
Final 1/4/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/4/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/4/2023 SGSOV Approved HAMIK HARTOUNIAN
Final 2/1/2023 Corrections Issued HAMIK HARTOUNIAN
Final 2/24/2023 OK to Issue CofO HAMIK HARTOUNIAN