3434 N GARDENSIDE LANE 90039
Certificate Information: 3434 N GARDENSIDE LANE 90039
- Application / Permit
- 18014-10000-01584
- Plan Check / Job No.
- B18LA05765
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add 6'-3" x 14'-6" to (E) One-Story Single Family Dwelling.
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Current Status
- CofO Issued on 3/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2018 | OMID HEDAYAT |
| Corrections Issued | 4/16/2018 | OMID HEDAYAT |
| Quality Review Completed | 4/17/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 4/24/2018 | APPLICANT |
| Applicant returned to address corrections | 6/19/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/5/2018 | OMID HEDAYAT |
| Plan Check Approved | 7/5/2018 | OMID HEDAYAT |
| Issued | 7/20/2021 | APPLICANT |
| CofO in Progress | 2/24/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 3/2/2023 | DEROLD HAUFF |
| CofO Issued | 3/2/2023 | DEROLD HAUFF |
| Permit Finaled | 3/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 5/1/2018 | MICHAEL CASTILLO |
| Low Impact Development | Cleared | 5/15/2018 | MATTHEW JIMENEZ |
| Green Code | Cleared | 6/6/2018 | DONALD CRICHLOW |
| Roof/Waste drainage to street | Cleared | 7/5/2018 | MICHAEL CASTILLO |
Contact Information
| Architect | Lee, Joong H; Lic. No.: C26271 | 3130 WILSHIRE BLVD # 301 LOS ANGELES, CA 90010 |
| Contractor | Owner-Builder | , |
| Engineer | Park, Juntae; Lic. No.: C65104 | 1444 HI POINT ST LOS ANGELES, CA 90035 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/17/2021 | Partial Inspection | RICHARD STEINBACH |
| Footing/Foundation/Slab | 9/28/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/5/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/18/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/8/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 2/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/8/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/4/2022 | Partial Approval | AMY COLIN |
| Green Building Rough | 3/4/2022 | Not Ready for Inspection | AMY COLIN |
| HVAC-Rough | 3/4/2022 | Not Ready for Inspection | AMY COLIN |
| Deputy Wood Construction | 3/11/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/14/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 3/14/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/14/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/29/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 4/5/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/5/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/28/2022 | Approved | CHARLES BOGHOSKHAN |
| Insulation | 4/28/2022 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 5/9/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 9/7/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 9/7/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 9/7/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 11/23/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 11/23/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Final | 11/23/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 11/23/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 12/28/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 12/28/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/28/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 12/28/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/28/2022 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 1/4/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 1/4/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/4/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 2/1/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 2/24/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |