4578 N ROUND TOP DR 90065

Certificate Information: 4578 N ROUND TOP DR 90065

Application / Permit
18014-10000-01574
Plan Check / Job No.
B18LA05707
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 28'1-1/2" X 42'8" IRREGULAR SHAPED 1ST FLOOOR ADDITION TO (E) SFD TO CREATE NEW (1) BEDROOMS, (2) BATHROOMS , NEW W.I.C., NEW LAUNDRY , INTERIOR REMODEL AT 1ST FLOOR TO CREATE NEW BEDROOM, ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 RARES BODEA
Corrections Issued 4/15/2018 RARES BODEA
Green Plans Picked Up 4/18/2018 APPLICANT
Quality Review Completed 4/19/2018 DOUGLAS NAKATANI
Building Plans Picked Up 4/23/2018 APPLICANT
Plan Check Approved 2/18/2020 RARES BODEA
Issued 3/3/2020 LADBS
CofO in Progress 8/20/2021 CRAIG VAUGHAN
Permit Finaled 5/3/2022 DEROLD HAUFF
CofO Issued 5/3/2022 DEROLD HAUFF
Permit Finaled 5/3/2022 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/1/2018 ADRIAN SANCHEZ
Distance to fire station Cleared 6/1/2018 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 6/1/2018 ADRIAN SANCHEZ
Green Code Cleared 6/1/2018 KHEDER ALRAZAA
Hydrant and Access approval Cleared 6/1/2018 JOHN CONNEALLY
Sewer availability Cleared 6/1/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 7/13/2018 NAZILA NOORIFAR
Low Impact Development Cleared 12/24/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/5/2020 THOMAS LANG
Supp. Use District POD/CDO/TDO Cleared 2/12/2020 JASON CHAN
GPI Written Notices Cleared 2/18/2020 RARES BODEA
Grading Pre-Inspection Cleared 2/18/2020 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Kazarians, Ardashes; Lic. No.: C36687 1528 CANADA BLVD STE 206      GLENDALE, CA 91208
Engineer Mahn, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Geologist Pongracz-Bartha,, Ed; Lic. No.: EG2370 10501 COLLETT AVE      GRANADA HILLS, CA 91344
Geologist Triebold, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/27/2020 Partial Inspection COREY HUPP
Footing/Foundation/Slab 4/14/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 4/21/2020 Partial Approval CRAIG VAUGHAN
Deputy Reinf. Masonry 4/30/2020 No Access for Inspection CRAIG VAUGHAN
PLUMBING-Rough 5/20/2020 Partial Approval RUBEN SALAS
Footing/Foundation/Slab 6/2/2020 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/27/2020 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 8/27/2020 Corrections Issued KATHRYN BUTTERWORTH
Green Building Rough 8/27/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
MERV13>=Rough 8/27/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 8/27/2020 Corrections Issued KATHRYN BUTTERWORTH
Wood Frame 8/27/2020 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/1/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 9/1/2020 Approved CRAIG VAUGHAN
Green Building Rough 9/1/2020 Approved CRAIG VAUGHAN
HVAC-Rough 9/1/2020 Corrections Issued CRAIG VAUGHAN
MERV13>=Rough 9/1/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 9/1/2020 Approved CRAIG VAUGHAN
HVAC-Rough 9/8/2020 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/8/2020 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 9/14/2020 Approved CRAIG VAUGHAN
Insulation 9/14/2020 Approved CRAIG VAUGHAN
Special/Order Compliance 9/14/2020 Approved THOMAS LOGRASSO
Drywall Nailing 9/23/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/23/2020 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 3/24/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Final 3/24/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 3/24/2021 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 3/24/2021 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 3/24/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 3/24/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/24/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 3/24/2021 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 6/3/2021 Corrections Issued CRAIG VAUGHAN
Final 6/3/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 6/3/2021 Approved CRAIG VAUGHAN
HVAC-Final 6/3/2021 Corrections Issued CRAIG VAUGHAN
MERV13>=Final 6/3/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 6/3/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 6/3/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 6/3/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 8/19/2021 Approved CRAIG VAUGHAN
Final 8/19/2021 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 8/19/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 8/19/2021 Approved CRAIG VAUGHAN