4426 1/2 S 10TH AVE 90043
Certificate Information: 4426 1/2 S 10TH AVE 90043
- Application / Permit
- 18014-10000-01524
- Plan Check / Job No.
- B18LA05490
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE INTO ACCESSORY DWELLING UNIT; SCOPE WILL ALSO CONSIST OF A 204 SQ-FT ADDITION.
- Permit Issued
- Issued on 6/1/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2018 | MICHAEL LOPEZ |
| Corrections Issued | 4/3/2018 | MICHAEL LOPEZ |
| Plan Check Approved | 6/1/2018 | MICHAEL LOPEZ |
| Issued | 6/1/2018 | LADBS |
| CofO in Progress | 6/5/2026 | LUIS CASTRO |
| Permit Finaled | 6/8/2026 | DEROLD HAUFF |
| CofO Issued | 6/8/2026 | DEROLD HAUFF |
| Permit Finaled | 6/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/3/2018 | MICHAEL CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 6/1/2018 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/1/2018 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 6/1/2018 | ADRIAN SANCHEZ |
Contact Information
| Contractor | La Rocca Builders Inc; Lic. No.: 934161-B | 565 N ARDEN BLVD LOS ANGELES, CA 90004 |
| Engineer | Basso, Alexandre; Lic. No.: C77670 | 3045 COMMUNITY AVENUE LA CRESCENTA, CA 91214 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2018 | Approved | BOB GOBUTY |
| ELECTRICAL-Rough | 1/8/2019 | Not Ready for Inspection | LUIS ALVAREZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2019 | Approved | LUIS ALVAREZ |
| Green Building Rough | 1/8/2019 | Not Ready for Inspection | LUIS ALVAREZ |
| HVAC-Rough | 1/8/2019 | Not Ready for Inspection | LUIS ALVAREZ |
| PLUMBING-Rough | 1/8/2019 | Not Ready for Inspection | LUIS ALVAREZ |
| BUILDING-Rough-Frame | 5/2/2019 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 5/2/2019 | Not Ready for Inspection | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 5/2/2019 | Not Ready for Inspection | COREY HUPP |
| Sewer | 5/2/2019 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 5/15/2019 | Not Ready for Inspection | COREY HUPP |
| HVAC-Rough | 5/15/2019 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 5/15/2019 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 6/4/2019 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 6/4/2019 | Not Ready for Inspection | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 6/4/2019 | Partial Approval | COREY HUPP |
| Sewer | 6/4/2019 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 6/27/2019 | Partial Approval | COREY HUPP |
| Green Building Rough | 6/27/2019 | Approved | COREY HUPP |
| PLUMBING-Rough | 6/27/2019 | Approved | COREY HUPP |
| Sewer | 6/27/2019 | Approved | COREY HUPP |
| Insulation | 7/11/2019 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 7/11/2019 | Not Ready for Inspection | COREY HUPP |
| Drywall Nailing | 9/16/2019 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 9/16/2019 | Partial Inspection | COREY HUPP |
| ELECTRICAL-Final | 5/2/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 5/2/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 5/2/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 5/2/2023 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 5/2/2023 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | ANTHONY EGSON |
| Final | 12/19/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 12/19/2023 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 12/19/2023 | Approved | ANTHONY EGSON |
| Final | 1/5/2026 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 1/5/2026 | Not Ready for Inspection | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 1/5/2026 | SGSOV Not Ready | LUIS CASTRO |
| Final | 4/21/2026 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 4/21/2026 | Approved | LUIS CASTRO |
| HVAC-Final | 4/21/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/21/2026 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Approved | LUIS CASTRO |
| ELECTRICAL-Final | 5/11/2026 | Approved | LUIS CASTRO |
| Final | 5/11/2026 | OK to Issue CofO | LUIS CASTRO |
| Service/Power Release | 5/11/2026 | Approved | LUIS CASTRO |
| Service/Power Release | 6/5/2026 | Approved | LUIS CASTRO |