2642 S MIDVALE AVE 90064

Certificate Information: 2642 S MIDVALE AVE 90064

Application / Permit
18014-10000-01111
Plan Check / Job No.
B18LA03948
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADU ADDITION OVER (E) GARAGE PER AB494 AND SB229 W/ (N) EXTERIOR STAIRS;EXTERIOR ALTERATIONS TO (E) GARAGE TO ADD (N) WINDOWS.
Permit Issued
Issued on 12/4/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2018 APPLICANT
Assigned to Plan Check Engineer 3/15/2018 JEFFREY MACHADO
Green Plans Picked Up 3/22/2018 APPLICANT
Corrections Issued 3/27/2018 JEFFREY MACHADO
Quality Review Completed 4/6/2018 MINYE PAK
Building Plans Picked Up 4/9/2018 APPLICANT
Plan Check Approved 9/9/2019 JEFFREY MACHADO
Issued 12/4/2019 LADBS
CofO in Progress 6/24/2025 MICHAEL PELHAM
Permit Finaled 6/25/2025 RICHARD STEINBACH
CofO Issued 6/25/2025 RICHARD STEINBACH
Permit Finaled 6/25/2025 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 7/27/2019 RIDWAN HARDY
Address approval Cleared 7/31/2019 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 7/31/2019 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 8/7/2019 ROBYN STEELE
Sewer availability Cleared 8/7/2019 ROBYN STEELE
Green Code Cleared 8/12/2019 JEFFREY MACHADO
Grading Pre-Inspection Cleared 8/27/2019 JEFFREY MACHADO

Contact Information

Contractor Delta Remodeling Inc; Lic. No.: 913496-B 8309 TUJUNGA AVENUE #105      SUN VALLEY, CA 91352
Engineer Khanjian, Hovik J; Lic. No.: C51609 326 S. SPARKS STREET      BURBANK, CA 91506

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/18/2019 Approved KEVIN BEAULIEU
Excavation/Setback/Form/Re-Bar 12/27/2019 Conditional Approval KEVIN BEAULIEU
Sewer 9/24/2020 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 11/25/2020 Not Ready for Inspection RICHARD ROBLES
ELECTRICAL-Rough 11/25/2020 Corrections Issued RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 11/25/2020 Corrections Issued RICHARD ROBLES
Green Building Rough 11/25/2020 Not Ready for Inspection RICHARD ROBLES
PLUMBING-Rough 11/25/2020 Approved RICHARD ROBLES
Underground Mechanical 11/25/2020 Approved RICHARD ROBLES
ELECTRICAL-Rough 12/16/2020 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2020 Partial Approval KEVIN SARGSYAN
HVAC-Rough 12/16/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 1/20/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Partial Approval EVAN COOPER
HVAC-Rough 1/20/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 1/27/2021 Approved RICHARD ROBLES
Green Building Rough 1/27/2021 Approved RICHARD ROBLES
Interior/Exterior Lathing 1/27/2021 Approved RICHARD ROBLES
Shower Pan 1/27/2021 Approved RICHARD ROBLES
Insulation 2/5/2021 Approved RICHARD ROBLES
Drywall Nailing 2/10/2021 Approved RICHARD ROBLES
ELECTRICAL-Final 6/9/2022 Approved JOHNNY MIRANDA
Final 6/9/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 6/9/2022 Approved JOHNNY MIRANDA
Green Building Final 6/9/2022 Approved JOHNNY MIRANDA
HVAC-Final 6/9/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 6/9/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 6/9/2022 Approved JOHNNY MIRANDA
Final 6/24/2025 OK to Issue CofO MICHAEL PELHAM