4320 W 10TH ST 90019
Certificate Information: 4320 W 10TH ST 90019
- Application / Permit
- 18014-10000-01014
- Plan Check / Job No.
- B18LA03595
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229; SCOPE WILL ALSO CONSIST OF A 405 SQ-FT ADDITION.
- Permit Issued
- Issued on 11/19/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2018 | MICHAEL LOPEZ |
| Corrections Issued | 3/19/2018 | MICHAEL LOPEZ |
| Quality Review Completed | 3/20/2018 | DAVID CHANG |
| Applicant returned to address corrections | 8/24/2018 | MICHAEL LOPEZ |
| Green Plans Picked Up | 8/24/2018 | APPLICANT |
| Plan Check Approved | 9/19/2018 | MICHAEL LOPEZ |
| Plan Check Approved | 10/24/2018 | MICHAEL LOPEZ |
| Issued | 11/19/2018 | LADBS |
| CofO in Progress | 5/13/2025 | JEFFREY MEAD |
| Permit Finaled | 5/15/2025 | DEROLD HAUFF |
| CofO Issued | 5/15/2025 | DEROLD HAUFF |
| Permit Finaled | 5/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2018 | JAMES MORALEZ |
| CPC | Cleared | 6/15/2018 | DANALYNN DOMINGUEZ |
| CPC | Cleared | 6/15/2018 | DANALYNN DOMINGUEZ |
| CPC | Cleared | 6/15/2018 | DANALYNN DOMINGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2018 | JAMES MORALEZ |
| Roof/Waste drainage to street | Cleared | 6/15/2018 | JAMES MORALEZ |
| Sewer availability | Cleared | 6/15/2018 | JAMES MORALEZ |
| HPOZ | Cleared | 8/30/2018 | BRADLEY FURUYA |
| Green Code | Cleared | 9/10/2018 | KHEDER ALRAZAA |
| Green Code | Cleared | 9/10/2018 | MICHAEL LOPEZ |
Contact Information
| Architect | Fong, Hoyu; Lic. No.: C34057 | 713 WEST DUARTE ROAD SUITE G205 ARCADIA, CA 91007 |
| Contractor | P & S Engineering Inc; Lic. No.: 1031273-B | 947 S GRAMERCY DR LOS ANGELES, CA 90019 |
| Engineer | Chen, Dan; Lic. No.: C47140 | 20548 VEJAR RD WALNUT, CA 91789 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/7/2019 | No Access for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/30/2019 | Corrections Issued | DANIEL GONZALEZ |
| METHANE-Barrier | 1/30/2019 | Not Ready for Inspection | DANIEL GONZALEZ |
| METHANE-Subgrade | 1/30/2019 | Not Ready for Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 2/14/2019 | Not Ready for Inspection | LUIS BARRALES |
| METHANE-Barrier | 2/14/2019 | Not Ready for Inspection | LUIS BARRALES |
| METHANE-Subgrade | 2/14/2019 | Not Ready for Inspection | LUIS BARRALES |
| Pre-Inspection | 2/15/2019 | Corrections Issued | LUIS BARRALES |
| Footing/Foundation/Slab | 2/20/2019 | Approved | LUIS BARRALES |
| METHANE-Barrier | 2/20/2019 | Approved | LUIS BARRALES |
| METHANE-Subgrade | 2/20/2019 | Approved | LUIS BARRALES |
| PLUMBING-Rough | 4/2/2019 | Corrections Issued | PIERRE VEGA |
| Wood Frame | 4/2/2019 | Not Ready for Inspection | PIERRE VEGA |
| PLUMBING-Rough | 4/5/2019 | Partial Approval | LUIS BARRALES |
| Wood Frame | 4/5/2019 | Corrections Issued | LUIS BARRALES |
| Insulation | 4/9/2019 | Partial Approval | LUIS BARRALES |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2019 | Partial Approval | LUIS BARRALES |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2019 | Partial Approval | LUIS BARRALES |
| PLUMBING-Rough | 8/21/2019 | Approved | LUIS BARRALES |
| ELECTRICAL-Rough | 8/27/2019 | Approved | LUIS BARRALES |
| HVAC-Rough | 8/27/2019 | Approved | LUIS BARRALES |
| Wood Frame | 8/28/2019 | Not Ready for Inspection | LUIS BARRALES |
| Wood Frame | 8/30/2019 | Corrections Issued | LUIS BARRALES |
| Pre-Inspection | 11/14/2019 | Corrections Issued | LUIS BARRALES |
| ELECTRICAL-Rough | 11/22/2019 | Partial Approval | LUIS BARRALES |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2019 | Approved | LUIS BARRALES |
| HVAC-Rough | 11/22/2019 | Partial Approval | LUIS BARRALES |
| Interior/Exterior Lathing | 11/22/2019 | Approved | LUIS BARRALES |
| Pre-Inspection | 11/22/2019 | Approved | LUIS BARRALES |
| Wood Frame | 11/22/2019 | Partial Approval | LUIS BARRALES |
| Wood Frame | 12/12/2019 | Not Ready for Inspection | LUIS BARRALES |
| Excavation/Setback/Form/Re-Bar | 2/5/2020 | Partial Approval | LUIS BARRALES |
| Wood Frame | 3/2/2020 | Corrections Issued | MICHAEL FAUNCE |
| METHANE-Barrier | 3/9/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 3/13/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Insulation | 3/17/2020 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 3/24/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/17/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 6/18/2020 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 6/18/2020 | Approved | ARTHUR SARGSYAN |
| Final | 6/18/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 6/18/2020 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 6/18/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 6/18/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Final | 6/18/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 6/18/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 6/18/2020 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2020 | SGSOV Approved | ARTHUR SARGSYAN |
| Service/Power Release | 6/18/2020 | Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 6/18/2020 | Approved | ARTHUR SARGSYAN |
| Final | 4/16/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 4/16/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 4/18/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 5/1/2025 | Corrections Issued | JEFFREY MEAD |
| Final | 5/12/2025 | OK to Issue CofO | JEFFREY MEAD |