19102 W WELBY WAY 91335

Certificate Information: 19102 W WELBY WAY 91335

Application / Permit
18014-10000-00792
Plan Check / Job No.
B18LA02808
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to Existing Garage and Convert New Detached ADU PER AB-494 and SB-229.
Permit Issued
Issued on 8/6/2018
Issuing Office
Metro
Current Status
CofO Issued on 6/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2018 APPLICANT
Assigned to Plan Check Engineer 3/1/2018 ZAW HAN
Corrections Issued 3/12/2018 ZAW HAN
Quality Review Completed 3/16/2018 KESETE HAREGOT
Building Plans Picked Up 3/23/2018 APPLICANT
Green Plans Picked Up 3/23/2018 APPLICANT
Applicant returned to address corrections 5/15/2018 ZAW HAN
Applicant returned to address corrections 6/26/2018 ZAW HAN
Plan Check Approved 7/18/2018 Zaw Han
Issued 8/6/2018 LADBS
CofO in Progress 5/25/2021 VINCENT HANLEY
Permit Finaled 6/3/2021 JOHN JANSON
CofO Issued 6/3/2021 JOHN JANSON
Permit Finaled 6/3/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/14/2018 MICHAEL CASTILLO
Permit Cleared 5/14/2018 MICHAEL CASTILLO
Green Code Cleared 5/17/2018 NEGAR NEJAD
ZI Cleared 5/25/2018 FIPE LEILUA
Construction near power lines Cleared 5/30/2018 WALTER RAMIREZ
Construction within easement Cleared 5/30/2018 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/31/2018 ADRIAN SANCHEZ
Low Impact Development Cleared 5/31/2018 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 5/31/2018 JAMES MORALEZ
Sewer availability Cleared 5/31/2018 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/5/2020 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 5/5/2020 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 8/12/2020 Approved VINCENT HANLEY
PLUMBING-Rough 9/22/2020 Partial Approval VINCENT HANLEY
Sewer 9/22/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/9/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Partial Approval VINCENT HANLEY
PLUMBING-Rough 11/13/2020 No Access for Inspection VINCENT HANLEY
PLUMBING-Rough 11/18/2020 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 12/14/2020 Approved VINCENT HANLEY
HVAC-Rough 12/22/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/8/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/8/2021 Approved VINCENT HANLEY
Pre-Inspection 1/8/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/19/2021 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 1/22/2021 Approved VINCENT HANLEY
Green Building Rough 1/22/2021 Approved VINCENT HANLEY
Insulation 1/22/2021 Approved VINCENT HANLEY
Wood Frame 1/22/2021 Approved VINCENT HANLEY
Drywall Nailing 1/29/2021 Partial Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 2/2/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 2/4/2021 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/18/2021 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 2/18/2021 Approved VINCENT HANLEY
Drywall Nailing 5/12/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 5/12/2021 Approved VINCENT HANLEY
Final 5/12/2021 Corrections Issued VINCENT HANLEY
Green Building Final 5/12/2021 Approved VINCENT HANLEY
HVAC-Final 5/12/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/12/2021 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 5/12/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 5/20/2021 Corrections Issued VINCENT HANLEY
Final 5/20/2021 Not Ready for Inspection VINCENT HANLEY
HVAC-Final 5/20/2021 Approved VINCENT HANLEY
PLUMBING-Final 5/20/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/20/2021 SGSOV Approved VINCENT HANLEY
Final 5/25/2021 OK to Issue CofO VINCENT HANLEY