19102 W WELBY WAY 91335
Certificate Information: 19102 W WELBY WAY 91335
- Application / Permit
- 18014-10000-00792
- Plan Check / Job No.
- B18LA02808
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to Existing Garage and Convert New Detached ADU PER AB-494 and SB-229.
- Permit Issued
- Issued on 8/6/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2018 | ZAW HAN |
| Corrections Issued | 3/12/2018 | ZAW HAN |
| Quality Review Completed | 3/16/2018 | KESETE HAREGOT |
| Building Plans Picked Up | 3/23/2018 | APPLICANT |
| Green Plans Picked Up | 3/23/2018 | APPLICANT |
| Applicant returned to address corrections | 5/15/2018 | ZAW HAN |
| Applicant returned to address corrections | 6/26/2018 | ZAW HAN |
| Plan Check Approved | 7/18/2018 | Zaw Han |
| Issued | 8/6/2018 | LADBS |
| CofO in Progress | 5/25/2021 | VINCENT HANLEY |
| Permit Finaled | 6/3/2021 | JOHN JANSON |
| CofO Issued | 6/3/2021 | JOHN JANSON |
| Permit Finaled | 6/3/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2018 | MICHAEL CASTILLO |
| Permit | Cleared | 5/14/2018 | MICHAEL CASTILLO |
| Green Code | Cleared | 5/17/2018 | NEGAR NEJAD |
| ZI | Cleared | 5/25/2018 | FIPE LEILUA |
| Construction near power lines | Cleared | 5/30/2018 | WALTER RAMIREZ |
| Construction within easement | Cleared | 5/30/2018 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 5/31/2018 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 5/31/2018 | JAMES MORALEZ |
| Sewer availability | Cleared | 5/31/2018 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/5/2020 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/5/2020 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 8/12/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 9/22/2020 | Partial Approval | VINCENT HANLEY |
| Sewer | 9/22/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/9/2020 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 11/13/2020 | No Access for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 11/18/2020 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/14/2020 | Approved | VINCENT HANLEY |
| HVAC-Rough | 12/22/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/8/2021 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2021 | Approved | VINCENT HANLEY |
| Pre-Inspection | 1/8/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/19/2021 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/22/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/22/2021 | Approved | VINCENT HANLEY |
| Insulation | 1/22/2021 | Approved | VINCENT HANLEY |
| Wood Frame | 1/22/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 1/29/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 2/2/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 2/4/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 2/18/2021 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/18/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/12/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/12/2021 | Approved | VINCENT HANLEY |
| Final | 5/12/2021 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 5/12/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 5/12/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/12/2021 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 5/12/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/20/2021 | Corrections Issued | VINCENT HANLEY |
| Final | 5/20/2021 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Final | 5/20/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/20/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/20/2021 | SGSOV Approved | VINCENT HANLEY |
| Final | 5/25/2021 | OK to Issue CofO | VINCENT HANLEY |