1178 N ALEXANDRIA AVE 90029
Certificate Information: 1178 N ALEXANDRIA AVE 90029
- Application / Permit
- 18014-10000-00634
- Plan Check / Job No.
- B18LA02206
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1 STORY ADDITION (32'-2"(L) x 21'-3"(W), 576 SF) TO REAR OF (E) SINGLE FAMILY DWELLING TO CREATE 1 NEW MASTER BEDROOM, 1 BATHROOM, 1 SUNROOM, AND 1 NEW FAMILY ROOM. SCOPE WILL ALSO INCLUDE A 2 STORY ADDITION (16'-6"(L) x 32'-6"(W), 481 SF) TO THE FRONT OF (E) SFD TO CREATE 2 NEW BEDROOMS AND 2 BATHROOMS.
- Permit Issued
- Issued on 9/18/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2018 | MICHAEL LOPEZ |
| Green Plans Picked Up | 2/15/2018 | APPLICANT |
| Corrections Issued | 2/20/2018 | MICHAEL LOPEZ |
| Quality Review Completed | 2/21/2018 | CHARLES CHANG |
| Building Plans Picked Up | 2/27/2018 | APPLICANT |
| Plan Check Approved | 3/30/2018 | MICHAEL LOPEZ |
| Plan Check Approved | 6/27/2018 | MICHAEL LOPEZ |
| Issued | 9/18/2018 | LADBS |
| CofO in Progress | 11/21/2022 | DONALD CRICHLOW |
| Permit Finaled | 11/29/2022 | DEROLD HAUFF |
| CofO Issued | 11/29/2022 | DEROLD HAUFF |
| Permit Finaled | 11/29/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2018 | EDUARDO PEDROZA |
| Sewer availability | Cleared | 3/15/2018 | EDUARDO PEDROZA |
| Low Impact Development | Cleared | 3/20/2018 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/20/2018 | CELINA MORENO |
| Green Code | Cleared | 3/21/2018 | KATHRYN BUTTERWORTH |
Contact Information
| Engineer | Yenjai, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/26/2018 | Approved | ANDEY CHAPARRO |
| Footing/Foundation/Slab | 10/26/2018 | Corrections Issued | ANDEY CHAPARRO |
| Footing/Foundation/Slab | 11/15/2018 | Approved | ANDEY CHAPARRO |
| Pre-Inspection | 11/26/2019 | Partial Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 12/4/2019 | Partial Approval | ROBERT VORHIS |
| Green Building Rough | 12/4/2019 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 12/4/2019 | Partial Approval | ROBERT VORHIS |
| Drywall Nailing | 12/10/2019 | Not Ready for Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2019 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2020 | Partial Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 1/22/2020 | Partial Inspection | ROBERT VORHIS |
| Sewer | 1/22/2020 | Partial Approval | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 2/3/2020 | Partial Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 2/7/2020 | Partial Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 3/11/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2020 | Approved | ROBERT VORHIS |
| HVAC-Rough | 3/26/2020 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 3/26/2020 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 4/8/2020 | Approved | ROBERT VORHIS |
| Green Building Rough | 4/8/2020 | Approved | ROBERT VORHIS |
| Insulation | 7/1/2020 | Approved | ROBERT VORHIS |
| Drywall Nailing | 7/10/2020 | Approved | ROBERT VORHIS |
| Shower Pan | 8/25/2020 | Not Ready for Inspection | DAVID MATSON |
| Interior/Exterior Lathing | 8/31/2020 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 10/7/2020 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 10/7/2020 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 6/8/2021 | Approved | ROBERT VORHIS |
| Final | 4/13/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 4/13/2022 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 4/13/2022 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 4/13/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 4/19/2022 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 11/8/2022 | Approved | FREDDIE RIVERA |
| Final | 11/8/2022 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 11/8/2022 | Approved | FREDDIE RIVERA |
| HVAC-Final | 11/8/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 11/8/2022 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 11/8/2022 | Approved | FREDDIE RIVERA |