1400 S ALAMEDA ST 90021
Certificate Information: 1400 S ALAMEDA ST 90021
- Application / Permit
- 18014-10000-00631
- Plan Check / Job No.
- B18LA02193
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (9) Gasoline Station
- Work Description
- INSTALL NEW GAS STATION CANOPY.
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Metro
- Current Status
- Issued on 2/4/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/5/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2018 | JOE VO |
| Corrections Issued | 2/20/2018 | JOE VO |
| Quality Review Completed | 2/21/2018 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 2/21/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 2/21/2018 | APPLICANT |
| Green Plans Picked Up | 2/26/2018 | APPLICANT |
| Plan Check Approved | 12/4/2019 | JOE VO |
| Issued | 2/4/2020 | LADBS |
Permit Application Clearance Information
| Green Code | Cleared | 2/9/2018 | WILLIAM ROSE |
| DAS Clearance | Cleared | 5/11/2018 | EDDIE GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2018 | MICHAEL CASTILLO |
| Roof/Waste drainage to street | Cleared | 5/14/2018 | MICHAEL CASTILLO |
| Specific Plan | Cleared | 5/14/2018 | DANALYNN DOMINGUEZ |
| Low Impact Development | Cleared | 12/2/2019 | AMMAR ELTAWIL |
Contact Information
| Contractor | Progressive Fueling Construction Inc; Lic. No.: 894043-A | 936 E NOCTA STREET ONTARIO, CA 91764 |
| Engineer | Peyton,, David E; Lic. No.: S3288 | 5722 E THE TOLEDO LONG BEACH, CA 90803 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 3/31/2020 | Partial Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 4/7/2020 | Conditional Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 6/2/2020 | Partial Approval | JONATHAN QUACH |
| Pre-Inspection | 6/25/2020 | Corrections Issued | JONATHAN QUACH |
| Special/Order Compliance | 6/26/2020 | Partial Inspection | RONALD PACHECO |
| Footing/Foundation/Slab | 7/31/2020 | Partial Inspection | RONALD PACHECO |
| Special/Order Compliance | 7/31/2020 | Partial Inspection | RONALD PACHECO |
| Special/Order Compliance | 12/31/2020 | Conditional Approval | LANNY MERRICK |
| Special/Order Compliance | 3/22/2021 | Partial Inspection | LANNY MERRICK |
| Special/Order Compliance | 6/17/2021 | Partial Inspection | LANNY MERRICK |
| Final | 7/20/2021 | Not Ready for Inspection | LANNY MERRICK |
| Footing/Foundation/Slab | 7/20/2021 | Not Ready for Inspection | LANNY MERRICK |
| SGSOV-Seismic Gas S/O Valve | 7/20/2021 | SGSOV Approved | LANNY MERRICK |
| Smoke Detectors | 7/20/2021 | Approved | LANNY MERRICK |
| Wood Frame | 7/20/2021 | Not Ready for Inspection | LANNY MERRICK |
| Final | 10/6/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Footing/Foundation/Slab | 10/6/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Wood Frame | 10/6/2021 | Not Ready for Inspection | DANIEL COLLINS |