4001 S BRONSON AVE 90008
Certificate Information: 4001 S BRONSON AVE 90008
- Application / Permit
- 18014-10000-00549
- Plan Check / Job No.
- B18LA01911
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED GROUND FLOOR AND SECOND FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING TO CONVERT (E) BEDROOM TO LIVING ROOM AND EXTEND (E) KITCHEN AT GROUND FLOOR, ALSO CREATE 3 NEW BEDROOMS AND 2 NEW BATHROOMS AT SECOND FLOOR. SCOPE WILL ALSO CONSIST OF INTERIOR REMODEL INCLUDING WINDOW AND DOOR CHANGEOUTS. ***SEE COMMENTS***
- Permit Issued
- Issued on 7/19/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/30/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2018 | MICHAEL LOPEZ |
| Corrections Issued | 2/12/2018 | MICHAEL LOPEZ |
| Green Plans Picked Up | 2/14/2018 | APPLICANT |
| Quality Review Completed | 2/15/2018 | CHARLES CHANG |
| Building Plans Picked Up | 2/16/2018 | APPLICANT |
| Applicant returned to address corrections | 4/24/2018 | MICHAEL LOPEZ |
| Plan Check Approved | 7/19/2018 | MICHAEL LOPEZ |
| Issued | 7/19/2018 | LADBS |
| CofO in Progress | 1/27/2020 | COREY HUPP |
| CofO Issued | 1/30/2020 | DEROLD HAUFF |
| Permit Finaled | 1/30/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2018 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 3/14/2018 | NAZILA NOORIFAR |
| Green Code | Cleared | 6/5/2018 | COLIN LOREDO |
| Low Impact Development | Cleared | 6/29/2018 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 7/5/2018 | MICHAEL CASTILLO |
Contact Information
| Contractor | Custom Design & Construction; Lic. No.: 524561-B | 2001 E MARIPOSA AVE EL SEGUNDO, CA 90245 |
| Engineer | Rhee, Kyle; Lic. No.: C78215 | 3855 W 7TH ST #304 LOS ANGELES, CA 90005 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/27/2018 | Approved | LUIS ALVAREZ |
| BUILDING-Rough-Frame | 8/30/2018 | Partial Approval | LUIS ALVAREZ |
| Insulation | 8/30/2018 | Partial Approval | LUIS ALVAREZ |
| BUILDING-Rough-Frame | 12/12/2018 | Approved | LUIS ALVAREZ |
| ELECTRICAL-Rough | 12/12/2018 | Approved | LUIS ALVAREZ |
| Green Building Rough | 12/12/2018 | Approved | LUIS ALVAREZ |
| HVAC-Rough | 12/12/2018 | Approved | LUIS ALVAREZ |
| PLUMBING-Rough | 12/12/2018 | Approved | LUIS ALVAREZ |
| Deputy Wood Construction | 12/14/2018 | Conditional Approval | LUIS ALVAREZ |
| Insulation | 1/11/2019 | Approved | LUIS ALVAREZ |
| Interior/Exterior Lathing | 1/11/2019 | Approved | LUIS ALVAREZ |
| Shower Pan | 1/11/2019 | Approved | LUIS ALVAREZ |
| Drywall Nailing | 1/23/2019 | Approved | LUIS ALVAREZ |
| Interior/Exterior Lathing | 1/31/2019 | Approved | LUIS ALVAREZ |
| Final | 10/3/2019 | Not Ready for Inspection | COREY HUPP |
| Green Building Final | 10/3/2019 | Approved | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 10/3/2019 | SGSOV Approved | COREY HUPP |
| Smoke Detectors | 10/3/2019 | Approved | COREY HUPP |
| Final | 10/10/2019 | Conditional Approval | COREY HUPP |
| Final | 1/27/2020 | OK to Issue CofO | COREY HUPP |