4001 S BRONSON AVE 90008

Certificate Information: 4001 S BRONSON AVE 90008

Application / Permit
18014-10000-00549
Plan Check / Job No.
B18LA01911
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED GROUND FLOOR AND SECOND FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING TO CONVERT (E) BEDROOM TO LIVING ROOM AND EXTEND (E) KITCHEN AT GROUND FLOOR, ALSO CREATE 3 NEW BEDROOMS AND 2 NEW BATHROOMS AT SECOND FLOOR. SCOPE WILL ALSO CONSIST OF INTERIOR REMODEL INCLUDING WINDOW AND DOOR CHANGEOUTS. ***SEE COMMENTS***
Permit Issued
Issued on 7/19/2018
Issuing Office
Metro
Current Status
CofO Issued on 1/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2018 APPLICANT
Assigned to Plan Check Engineer 2/8/2018 MICHAEL LOPEZ
Corrections Issued 2/12/2018 MICHAEL LOPEZ
Green Plans Picked Up 2/14/2018 APPLICANT
Quality Review Completed 2/15/2018 CHARLES CHANG
Building Plans Picked Up 2/16/2018 APPLICANT
Applicant returned to address corrections 4/24/2018 MICHAEL LOPEZ
Plan Check Approved 7/19/2018 MICHAEL LOPEZ
Issued 7/19/2018 LADBS
CofO in Progress 1/27/2020 COREY HUPP
CofO Issued 1/30/2020 DEROLD HAUFF
Permit Finaled 1/30/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/14/2018 NAZILA NOORIFAR
Sewer availability Cleared 3/14/2018 NAZILA NOORIFAR
Green Code Cleared 6/5/2018 COLIN LOREDO
Low Impact Development Cleared 6/29/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 7/5/2018 MICHAEL CASTILLO

Contact Information

Contractor Custom Design & Construction; Lic. No.: 524561-B 2001 E MARIPOSA AVE      EL SEGUNDO, CA 90245
Engineer Rhee, Kyle; Lic. No.: C78215 3855 W 7TH ST #304      LOS ANGELES, CA 90005

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/27/2018 Approved LUIS ALVAREZ
BUILDING-Rough-Frame 8/30/2018 Partial Approval LUIS ALVAREZ
Insulation 8/30/2018 Partial Approval LUIS ALVAREZ
BUILDING-Rough-Frame 12/12/2018 Approved LUIS ALVAREZ
ELECTRICAL-Rough 12/12/2018 Approved LUIS ALVAREZ
Green Building Rough 12/12/2018 Approved LUIS ALVAREZ
HVAC-Rough 12/12/2018 Approved LUIS ALVAREZ
PLUMBING-Rough 12/12/2018 Approved LUIS ALVAREZ
Deputy Wood Construction 12/14/2018 Conditional Approval LUIS ALVAREZ
Insulation 1/11/2019 Approved LUIS ALVAREZ
Interior/Exterior Lathing 1/11/2019 Approved LUIS ALVAREZ
Shower Pan 1/11/2019 Approved LUIS ALVAREZ
Drywall Nailing 1/23/2019 Approved LUIS ALVAREZ
Interior/Exterior Lathing 1/31/2019 Approved LUIS ALVAREZ
Final 10/3/2019 Not Ready for Inspection COREY HUPP
Green Building Final 10/3/2019 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 10/3/2019 SGSOV Approved COREY HUPP
Smoke Detectors 10/3/2019 Approved COREY HUPP
Final 10/10/2019 Conditional Approval COREY HUPP
Final 1/27/2020 OK to Issue CofO COREY HUPP