8945 S BARING CROSS ST 90044
Certificate Information: 8945 S BARING CROSS ST 90044
- Application / Permit
- 18014-10000-00482
- Plan Check / Job No.
- B18LA01679
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 1-CAR DETACHED GARAGE (252 SF) TO 1-STORY ADU WITH (N) GROUND FLOOR ADDITION FOR TOTAL OF 495 SF.
- Permit Issued
- Issued on 2/1/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2018 | APPLICANT |
| Green Plans Picked Up | 2/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2018 | JAHANSHAH POURHASSAN |
| Corrections Issued | 3/8/2018 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 3/16/2018 | JASON HEALEY |
| Building Plans Picked Up | 3/21/2018 | APPLICANT |
| Applicant returned to address corrections | 11/19/2018 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 11/29/2018 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 2/1/2019 | JAHANSHAH POURHASSAN |
| Issued | 2/1/2019 | LADBS |
| CofO in Progress | 2/22/2021 | OSVALDO PARAMO |
| CofO in Progress | 2/22/2021 | OSVALDO PARAMO |
| CofO in Progress | 2/22/2021 | OSVALDO PARAMO |
| Permit Finaled | 2/24/2023 | DANIEL ORRANTE |
| CofO Issued | 2/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 3/12/2018 | SARAH ABOULHOSN |
| Address approval | Cleared | 7/20/2018 | JAMES MORALEZ |
| Roof/Waste drainage to street | Cleared | 7/20/2018 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 8/27/2018 | MICHAEL CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/20/2019 | Partial Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 6/7/2019 | Corrections Issued | WILLIAM ROSE |
| Footing/Foundation/Slab | 6/24/2019 | Corrections Issued | ANDEY CHAPARRO |
| Excavation/Setback/Form/Re-Bar | 7/1/2019 | Partial Approval | ANDEY CHAPARRO |
| Footing/Foundation/Slab | 7/11/2019 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 8/20/2019 | Not Ready for Inspection | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 9/12/2019 | Not Ready for Inspection | EUGENE CASSIDY |
| Underground Mechanical | 9/12/2019 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/17/2019 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 9/17/2019 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/17/2019 | Approved | EUGENE CASSIDY |
| Wood Frame | 9/24/2019 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 10/1/2019 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 10/3/2019 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/15/2019 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 10/24/2019 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/24/2019 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 11/6/2019 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/6/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 11/14/2019 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/13/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 1/13/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 1/13/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 1/13/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 1/13/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/13/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 1/13/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/30/2020 | Approved | EUGENE CASSIDY |
| Final | 1/30/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 1/30/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 1/30/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/30/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/30/2020 | SGSOV Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/4/2020 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/4/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/4/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 11/4/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/19/2020 | Not Ready for Inspection | JOHN KLARIN |
| Final | 11/25/2020 | Not Ready for Inspection | DAVID FEILER |
| Final | 12/24/2020 | Corrections Issued | EUGENE CASSIDY |
| Final | 1/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| Final | 1/19/2021 | OK to Issue CofO | OSVALDO PARAMO |
| Special/Order Compliance | 2/22/2021 | Approved | OSVALDO PARAMO |