5172 N CHIMINEAS AVE 91356
Certificate Information: 5172 N CHIMINEAS AVE 91356
- Application / Permit
- 18014-10000-00305
- Plan Check / Job No.
- B18LA01049
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND ADDITION OF 1 STORY 322 SQ FT TO (E) 1 STORY SFD
- Permit Issued
- Issued on 2/22/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/18/2018 | ARSALAN SHABESTARI |
| Corrections Issued | 1/30/2018 | ARSALAN SHABESTARI |
| Plan Check Approved | 2/22/2018 | AUNG SOE |
| Issued | 2/22/2018 | LADBS |
| CofO in Progress | 10/16/2023 | SEAN WIRCH |
| Permit Finaled | 4/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/23/2024 | DANIEL ORRANTE |
| CofO Issued | 4/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2018 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 2/22/2018 | BARTON HOLMES |
| Low Impact Development | Cleared | 2/22/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/22/2018 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Beizai, Vahid Vic; Lic. No.: C43801 | 1125 EAST BROADWAY 159 GLENDALE, CA 91025 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/26/2018 | Partial Approval | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 3/8/2018 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2018 | Partial Approval | SEAN WIRCH |
| ELECTRICAL-Rough | 4/19/2018 | Approved | SEAN WIRCH |
| HVAC-Rough | 4/19/2018 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 4/19/2018 | Approved | SEAN WIRCH |
| Shower Pan | 4/19/2018 | Not Ready for Inspection | SEAN WIRCH |
| Shower Pan | 4/20/2018 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 4/23/2018 | Approved | SEAN WIRCH |
| Green Building Rough | 4/23/2018 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 4/23/2018 | Not Ready for Inspection | SEAN WIRCH |
| Shower Pan | 4/23/2018 | Approved | SEAN WIRCH |
| Insulation | 4/25/2018 | Approved | SEAN WIRCH |
| Drywall Nailing | 5/4/2018 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 5/4/2018 | Partial Approval | SEAN WIRCH |
| Interior/Exterior Lathing | 5/7/2018 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 6/14/2018 | Approved | SEAN WIRCH |
| HVAC-Final | 6/14/2018 | Approved | SEAN WIRCH |
| PLUMBING-Final | 6/14/2018 | Approved | SEAN WIRCH |
| Service/Power Release | 6/14/2018 | Approved | SEAN WIRCH |
| Smoke Detectors | 6/14/2018 | Approved | SEAN WIRCH |
| Final | 7/27/2018 | Conditional Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 7/27/2018 | Approved | SEAN WIRCH |
| Green Building Final | 7/27/2018 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 7/27/2018 | SGSOV Approved | SEAN WIRCH |
| Final | 9/29/2023 | Partial Inspection | SEAN WIRCH |
| Final | 10/17/2023 | OK to Issue CofO | SEAN WIRCH |