5172 N CHIMINEAS AVE 91356

Certificate Information: 5172 N CHIMINEAS AVE 91356

Application / Permit
18014-10000-00305
Plan Check / Job No.
B18LA01049
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ADDITION OF 1 STORY 322 SQ FT TO (E) 1 STORY SFD
Permit Issued
Issued on 2/22/2018
Issuing Office
Metro
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2018 APPLICANT
Assigned to Plan Check Engineer 1/18/2018 ARSALAN SHABESTARI
Corrections Issued 1/30/2018 ARSALAN SHABESTARI
Plan Check Approved 2/22/2018 AUNG SOE
Issued 2/22/2018 LADBS
CofO in Progress 10/16/2023 SEAN WIRCH
Permit Finaled 4/23/2024 DANIEL ORRANTE
Permit Finaled 4/23/2024 DANIEL ORRANTE
CofO Issued 4/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/22/2018 STEVE MELGAR
Grading Pre-Inspection Cleared 2/22/2018 BARTON HOLMES
Low Impact Development Cleared 2/22/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/22/2018 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Beizai, Vahid Vic; Lic. No.: C43801 1125 EAST BROADWAY 159      GLENDALE, CA 91025

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/26/2018 Partial Approval SEAN WIRCH
Excavation/Setback/Form/Re-Bar 3/8/2018 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 4/6/2018 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 4/19/2018 Approved SEAN WIRCH
HVAC-Rough 4/19/2018 Approved SEAN WIRCH
PLUMBING-Rough 4/19/2018 Approved SEAN WIRCH
Shower Pan 4/19/2018 Not Ready for Inspection SEAN WIRCH
Shower Pan 4/20/2018 Approved SEAN WIRCH
BUILDING-Rough-Frame 4/23/2018 Approved SEAN WIRCH
Green Building Rough 4/23/2018 Approved SEAN WIRCH
Interior/Exterior Lathing 4/23/2018 Not Ready for Inspection SEAN WIRCH
Shower Pan 4/23/2018 Approved SEAN WIRCH
Insulation 4/25/2018 Approved SEAN WIRCH
Drywall Nailing 5/4/2018 Approved SEAN WIRCH
Interior/Exterior Lathing 5/4/2018 Partial Approval SEAN WIRCH
Interior/Exterior Lathing 5/7/2018 Approved SEAN WIRCH
ELECTRICAL-Final 6/14/2018 Approved SEAN WIRCH
HVAC-Final 6/14/2018 Approved SEAN WIRCH
PLUMBING-Final 6/14/2018 Approved SEAN WIRCH
Service/Power Release 6/14/2018 Approved SEAN WIRCH
Smoke Detectors 6/14/2018 Approved SEAN WIRCH
Final 7/27/2018 Conditional Approval SEAN WIRCH
Footing/Foundation/Slab 7/27/2018 Approved SEAN WIRCH
Green Building Final 7/27/2018 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 7/27/2018 SGSOV Approved SEAN WIRCH
Final 9/29/2023 Partial Inspection SEAN WIRCH
Final 10/17/2023 OK to Issue CofO SEAN WIRCH