1124 N CORONADO TER 90026
Certificate Information: 1124 N CORONADO TER 90026
- Application / Permit
- 18014-10000-00219
- Plan Check / Job No.
- B18LA00741
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD IRREGULAR 22'-7" X 37'-6" AND MAJOR REMODEL THROUGHOUT FOR (E) 1-STORY SFD PER ENGINEERING.
- Permit Issued
- Issued on 4/13/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2018 | PINANK PATEL |
| Green Plans Picked Up | 2/12/2018 | APPLICANT |
| Corrections Issued | 2/16/2018 | PINANK PATEL |
| Quality Review Completed | 2/26/2018 | WING SUEN |
| Building Plans Picked Up | 3/2/2018 | APPLICANT |
| Plan Check Approved | 4/12/2018 | PINANK PATEL |
| Issued | 4/13/2018 | LADBS |
| CofO in Progress | 11/10/2020 | RUBEN SALAS |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
| CofO Issued | 11/13/2020 | DEROLD HAUFF |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2018 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 3/2/2018 | NAZILA NOORIFAR |
| Green Code | Cleared | 3/15/2018 | COLIN LOREDO |
| Low Impact Development | Cleared | 4/3/2018 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 4/3/2018 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 4/12/2018 | PINANK PATEL |
| Grading Pre-Inspection | Cleared | 4/12/2018 | PINANK PATEL |
Contact Information
| Architect | Song, Michael; Lic. No.: C32566 | 5608 E PEABODY STREET LONG BEACH, CA 90808 |
| Engineer | Alson, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/16/2018 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Barrier | 5/16/2018 | Approved | ROBERT MCDOWELL |
| METHANE-Subgrade | 5/16/2018 | Approved | ROBERT MCDOWELL |
| Deputy Drilled-In Anchors | 5/23/2018 | Conditional Approval | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 8/22/2018 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2018 | Partial Approval | ROBERT MCDOWELL |
| Insulation | 9/19/2018 | Partial Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 2/6/2019 | Corrections Issued | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 2/6/2019 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 2/6/2019 | Approved | ROBERT MCDOWELL |
| METHANE-Rough | 2/6/2019 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 2/6/2019 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 2/6/2019 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 6/17/2019 | Corrections Issued | DAVID CHAN |
| HVAC-Rough | 6/17/2019 | Corrections Issued | DAVID CHAN |
| Insulation | 7/9/2019 | Conditional Approval | DAVID CHAN |
| Deputy Wood Construction | 7/11/2019 | Approved | ELMER BLAND |
| BUILDING-Rough-Frame | 8/21/2019 | Conditional Approval | DAVID CHAN |
| Drywall Nailing | 8/30/2019 | Conditional Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 6/24/2020 | Approved | ROBERT VORHIS |
| Drywall Nailing | 6/24/2020 | Approved | ROBERT VORHIS |
| Final | 6/24/2020 | Partial Inspection | ROBERT VORHIS |
| Green Building Final | 6/24/2020 | Partial Inspection | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 6/24/2020 | SGSOV Approved | ROBERT VORHIS |
| Smoke Detectors | 6/24/2020 | Approved | ROBERT VORHIS |
| Final | 9/22/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Green Building Final | 9/22/2020 | Approved | ROBERT VORHIS |
| Final | 10/8/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 10/29/2020 | Corrections Issued | RUBEN SALAS |
| Final | 11/4/2020 | Partial Approval | RUBEN SALAS |
| Service/Power Release | 11/4/2020 | Approved | RUBEN SALAS |