531 1/2 E COLEMAN AVE 90042

Certificate Information: 531 1/2 E COLEMAN AVE 90042

Application / Permit
18014-10000-00135
Plan Check / Job No.
B18LA00421
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) REC ROOM AND CONVERT TO ADU PER AB 2299 AND SB 1069. CONSTRUCTION PER CITY STANDARD PRESCRIPTIVE METHOD IB.
Permit Issued
Issued on 4/9/2018
Issuing Office
Metro
Current Status
CofO Issued on 9/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2018 APPLICANT
Assigned to Plan Check Engineer 1/18/2018 JOE VO
Corrections Issued 1/22/2018 JOE VO
Quality Review Completed 1/23/2018 LAWRENCE QUIRANTE
Building Plans Picked Up 1/25/2018 APPLICANT
Green Plans Picked Up 2/22/2018 APPLICANT
Plan Check Approved 3/29/2018 JOE VO
Issued 4/9/2018 LADBS
CofO in Progress 9/3/2022 AMY COLIN
Permit Finaled 9/16/2022 DEROLD HAUFF
CofO Issued 9/16/2022 DEROLD HAUFF
Permit Finaled 9/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 3/7/2018 COLIN LOREDO
Address approval Cleared 3/15/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 3/15/2018 MICHAEL CASTILLO
Sewer availability Cleared 3/15/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 3/16/2018 ROBERT DUFF
Low Impact Development Cleared 3/16/2018 MITESH PATEL
Miscellaneous Cleared 3/16/2018 ROBERT DUFF
Roof/Waste drainage to street Cleared 3/16/2018 CARLA VALLADARES
Permit Cleared 4/6/2018 MICHAEL CASTILLO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/19/2019 Not Ready for Inspection ENRIQUE MIRELES
Underground Mechanical 8/19/2019 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 9/24/2019 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 10/8/2019 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 11/13/2019 Not Ready for Inspection ENRIQUE MIRELES
Deputy Drilled-In Anchors 11/14/2019 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 2/18/2020 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 3/5/2020 Partial Approval COREY HUPP
BUILDING-Rough-Frame 12/4/2020 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 4/5/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 4/5/2021 Approved CRAIG VAUGHAN
Green Building Rough 4/5/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 4/5/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 4/19/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 4/19/2021 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/11/2021 Approved COREY HUPP
PLUMBING-Rough 5/11/2021 Approved COREY HUPP
Wood Frame 5/11/2021 Approved COREY HUPP
HVAC-Rough 6/11/2021 Approved COREY HUPP
Interior/Exterior Lathing 6/11/2021 Partial Approval COREY HUPP
Insulation 6/21/2021 Approved CRAIG VAUGHAN
Drywall Nailing 7/2/2021 Approved COREY HUPP
Green Building Rough 7/2/2021 Approved COREY HUPP
Shower Pan 10/12/2021 Corrections Issued AMY COLIN
Shower Pan 10/15/2021 Approved RUBEN SALAS
BUILDING-Rough-Frame 3/29/2022 Approved AMY COLIN
Final 3/29/2022 Not Ready for Inspection AMY COLIN
Footing/Foundation/Slab 3/29/2022 Approved AMY COLIN
Green Building Final 3/29/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 3/29/2022 SGSOV Not Ready AMY COLIN
Smoke Detectors 3/29/2022 Approved AMY COLIN
Final 4/6/2022 Partial Approval AMY COLIN
SGSOV-Seismic Gas S/O Valve 4/6/2022 SGSOV Approved AMY COLIN
Final 9/3/2022 OK to Issue CofO AMY COLIN