612 S BROADWAY 90014

Certificate Information: 612 S BROADWAY 90014

Application / Permit
18014-10000-00041
Plan Check / Job No.
B18LA00122
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
[NDC-532] Additon of restaurant (core and shell only) to the existing non-ductile concrete builidng and Seismic renovation of an existing non-ductile highrise building and change of use from Retail to Creative Office and Retail. Comply with the non-ductile concrete builidng ordinance.
Permit Issued
Issued on 12/17/2018
Issuing Office
Metro
Current Status
CofO Issued on 11/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2018 APPLICANT
Assigned to Plan Check Engineer 2/1/2018 LARRY LEE
Corrections Issued 2/23/2018 LARRY LEE
Quality Review Completed 2/27/2018 WING SUEN
Building Plans Picked Up 3/28/2018 APPLICANT
Applicant returned to address corrections 6/29/2018 LARRY LEE
Applicant returned to address corrections 7/11/2018 LARRY LEE
Applicant returned to address corrections 9/27/2018 LARRY LEE
Applicant returned to address corrections 11/1/2018 LARRY LEE
Plan Check Approved 12/7/2018 LARRY LEE
Issued 12/17/2018 LADBS
TCO Issued (Expire Date: 03-22-2022) 9/23/2021 ERNESTO CORRAL
CofO in Progress 11/8/2021 DANIEL COLLINS
Permit Finaled 11/18/2021 ERNESTO CORRAL
CofO Issued 11/18/2021 ERNESTO CORRAL
Permit Finaled 11/18/2021 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 7/3/2018 LARRY LEE
DAS Clearance Cleared 7/13/2018 LARRY LEE
City Hist. Cultural Monument Cleared 9/19/2018 LAMBERT GIESSINGER
Historic monument Cleared 9/19/2018 LAMBERT GIESSINGER
"D" conditions Cleared 9/20/2018 DANALYNN DOMINGUEZ
"Q" conditions Cleared 9/20/2018 DANALYNN DOMINGUEZ
CPC Cleared 9/20/2018 DANALYNN DOMINGUEZ
CPC Cleared 9/20/2018 DANALYNN DOMINGUEZ
ZA Case Cleared 9/20/2018 DANALYNN DOMINGUEZ
Historical monument Cleared 9/21/2018 JIM URQUHART
Project located in CRA area Cleared 9/21/2018 JIM URQUHART
Eng Process Fee Ord 176,300 Cleared 9/25/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 9/25/2018 ROBERT DUFF
Sewer availability Cleared 9/27/2018 JEANETTE VONG
Highway dedication Cleared 11/5/2018 STEVE MELGAR
ZI Cleared 11/9/2018 SOPHIE GABEL-SCHEINBAU
Encroachment in public way Cleared 11/21/2018 KARAN PATEL
Low Impact Development Cleared 11/26/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 11/26/2018 MICHAEL CASTILLO
Fire Marshall Fire Life Safety Cleared 12/6/2018 OSCAR SALGADO JR
Food Service Establishment Cleared 12/6/2018 KENNETH BROWNE
Miscellaneous Cleared 12/6/2018 NAZILA NOORIFAR
ZA Case Cleared 12/7/2018 SOPHIE GABEL-SCHEINBAU

Contact Information

Architect Liljegren, Karin J; Lic. No.: C28158 727 W 7TH STREET # 610      LOS ANGELES, CA 90017
Contractor M D M Builders Group; Lic. No.: 933238-B 541 SOUTH SPRING ST STE 213      LOS ANGELES, CA 90013
Engineer Gharibans, Edmond T; Lic. No.: S2942 18544 BRYMER STREET      NORTHRIDGE, CA 913261951

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/4/2019 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/11/2019 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 2/12/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 2/14/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 2/19/2019 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 2/22/2019 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 2/26/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 3/6/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 3/29/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 4/3/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 4/4/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 4/5/2019 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/5/2019 Partial Approval NICK DANERI
Green Building Rough 4/5/2019 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 4/5/2019 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 4/12/2019 Conditional Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 4/18/2019 Partial Approval DANIEL COLLINS
Green Building Rough 4/18/2019 Approved DANIEL COLLINS
Reinforced Concrete Frame 4/18/2019 Partial Approval DANIEL COLLINS
Deputy Other (see comments) 4/19/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 4/25/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 4/30/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 5/3/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 5/6/2019 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 5/6/2019 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 5/7/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 5/8/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 5/15/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 5/20/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 5/20/2019 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 5/20/2019 Partial Approval DANIEL COLLINS
Deputy Drilled-In Anchors 5/28/2019 Conditional Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 6/3/2019 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 6/3/2019 Partial Approval DANIEL COLLINS
Deputy Drilled-In Anchors 6/4/2019 Approved DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 6/18/2019 Conditional Approval KATY RAMIREZ
Reinforced Concrete Frame 6/18/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/25/2019 Conditional Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 7/1/2019 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 7/1/2019 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 7/3/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 7/10/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 7/10/2019 Conditional Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 7/12/2019 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 7/12/2019 Partial Approval DANIEL COLLINS
Deputy Drilled-In Anchors 7/18/2019 Conditional Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 7/18/2019 Partial Approval DANIEL COLLINS
Deputy Drilled-In Anchors 7/19/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 7/24/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 8/7/2019 Conditional Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 8/7/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 8/15/2019 Not Ready for Inspection DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 8/15/2019 Not Ready for Inspection DANIEL COLLINS
Deputy Drilled-In Anchors 8/20/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 8/20/2019 Partial Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 8/20/2019 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 8/23/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 8/29/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 8/29/2019 Conditional Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 8/29/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 8/30/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 9/10/2019 Not Ready for Inspection DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 9/10/2019 Not Ready for Inspection DANIEL COLLINS
Reinforced Concrete Frame 9/10/2019 Not Ready for Inspection DANIEL COLLINS
Deputy Drilled-In Anchors 9/11/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 9/11/2019 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 9/11/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 9/17/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 9/19/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 9/19/2019 Conditional Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 9/19/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 9/24/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/2/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/9/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/15/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 10/30/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 11/12/2019 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 12/3/2019 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 12/4/2019 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 12/5/2019 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 12/6/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 12/11/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 1/3/2020 Conditional Approval DANIEL COLLINS
Deputy Other (see comments) 1/7/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 1/7/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 1/10/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 1/14/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 1/16/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 1/23/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 1/23/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 1/24/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 1/28/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 1/30/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 2/3/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 2/11/2020 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 2/11/2020 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 2/12/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 2/13/2020 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 2/13/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 2/24/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 2/26/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 3/13/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 4/3/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 4/7/2020 Conditional Approval DANIEL COLLINS
Deputy Other (see comments) 4/16/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 4/16/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 5/11/2020 Conditional Approval DANIEL COLLINS
Light Gage Steel Frame 7/8/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 7/15/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/15/2020 Partial Approval RAFAEL ESPINOZA
Insulation 7/17/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 7/24/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 8/7/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 8/11/2020 Partial Approval DANIEL COLLINS
Insulation 8/11/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 9/10/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 9/15/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 9/25/2020 Partial Approval DANIEL COLLINS
Insulation 9/25/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 9/25/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 10/13/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 10/13/2020 Partial Approval DANIEL COLLINS
Deputy Fireproofing 10/14/2020 Conditional Approval KATY RAMIREZ
Deputy Fireproofing 10/15/2020 Conditional Approval KATY RAMIREZ
Deputy Fireproofing 10/16/2020 Conditional Approval KATY RAMIREZ
Deputy Fireproofing 10/19/2020 Conditional Approval KATY RAMIREZ
Deputy Fireproofing 10/20/2020 Conditional Approval KATY RAMIREZ
Drywall Nailing 11/4/2020 Partial Approval DANIEL COLLINS
Insulation 11/4/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 11/4/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 11/25/2020 Partial Inspection DANIEL COLLINS
Light Gage Steel Frame 11/25/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/1/2020 Conditional Approval DANIEL COLLINS
Drywall Nailing 12/8/2020 Partial Approval DANIEL COLLINS
Insulation 12/8/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/8/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/18/2020 Partial Approval DANIEL COLLINS
Insulation 1/19/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 1/19/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 1/25/2021 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 1/27/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 1/27/2021 Corrections Issued DANIEL COLLINS
Light Gage Steel Frame 2/1/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 2/8/2021 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 2/18/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 2/18/2021 Partial Inspection DANIEL COLLINS
Insulation 2/25/2021 Partial Inspection DANIEL COLLINS
Light Gage Steel Frame 2/25/2021 Partial Approval DANIEL COLLINS
Insulation 3/2/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 3/2/2021 Partial Approval DANIEL COLLINS
Insulation 3/9/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 3/9/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 3/26/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 3/26/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 4/13/2021 Partial Inspection DANIEL COLLINS
Light Gage Steel Frame 4/15/2021 Partial Approval DANIEL COLLINS
Special/Order Compliance 5/20/2021 Partial Inspection DANIEL COLLINS
Final 9/17/2021 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 9/17/2021 Approved DANIEL COLLINS
Green Building Final 9/17/2021 Approved DANIEL COLLINS
Reinforced Concrete Frame 9/17/2021 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 9/17/2021 SGSOV Approved DANIEL COLLINS
Smoke Detectors 9/17/2021 Approved DANIEL COLLINS
Final 9/23/2021 Conditional Approval ERNESTO CORRAL
Final 11/1/2021 Conditional Approval DANIEL COLLINS