922 W 73RD ST 90044
Certificate Information: 922 W 73RD ST 90044
- Application / Permit
- 18010-70001-05368
- Plan Check / Job No.
- B20SL00388
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO PERMIT 18010-70000-05368 TO REVISE DESIGN OF PROPOSED ACCESSORY DWELLING UNIT. per LAMC 12.22 A.33 (c) and (d) ALL WORK PER WFPP
- Permit Issued
- Issued on 7/26/2021
- Issuing Office
- Current Status
- Issued on 7/26/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2020 | LUKE GONZALES |
| Corrections Issued | 3/24/2020 | LUKE GONZALES |
| Quality Review Completed | 3/31/2020 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 10/7/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 10/30/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 12/15/2020 | LUKE GONZALES |
| Plan Check Approved | 12/15/2020 | LUKE GONZALES |
| Building Plans Picked Up | 5/19/2021 | APPLICANT |
| Issued | 7/26/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2020 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 8/13/2020 | ELENA LOPEZ |
| ZI | Cleared | 8/20/2020 | ANACANY HURTADO |
| Low Impact Development | Cleared | 9/2/2020 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 9/9/2020 | MATTHEW CRAIG |
| Hydrant and Access approval | Cleared | 9/9/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 12/31/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/10/2021 | Corrections Issued | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 10/6/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/6/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/14/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 10/18/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 1/9/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/17/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 1/17/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/20/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 1/20/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 2/23/2023 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 2/23/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/20/2023 | Partial Approval | LILIANA PORTILLO |
| Pre-Inspection | 5/10/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/25/2023 | Approved | MICHAEL LEWIS |
| Sewer | 7/27/2023 | Corrections Issued | MICHAEL LEWIS |
| Sewer | 8/1/2023 | Approved | ENRIQUE MIRELES |
| Gas Test | 8/15/2023 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 8/17/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/15/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 9/15/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 9/15/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/19/2023 | Approved | STUART CHAPMAN |
| Insulation | 10/10/2023 | Corrections Issued | BRENDAN MORELLI |
| Insulation | 1/29/2024 | No Access for Inspection | MICHAEL LEWIS |
| Insulation | 2/8/2024 | Corrections Issued | MICHAEL LEWIS |
| Drywall Nailing | 2/13/2024 | No Access for Inspection | RONNIE MINDANAO |
| Drywall Nailing | 2/16/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 12/24/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 1/27/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Final | 1/27/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 1/27/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 4/1/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Final | 12/5/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 12/5/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 1/30/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/30/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |