332-332 1/2 W OPP ST 90744
Certificate Information: 332-332 1/2 W OPP ST 90744
- Application / Permit
- 18010-70000-05954
- Plan Check / Job No.
- B18SL01802
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX AND ATTACHED (2) 2-CAR GARAGES.
- Permit Issued
- Issued on 7/22/2019
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 2/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2018 | HELEN NGUYEN |
| Green Plans Picked Up | 12/28/2018 | APPLICANT |
| Corrections Issued | 1/3/2019 | HELEN NGUYEN |
| Quality Review Completed | 1/9/2019 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 1/18/2019 | APPLICANT |
| Plan Check Approved | 7/19/2019 | HELEN NGUYEN |
| Issued | 7/22/2019 | LADBS |
| CofO in Progress | 12/14/2020 | JOHN KLARIN |
| Permit Finaled | 2/11/2021 | DEROLD HAUFF |
| CofO Issued | 2/11/2021 | DEROLD HAUFF |
| Permit Finaled | 2/11/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 6/5/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 6/5/2019 | SOPHIE GABEL-SCHEINBAU |
| "Q" conditions | Cleared | 6/11/2019 | ANNA VAN |
| Abandoned oil well | Cleared | 6/11/2019 | GEORGE SUCHAND |
| Frnt yard landscape/Water mgmt | Cleared | 6/11/2019 | ANNA VAN |
| Hydrant and Access approval | Cleared | 6/11/2019 | GEORGE SUCHAND |
| Opn space landscape/Water mgmt | Cleared | 6/11/2019 | ANNA VAN |
| Green Code | Cleared | 6/25/2019 | KHEDER ALRAZAA |
| Address approval | Cleared | 6/26/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2019 | ERIK BEASLEY |
| Permit | Cleared | 6/26/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 6/26/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 7/19/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/19/2019 | ELAINE LEI |
| Trees in Parkway | Cleared | 7/19/2019 | ADRIAN SANCHEZ |
Contact Information
| Contractor | J M E Construction; Lic. No.: 921816-B | 1450 RONAN AVENUE WILMINGTON, CA 90744 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/2/2019 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 8/2/2019 | Approved | JOHN KLARIN |
| METHANE-Barrier | 8/2/2019 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 8/2/2019 | Approved | JOHN KLARIN |
| Gas Test | 8/27/2019 | Partial Inspection | JOHN KLARIN |
| PLUMBING-Rough | 8/27/2019 | Partial Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2019 | Approved | JOHN KLARIN |
| Insulation | 9/3/2019 | Partial Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2019 | Partial Inspection | JOHN KLARIN |
| Wood Frame | 11/20/2019 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/19/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 3/19/2020 | Approved | JOHN KLARIN |
| Green Building Rough | 3/19/2020 | Approved | JOHN KLARIN |
| HVAC-Rough | 3/19/2020 | Approved | JOHN KLARIN |
| METHANE-Rough | 3/19/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 3/19/2020 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 3/19/2020 | Approved | JOHN KLARIN |
| Insulation | 3/23/2020 | Not Ready for Inspection | ANSON MAGLASANG |
| Insulation | 3/26/2020 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 4/7/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 4/7/2020 | Approved | BRIAN CHRISTIAN |
| Shower Pan | 4/7/2020 | Approved | BRIAN CHRISTIAN |
| Sewer | 4/30/2020 | Partial Inspection | JOHN KLARIN |
| Underground Mechanical | 4/30/2020 | Partial Inspection | JOHN KLARIN |
| Underground Mechanical | 6/22/2020 | Approved | EUGENE CASSIDY |
| Service/Power Release | 10/2/2020 | Not Ready for Inspection | JOHN KLARIN |
| Final | 11/18/2020 | Conditional Approval | JOHN KLARIN |
| Green Building Final | 11/18/2020 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 11/18/2020 | Approved | JOHN KLARIN |
| Smoke Detectors | 11/18/2020 | Approved | JOHN KLARIN |
| Final | 12/14/2020 | OK to Issue CofO | JOHN KLARIN |