520 W 50TH ST 90037
Certificate Information: 520 W 50TH ST 90037
- Application / Permit
- 18010-70000-05800
- Plan Check / Job No.
- B18SL01751
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD W/ ATTACHED GARAGE.
- Permit Issued
- Issued on 1/22/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2018 | APPLICANT |
| Green Plans Picked Up | 12/11/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2018 | JOE VO |
| Corrections Issued | 12/17/2018 | JOE VO |
| Quality Review Completed | 12/19/2018 | GARO TELMI |
| Building Plans Picked Up | 1/4/2019 | APPLICANT |
| Applicant returned to address corrections | 3/1/2019 | JOE VO |
| Plan Check Approved | 3/5/2019 | JOE VO |
| Issued | 1/22/2020 | LADBS |
| CofO in Progress | 1/7/2021 | ROBERT MCDOWELL |
| Permit Finaled | 1/12/2021 | DEROLD HAUFF |
| Permit Finaled | 1/12/2021 | DEROLD HAUFF |
| CofO Issued | 1/12/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 2/20/2019 | COLIN LOREDO |
| Address approval | Cleared | 2/21/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 2/21/2019 | ROBERT DUFF |
| Permit | Cleared | 2/21/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/21/2019 | ELAINE LEI |
| Low Impact Development | Cleared | 2/28/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/28/2019 | ELAINE LEI |
| Driveway location | Cleared | 3/5/2019 | EDUARDO HERMOSO |
Contact Information
| Contractor | F S Z Bros General Contractors Inc; Lic. No.: 794097-B | 9036 IMPERIAL HWY DOWNEY, CA 90242 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/24/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 3/31/2020 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 6/24/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 6/24/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 6/24/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 6/24/2020 | Approved | ROBERT MCDOWELL |
| MERV13>=Rough | 6/24/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 6/24/2020 | Approved | ROBERT MCDOWELL |
| Verify Rec and Parks Fee Memo | 6/24/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 6/24/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 7/1/2020 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 7/1/2020 | Partial Approval | COREY HUPP |
| Drywall Nailing | 7/9/2020 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 7/9/2020 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Final | 11/20/2020 | Approved | ROBERT MCDOWELL |
| Final | 11/20/2020 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Final | 11/20/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 11/20/2020 | Approved | ROBERT MCDOWELL |
| MERV13>=Final | 11/20/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 11/20/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 11/20/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 11/20/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 11/20/2020 | Approved | ROBERT MCDOWELL |
| Final | 1/7/2021 | OK to Issue CofO | ROBERT MCDOWELL |