520 W 50TH ST 90037

Certificate Information: 520 W 50TH ST 90037

Application / Permit
18010-70000-05800
Plan Check / Job No.
B18SL01751
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SFD W/ ATTACHED GARAGE.
Permit Issued
Issued on 1/22/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2018 APPLICANT
Green Plans Picked Up 12/11/2018 APPLICANT
Assigned to Plan Check Engineer 12/14/2018 JOE VO
Corrections Issued 12/17/2018 JOE VO
Quality Review Completed 12/19/2018 GARO TELMI
Building Plans Picked Up 1/4/2019 APPLICANT
Applicant returned to address corrections 3/1/2019 JOE VO
Plan Check Approved 3/5/2019 JOE VO
Issued 1/22/2020 LADBS
CofO in Progress 1/7/2021 ROBERT MCDOWELL
Permit Finaled 1/12/2021 DEROLD HAUFF
Permit Finaled 1/12/2021 DEROLD HAUFF
CofO Issued 1/12/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 2/20/2019 COLIN LOREDO
Address approval Cleared 2/21/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 2/21/2019 ELAINE LEI
Hydrant and Access approval Cleared 2/21/2019 ROBERT DUFF
Permit Cleared 2/21/2019 ERIK BEASLEY
Sewer availability Cleared 2/21/2019 ELAINE LEI
Low Impact Development Cleared 2/28/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/28/2019 ELAINE LEI
Driveway location Cleared 3/5/2019 EDUARDO HERMOSO

Contact Information

Contractor F S Z Bros General Contractors Inc; Lic. No.: 794097-B 9036 IMPERIAL HWY      DOWNEY, CA 90242
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/24/2020 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/31/2020 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 5/14/2020 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 5/26/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 6/24/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 6/24/2020 Approved ROBERT MCDOWELL
Green Building Rough 6/24/2020 Approved ROBERT MCDOWELL
HVAC-Rough 6/24/2020 Approved ROBERT MCDOWELL
MERV13>=Rough 6/24/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 6/24/2020 Approved ROBERT MCDOWELL
Verify Rec and Parks Fee Memo 6/24/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 6/24/2020 Approved ROBERT MCDOWELL
Insulation 7/1/2020 Approved COREY HUPP
Interior/Exterior Lathing 7/1/2020 Partial Approval COREY HUPP
Drywall Nailing 7/9/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 7/9/2020 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Final 11/20/2020 Approved ROBERT MCDOWELL
Final 11/20/2020 Corrections Issued ROBERT MCDOWELL
Green Building Final 11/20/2020 Approved ROBERT MCDOWELL
HVAC-Final 11/20/2020 Approved ROBERT MCDOWELL
MERV13>=Final 11/20/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 11/20/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 11/20/2020 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 11/20/2020 Approved ROBERT MCDOWELL
Smoke Detectors 11/20/2020 Approved ROBERT MCDOWELL
Final 1/7/2021 OK to Issue CofO ROBERT MCDOWELL