131 1/2 E 74TH ST 90003
Certificate Information: 131 1/2 E 74TH ST 90003
- Application / Permit
- 18010-70000-05395
- Plan Check / Job No.
- B18SL01628
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU PER AB 494 AND SB 229.
- Permit Issued
- Issued on 5/31/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2018 | ADAM HEGAZI |
| Corrections Issued | 12/10/2018 | ADAM HEGAZI |
| Quality Review Completed | 12/11/2018 | MOHAMMAD FIROUZBAKHT |
| Green Plans Picked Up | 2/5/2019 | APPLICANT |
| Building Plans Picked Up | 2/22/2019 | APPLICANT |
| Applicant returned to address corrections | 4/12/2019 | ADAM HEGAZI |
| Plan Check Approved | 5/31/2019 | ADAM HEGAZI |
| Plan Check Approved | 5/31/2019 | ADAM HEGAZI |
| Issued | 5/31/2019 | LADBS |
| CofO in Progress | 5/13/2021 | FREDDIE RIVERA |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
| CofO Issued | 10/1/2022 | DEROLD HAUFF |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2019 | CELINA MORENO |
| Construction near power lines | Cleared | 3/8/2019 | OSCAR CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 3/8/2019 | JOHN CONNEALLY |
| Green Code | Cleared | 3/27/2019 | KHEDER ALRAZAA |
| Sewer availability | Cleared | 4/26/2019 | ELAINE LEI |
| Low Impact Development | Cleared | 5/21/2019 | SEAN SHAHMIRI |
| Roof/Waste drainage to street | Cleared | 5/21/2019 | ELENA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2019 | Corrections Issued | BOB DUNN |
| Footing/Foundation/Slab | 7/15/2019 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/23/2019 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 8/29/2019 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/5/2019 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/24/2019 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 10/24/2019 | Corrections Issued | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 10/24/2019 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 1/15/2020 | Conditional Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 1/15/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 1/31/2020 | Approved | EUGENE CASSIDY |
| Insulation | 1/31/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 1/31/2020 | Approved | EUGENE CASSIDY |
| HVAC-Final | 2/6/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 2/13/2020 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/24/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Drywall Nailing | 3/24/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 3/24/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/24/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 3/24/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 3/24/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/24/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 3/24/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 3/24/2020 | Corrections Issued | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 3/24/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/11/2020 | Partial Approval | JOHN KLARIN |
| Drywall Nailing | 6/11/2020 | Partial Approval | JOHN KLARIN |
| Final | 6/11/2020 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 6/11/2020 | Partial Approval | JOHN KLARIN |
| Green Building Final | 6/11/2020 | Partial Inspection | JOHN KLARIN |
| Green Building Rough | 6/11/2020 | Partial Approval | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/11/2020 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 6/11/2020 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 6/11/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/13/2020 | SGSOV Not Ready | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/10/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/10/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Final | 12/10/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/10/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/10/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/10/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/10/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Drywall Nailing | 3/15/2021 | Conditional Approval | FREDDIE RIVERA |
| Final | 3/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/15/2021 | No Access for Inspection | FREDDIE RIVERA |
| Green Building Final | 3/15/2021 | No Access for Inspection | FREDDIE RIVERA |
| Green Building Rough | 3/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/15/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 3/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/12/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 5/12/2021 | Approved | FREDDIE RIVERA |
| Final | 5/12/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/12/2021 | Approved | FREDDIE RIVERA |
| Green Building Final | 5/12/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/12/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/12/2021 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 5/12/2021 | Approved | FREDDIE RIVERA |
| Final | 5/13/2021 | OK to Issue CofO | FREDDIE RIVERA |