131 1/2 E 74TH ST 90003

Certificate Information: 131 1/2 E 74TH ST 90003

Application / Permit
18010-70000-05395
Plan Check / Job No.
B18SL01628
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADU PER AB 494 AND SB 229.
Permit Issued
Issued on 5/31/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2018 APPLICANT
Assigned to Plan Check Engineer 12/6/2018 ADAM HEGAZI
Corrections Issued 12/10/2018 ADAM HEGAZI
Quality Review Completed 12/11/2018 MOHAMMAD FIROUZBAKHT
Green Plans Picked Up 2/5/2019 APPLICANT
Building Plans Picked Up 2/22/2019 APPLICANT
Applicant returned to address corrections 4/12/2019 ADAM HEGAZI
Plan Check Approved 5/31/2019 ADAM HEGAZI
Plan Check Approved 5/31/2019 ADAM HEGAZI
Issued 5/31/2019 LADBS
CofO in Progress 5/13/2021 FREDDIE RIVERA
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/8/2019 CELINA MORENO
Construction near power lines Cleared 3/8/2019 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 3/8/2019 CELINA MORENO
Hydrant and Access approval Cleared 3/8/2019 JOHN CONNEALLY
Green Code Cleared 3/27/2019 KHEDER ALRAZAA
Sewer availability Cleared 4/26/2019 ELAINE LEI
Low Impact Development Cleared 5/21/2019 SEAN SHAHMIRI
Roof/Waste drainage to street Cleared 5/21/2019 ELENA LOPEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/11/2019 Corrections Issued BOB DUNN
Footing/Foundation/Slab 7/15/2019 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/23/2019 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 8/29/2019 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 9/5/2019 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 10/24/2019 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 10/24/2019 Corrections Issued EUGENE CASSIDY
Verify Sprinkler Sign Off 10/24/2019 Not Ready for Inspection EUGENE CASSIDY
Insulation 1/15/2020 Conditional Approval EUGENE CASSIDY
PLUMBING-Rough 1/15/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 1/31/2020 Approved EUGENE CASSIDY
Insulation 1/31/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 1/31/2020 Approved EUGENE CASSIDY
HVAC-Final 2/6/2020 Corrections Issued EUGENE CASSIDY
HVAC-Rough 2/13/2020 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 3/24/2020 Not Ready for Inspection EUGENE CASSIDY
Drywall Nailing 3/24/2020 Not Ready for Inspection EUGENE CASSIDY
Final 3/24/2020 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 3/24/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 3/24/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 3/24/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/24/2020 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 3/24/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 3/24/2020 Corrections Issued EUGENE CASSIDY
Verify Sprinkler Sign Off 3/24/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/11/2020 Partial Approval JOHN KLARIN
Drywall Nailing 6/11/2020 Partial Approval JOHN KLARIN
Final 6/11/2020 Not Ready for Inspection JOHN KLARIN
Footing/Foundation/Slab 6/11/2020 Partial Approval JOHN KLARIN
Green Building Final 6/11/2020 Partial Inspection JOHN KLARIN
Green Building Rough 6/11/2020 Partial Approval JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 6/11/2020 SGSOV Not Ready JOHN KLARIN
Service/Power Release 6/11/2020 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 6/11/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/13/2020 SGSOV Not Ready JOSEPH MCGARRY
BUILDING-Rough-Frame 12/10/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Drywall Nailing 12/10/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Final 12/10/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/10/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Green Building Final 12/10/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Green Building Rough 12/10/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/10/2020 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 12/10/2020 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/15/2021 Not Ready for Inspection FREDDIE RIVERA
Drywall Nailing 3/15/2021 Conditional Approval FREDDIE RIVERA
Final 3/15/2021 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 3/15/2021 No Access for Inspection FREDDIE RIVERA
Green Building Final 3/15/2021 No Access for Inspection FREDDIE RIVERA
Green Building Rough 3/15/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 3/15/2021 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 5/12/2021 Approved FREDDIE RIVERA
Drywall Nailing 5/12/2021 Approved FREDDIE RIVERA
Final 5/12/2021 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 5/12/2021 Approved FREDDIE RIVERA
Green Building Final 5/12/2021 Approved FREDDIE RIVERA
Green Building Rough 5/12/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/12/2021 SGSOV Approved FREDDIE RIVERA
Service/Power Release 5/12/2021 Approved FREDDIE RIVERA
Final 5/13/2021 OK to Issue CofO FREDDIE RIVERA