922 W 73RD ST 90044
Certificate Information: 922 W 73RD ST 90044
- Application / Permit
- 18010-70000-05368
- Plan Check / Job No.
- B18SL01609
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY ACCESSORY DWELLING UNIT AND ATTACHED 2-CAR GARAGE PER AB 494 AND SB 229
- Permit Issued
- Issued on 2/26/2020
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 2/26/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2018 | LUKE GONZALES |
| Corrections Issued | 11/17/2018 | LUKE GONZALES |
| Green Plans Picked Up | 11/28/2018 | APPLICANT |
| Quality Review Completed | 12/11/2018 | WESLEY FARRELL |
| Building Plans Picked Up | 1/17/2019 | APPLICANT |
| Applicant returned to address corrections | 3/20/2019 | LUKE GONZALES |
| Plan Check Approved | 5/3/2019 | LUKE GONZALES |
| Issued | 2/26/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 2/13/2019 | KAREN LE |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2019 | ROBYN STEELE |
| Sewer availability | Cleared | 2/21/2019 | ROBYN STEELE |
| Green Code | Cleared | 4/4/2019 | LUKE GONZALES |
| Low Impact Development | Cleared | 4/10/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/12/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 4/29/2019 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/23/2020 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 4/21/2020 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 6/10/2020 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 1/26/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/12/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 2/24/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Pre-Inspection | 3/22/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/6/2021 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/14/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 10/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/1/2025 | Corrections Issued | JOHN QUINTANILLA |