1251 W VERNON AVE 90037
Certificate Information: 1251 W VERNON AVE 90037
- Application / Permit
- 18010-70000-04648
- Plan Check / Job No.
- B18SL01360
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- NEW DETACHED 20X20 CARPORT.
- Permit Issued
- Issued on 11/9/2020
- Issuing Office
- Current Status
- CofO Issued on 6/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2018 | LUKE GONZALES |
| Corrections Issued | 9/21/2018 | LUKE GONZALES |
| Plan Check Approved | 8/2/2019 | TEODORO DIAZ RODRIGUEZ |
| Issued | 11/9/2020 | APPLICANT |
| CofO in Progress | 6/6/2021 | ROBERT MCDOWELL |
| Permit Finaled | 6/17/2021 | DEROLD HAUFF |
| CofO Issued | 6/17/2021 | DEROLD HAUFF |
| Permit Finaled | 6/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2019 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/3/2019 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pelayo,, Victor; Lic. No.: C73094 | 736 N 4TH STREET MONTEBELLO, CA 90640 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/16/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/21/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/21/2021 | Approved | FREDDIE RIVERA |
| Final | 6/4/2021 | OK to Issue CofO | ROBERT MCDOWELL |
| Green Building Final | 6/4/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 6/4/2021 | SGSOV No Gas | ROBERT MCDOWELL |
| Service/Power Release | 6/4/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Smoke Detectors | 6/4/2021 | Not Ready for Inspection | ROBERT MCDOWELL |