335 E 81ST ST 90003
Certificate Information: 335 E 81ST ST 90003
- Application / Permit
- 18010-70000-03957
- Plan Check / Job No.
- B18SL01195
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (20X20) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 (SEE COMMENTS) ***SEE COMMENTS***
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- Metro
- Current Status
- Issued on 2/21/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/10/2018 | APPLICANT |
| Green Plans Picked Up | 8/28/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2018 | JOSHUA DIAZ |
| Corrections Issued | 9/13/2018 | JOSHUA DIAZ |
| Quality Review Completed | 9/27/2018 | WESLEY FARRELL |
| Building Plans Picked Up | 9/27/2018 | APPLICANT |
| Applicant returned to address corrections | 9/21/2020 | MINA HABIB |
| Applicant returned to address corrections | 8/25/2021 | MINA HABIB |
| Applicant returned to address corrections | 8/26/2021 | MINA HABIB |
| Applicant returned to address corrections | 3/31/2022 | MINA HABIB |
| Applicant returned to address corrections | 4/11/2022 | MINA HABIB |
| Applicant returned to address corrections | 4/12/2022 | MINA HABIB |
| Applicant returned to address corrections | 12/12/2022 | MINA HABIB |
| Applicant returned to address corrections | 12/30/2022 | MINA HABIB |
| Applicant returned to address corrections | 2/1/2023 | MINA HABIB |
| Plan Check Approved | 2/21/2023 | MINA HABIB |
| Issued | 2/21/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2019 | CELINA MORENO |
| Address approval | Cleared | 5/14/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 5/14/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 6/5/2019 | JORGE MEJIA LEMUS |
| Green Code | Cleared | 10/1/2019 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 2/5/2020 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 12/28/2022 | AMAAN MALIK |
| Green Code | Cleared | 2/1/2023 | MINA HABIB |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/13/2023 | Conditional Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 4/19/2023 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/10/2023 | Partial Inspection | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 5/15/2023 | Corrections Issued | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 6/23/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 6/23/2023 | Approved | MICHAEL LEWIS |
| Pre-Inspection | 2/6/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 4/16/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 4/16/2024 | Approved | MICHAEL LEWIS |
| Sewer | 4/16/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 4/16/2024 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/2/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/1/2024 | Conditional Approval | MICHAEL LEWIS |
| Green Building Rough | 8/1/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/1/2024 | Approved | LUIS CASTRO |
| HVAC-Rough | 10/1/2024 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 10/1/2024 | Approved | LUIS CASTRO |
| Wood Frame | 10/1/2024 | Not Ready for Inspection | LUIS CASTRO |
| Insulation | 12/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/7/2025 | Partial Inspection | JOHN QUINTANILLA |
| Underground Mechanical | 1/7/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 2/12/2025 | Corrections Issued | JOSH MEISTER |
| Shower Pan | 2/12/2025 | Approved | JOSH MEISTER |
| Insulation | 3/4/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 3/4/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 3/5/2025 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 4/2/2025 | Approved | ANTHONY RAMOS |
| Final | 2/19/2026 | Corrections Issued | JOHN QUINTANILLA |
| Final | 4/2/2026 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Final | 4/2/2026 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Not Ready | JOHN QUINTANILLA |
| Service/Power Release | 4/2/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Smoke Detectors | 4/2/2026 | Approved | JOHN QUINTANILLA |