202-204 E 116TH ST 90061

Certificate Information: 202-204 E 116TH ST 90061

Application / Permit
18010-70000-03503
Plan Check / Job No.
B18SL01021
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2- STORY DUPLEX.
Permit Issued
Issued on 12/21/2018
Issuing Office
South Los Angeles
Current Status
CofO Issued on 1/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2018 APPLICANT
Green Plans Picked Up 8/2/2018 APPLICANT
Assigned to Plan Check Engineer 8/9/2018 CRISTINA SALAZAR
Corrections Issued 8/11/2018 CRISTINA SALAZAR
Quality Review Completed 8/14/2018 DAVID CHANG
Building Plans Picked Up 8/23/2018 APPLICANT
Applicant returned to address corrections 11/1/2018 CRISTINA SALAZAR
Applicant returned to address corrections 11/9/2018 CRISTINA SALAZAR
Plan Check Approved 11/20/2018 CRISTINA SALAZAR
Issued 12/21/2018 LADBS
CofO in Progress 12/30/2020 EUGENE CASSIDY
Permit Finaled 1/2/2021 DEROLD HAUFF
CofO Issued 1/2/2021 DEROLD HAUFF
Permit Finaled 1/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 9/11/2018 NEGAR NEJAD
Eng Process Fee Ord 176,300 Cleared 9/21/2018 ADOLFO GUTIERREZ
Sewer availability Cleared 9/21/2018 ADOLFO GUTIERREZ
Address approval Cleared 10/31/2018 KARAN PATEL
Low Impact Development Cleared 10/31/2018 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/31/2018 KARAN PATEL

Contact Information

Contractor New Life Construction; Lic. No.: 840681-B 10547 VARIEL AVE      CHATSWORTH, CA 91311
Engineer , ; Lic. No.: C83859 7366 W MANCHESTER AVE   #B    , CA 90045

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/28/2019 Approved JOHN KLARIN
Footing/Foundation/Slab 6/28/2019 Approved JOHN KLARIN
BUILDING-Rough-Frame 10/1/2019 No Access for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 10/1/2019 No Access for Inspection EUGENE CASSIDY
Green Building Rough 10/1/2019 No Access for Inspection EUGENE CASSIDY
MERV13>=Rough 10/1/2019 No Access for Inspection EUGENE CASSIDY
PLUMBING-Rough 10/1/2019 No Access for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 10/1/2019 No Access for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 10/16/2019 Corrections Issued WILLIAM ROSE
ELECTRICAL-Rough 10/16/2019 Not Ready for Inspection WILLIAM ROSE
Green Building Rough 10/16/2019 Not Ready for Inspection WILLIAM ROSE
MERV13>=Rough 10/16/2019 Not Ready for Inspection WILLIAM ROSE
Sewer 10/16/2019 Not Ready for Inspection WILLIAM ROSE
Verify Sprinkler Sign Off 10/16/2019 Not Ready for Inspection WILLIAM ROSE
ELECTRICAL-Rough 11/5/2019 No Access for Inspection JOHN KLARIN
PLUMBING-Final 11/5/2019 No Access for Inspection JOHN KLARIN
Wood Frame 11/5/2019 No Access for Inspection JOHN KLARIN
Deputy Wood Construction 12/6/2019 Conditional Approval WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 12/6/2019 Corrections Issued WILLIAM ROSE
BUILDING-Rough-Frame 1/28/2020 Approved WILLIAM ROSE
ELECTRICAL-Rough 1/28/2020 Approved WILLIAM ROSE
Green Building Rough 1/28/2020 Approved WILLIAM ROSE
HVAC-Rough 1/28/2020 Approved WILLIAM ROSE
MERV13>=Rough 1/28/2020 Approved WILLIAM ROSE
PLUMBING-Rough 1/28/2020 Approved WILLIAM ROSE
Verify Sprinkler Sign Off 1/28/2020 Approved WILLIAM ROSE
Insulation 1/31/2020 Approved WILLIAM ROSE
Drywall Nailing 2/5/2020 Approved WILLIAM ROSE
Interior/Exterior Lathing 2/5/2020 Approved WILLIAM ROSE
Gas Test 5/20/2020 Approved BRIAN CHRISTIAN
Sewer 5/20/2020 Approved BRIAN CHRISTIAN
Verify Rec and Parks Fee Memo 8/17/2020 Partial Approval EUGENE CASSIDY
ELECTRICAL-Final 9/25/2020 Approved EUGENE CASSIDY
Service/Power Release 9/25/2020 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 9/28/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 9/28/2020 Corrections Issued EUGENE CASSIDY
Final 10/26/2020 Corrections Issued EUGENE CASSIDY
Gas Test 10/26/2020 Approved EUGENE CASSIDY
Green Building Final 10/26/2020 Approved EUGENE CASSIDY
HVAC-Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/26/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 10/26/2020 Approved EUGENE CASSIDY
Final 10/30/2020 Corrections Issued EUGENE CASSIDY
MERV13>=Final 10/30/2020 Approved EUGENE CASSIDY
Service/Power Release 10/30/2020 Not Ready for Inspection EUGENE CASSIDY
Final 11/9/2020 Corrections Issued EUGENE CASSIDY
HVAC-Final 11/9/2020 Approved EUGENE CASSIDY
PLUMBING-Final 11/9/2020 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 11/9/2020 Not Ready for Inspection EUGENE CASSIDY
Final 11/16/2020 Corrections Issued EUGENE CASSIDY
Service/Power Release 11/16/2020 Not Ready for Inspection EUGENE CASSIDY
Final 12/29/2020 OK to Issue CofO EUGENE CASSIDY
Service/Power Release 12/29/2020 Approved EUGENE CASSIDY