202-204 E 116TH ST 90061
Certificate Information: 202-204 E 116TH ST 90061
- Application / Permit
- 18010-70000-03503
- Plan Check / Job No.
- B18SL01021
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2- STORY DUPLEX.
- Permit Issued
- Issued on 12/21/2018
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 1/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2018 | APPLICANT |
| Green Plans Picked Up | 8/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2018 | CRISTINA SALAZAR |
| Corrections Issued | 8/11/2018 | CRISTINA SALAZAR |
| Quality Review Completed | 8/14/2018 | DAVID CHANG |
| Building Plans Picked Up | 8/23/2018 | APPLICANT |
| Applicant returned to address corrections | 11/1/2018 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 11/9/2018 | CRISTINA SALAZAR |
| Plan Check Approved | 11/20/2018 | CRISTINA SALAZAR |
| Issued | 12/21/2018 | LADBS |
| CofO in Progress | 12/30/2020 | EUGENE CASSIDY |
| Permit Finaled | 1/2/2021 | DEROLD HAUFF |
| CofO Issued | 1/2/2021 | DEROLD HAUFF |
| Permit Finaled | 1/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 9/11/2018 | NEGAR NEJAD |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2018 | ADOLFO GUTIERREZ |
| Sewer availability | Cleared | 9/21/2018 | ADOLFO GUTIERREZ |
| Address approval | Cleared | 10/31/2018 | KARAN PATEL |
| Low Impact Development | Cleared | 10/31/2018 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/31/2018 | KARAN PATEL |
Contact Information
| Contractor | New Life Construction; Lic. No.: 840681-B | 10547 VARIEL AVE CHATSWORTH, CA 91311 |
| Engineer | , ; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B , CA 90045 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/28/2019 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 6/28/2019 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/1/2019 | No Access for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/1/2019 | No Access for Inspection | EUGENE CASSIDY |
| Green Building Rough | 10/1/2019 | No Access for Inspection | EUGENE CASSIDY |
| MERV13>=Rough | 10/1/2019 | No Access for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 10/1/2019 | No Access for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 10/1/2019 | No Access for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/16/2019 | Corrections Issued | WILLIAM ROSE |
| ELECTRICAL-Rough | 10/16/2019 | Not Ready for Inspection | WILLIAM ROSE |
| Green Building Rough | 10/16/2019 | Not Ready for Inspection | WILLIAM ROSE |
| MERV13>=Rough | 10/16/2019 | Not Ready for Inspection | WILLIAM ROSE |
| Sewer | 10/16/2019 | Not Ready for Inspection | WILLIAM ROSE |
| Verify Sprinkler Sign Off | 10/16/2019 | Not Ready for Inspection | WILLIAM ROSE |
| ELECTRICAL-Rough | 11/5/2019 | No Access for Inspection | JOHN KLARIN |
| PLUMBING-Final | 11/5/2019 | No Access for Inspection | JOHN KLARIN |
| Wood Frame | 11/5/2019 | No Access for Inspection | JOHN KLARIN |
| Deputy Wood Construction | 12/6/2019 | Conditional Approval | WILLIAM ROSE |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2019 | Corrections Issued | WILLIAM ROSE |
| BUILDING-Rough-Frame | 1/28/2020 | Approved | WILLIAM ROSE |
| ELECTRICAL-Rough | 1/28/2020 | Approved | WILLIAM ROSE |
| Green Building Rough | 1/28/2020 | Approved | WILLIAM ROSE |
| HVAC-Rough | 1/28/2020 | Approved | WILLIAM ROSE |
| MERV13>=Rough | 1/28/2020 | Approved | WILLIAM ROSE |
| PLUMBING-Rough | 1/28/2020 | Approved | WILLIAM ROSE |
| Verify Sprinkler Sign Off | 1/28/2020 | Approved | WILLIAM ROSE |
| Insulation | 1/31/2020 | Approved | WILLIAM ROSE |
| Drywall Nailing | 2/5/2020 | Approved | WILLIAM ROSE |
| Interior/Exterior Lathing | 2/5/2020 | Approved | WILLIAM ROSE |
| Gas Test | 5/20/2020 | Approved | BRIAN CHRISTIAN |
| Sewer | 5/20/2020 | Approved | BRIAN CHRISTIAN |
| Verify Rec and Parks Fee Memo | 8/17/2020 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Final | 9/25/2020 | Approved | EUGENE CASSIDY |
| Service/Power Release | 9/25/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 9/28/2020 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 9/28/2020 | Corrections Issued | EUGENE CASSIDY |
| Final | 10/26/2020 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 10/26/2020 | Approved | EUGENE CASSIDY |
| Green Building Final | 10/26/2020 | Approved | EUGENE CASSIDY |
| HVAC-Final | 10/26/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Final | 10/26/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 10/26/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/26/2020 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 10/26/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 10/26/2020 | Approved | EUGENE CASSIDY |
| Final | 10/30/2020 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Final | 10/30/2020 | Approved | EUGENE CASSIDY |
| Service/Power Release | 10/30/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 11/9/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 11/9/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 11/9/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 11/9/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 11/16/2020 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 11/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 12/29/2020 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 12/29/2020 | Approved | EUGENE CASSIDY |