206-208 E 116TH ST 90061

Certificate Information: 206-208 E 116TH ST 90061

Application / Permit
18010-70000-03501
Plan Check / Job No.
B18SL01020
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX.
Permit Issued
Issued on 8/19/2019
Issuing Office
Valley
Current Status
CofO Issued on 1/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2018 APPLICANT
Green Plans Picked Up 7/25/2018 APPLICANT
Assigned to Plan Check Engineer 8/9/2018 FARSHAD ALIMOHAMADI
Corrections Issued 8/14/2018 FARSHAD ALIMOHAMADI
Quality Review Completed 8/14/2018 DAVID CHANG
Building Plans Picked Up 8/15/2018 APPLICANT
Plan Check Approved 8/13/2019 FARSHAD ALIMOHAMADI
Issued 8/19/2019 LADBS
CofO in Progress 12/31/2020 ANSON MAGLASANG
Permit Finaled 1/2/2021 DEROLD HAUFF
CofO Issued 1/2/2021 DEROLD HAUFF
Permit Finaled 1/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/21/2018 ADOLFO GUTIERREZ
Sewer availability Cleared 9/21/2018 ADOLFO GUTIERREZ
Green Code Cleared 11/9/2018 COLIN LOREDO
Trees in Parkway Cleared 2/27/2019 ADRIAN SANCHEZ
Address approval Cleared 7/26/2019 ADRIAN SANCHEZ
Permit Cleared 7/26/2019 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 8/13/2019 GEORGE SUCHAND
Low Impact Development Cleared 8/13/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/13/2019 ERIK BEASLEY

Contact Information

Contractor New Life Construction; Lic. No.: 840681-B 10547 VARIEL AVE      CHATSWORTH, CA 91311

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/13/2019 No Access for Inspection WILLIAM ROSE
PLUMBING-Rough 9/13/2019 No Access for Inspection WILLIAM ROSE
Sewer 9/13/2019 No Access for Inspection WILLIAM ROSE
Excavation/Setback/Form/Re-Bar 10/31/2019 Not Ready for Inspection WILLIAM ROSE
Footing/Foundation/Slab 10/31/2019 Not Ready for Inspection WILLIAM ROSE
PLUMBING-Rough 10/31/2019 Not Ready for Inspection WILLIAM ROSE
Sewer 10/31/2019 Not Ready for Inspection WILLIAM ROSE
Excavation/Setback/Form/Re-Bar 1/23/2020 Partial Approval WILLIAM ROSE
PLUMBING-Rough 1/23/2020 Partial Approval WILLIAM ROSE
Underground Mechanical 1/23/2020 Partial Approval WILLIAM ROSE
Footing/Foundation/Slab 1/30/2020 Approved WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Partial Approval WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Partial Approval WILLIAM ROSE
Interior/Exterior Lathing 3/9/2020 Not Ready for Inspection WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 3/12/2020 Approved WILLIAM ROSE
BUILDING-Rough-Frame 4/7/2020 Approved EUGENE CASSIDY
Green Building Rough 4/7/2020 Approved EUGENE CASSIDY
MERV13>=Rough 4/7/2020 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 4/7/2020 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 4/7/2020 Approved EUGENE CASSIDY
Insulation 4/10/2020 Approved EUGENE CASSIDY
Drywall Nailing 4/21/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 4/21/2020 Approved BRIAN CHRISTIAN
Gas Test 5/20/2020 Approved BRIAN CHRISTIAN
Sewer 5/20/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 9/25/2020 Approved EUGENE CASSIDY
HVAC-Final 9/25/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 9/25/2020 Corrections Issued EUGENE CASSIDY
Service/Power Release 9/25/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 10/26/2020 Approved EUGENE CASSIDY
Final 10/26/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 10/26/2020 Approved EUGENE CASSIDY
HVAC-Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/26/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 10/26/2020 Approved EUGENE CASSIDY
Final 10/30/2020 Corrections Issued EUGENE CASSIDY
MERV13>=Final 10/30/2020 Approved EUGENE CASSIDY
Service/Power Release 10/30/2020 Not Ready for Inspection EUGENE CASSIDY
Final 11/9/2020 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 11/9/2020 Approved EUGENE CASSIDY
PLUMBING-Final 11/9/2020 Approved EUGENE CASSIDY
Service/Power Release 11/9/2020 Approved EUGENE CASSIDY