154-156 E 116TH ST 90061

Certificate Information: 154-156 E 116TH ST 90061

Application / Permit
18010-70000-03326
Plan Check / Job No.
B18SL00961
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW (3497 SQFT) 2 STORY DUPLEX.
Permit Issued
Issued on 11/7/2019
Issuing Office
South Los Angeles
Current Status
CofO Issued on 1/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2018 APPLICANT
Green Plans Picked Up 7/16/2018 APPLICANT
Assigned to Plan Check Engineer 7/26/2018 RAHEL BEYENE
Corrections Issued 7/30/2018 RAHEL BEYENE
Quality Review Completed 7/31/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 8/2/2018 APPLICANT
Applicant returned to address corrections 1/30/2019 RAHEL BEYENE
Plan Check Approved 2/8/2019 RAHEL BEYENE
Application Withdrawn-Void 10/2/2019 QUAN NGHIEM
Re-Activate Application 10/2/2019 QUAN NGHIEM
Issued 11/7/2019 LADBS
CofO in Progress 12/29/2020 ANSON MAGLASANG
Permit Finaled 1/2/2021 DEROLD HAUFF
CofO Issued 1/2/2021 DEROLD HAUFF
Permit Finaled 1/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/21/2018 ADOLFO GUTIERREZ
Sewer availability Cleared 9/21/2018 ADOLFO GUTIERREZ
Green Code Cleared 10/11/2018 SARAH ABOULHOSN
Trees in Parkway Cleared 1/22/2019 ADRIAN SANCHEZ
Address approval Cleared 1/28/2019 JEANETTE VONG
Low Impact Development Cleared 1/28/2019 ORVAL HERNANDEZ-MARCI
Permit Cleared 1/28/2019 JEANETTE VONG
Roof/Waste drainage to street Cleared 1/28/2019 JEANETTE VONG
Hold Cleared 1/21/2020 LOURDES RAMIRO

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/24/2020 Approved WILLIAM ROSE
Underground Mechanical 1/24/2020 Partial Approval WILLIAM ROSE
Footing/Foundation/Slab 1/30/2020 Approved WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 2/7/2020 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 2/11/2020 Partial Approval WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Approved WILLIAM ROSE
BUILDING-Rough-Frame 4/2/2020 Approved BRIAN CHRISTIAN
Green Building Rough 4/2/2020 Approved BRIAN CHRISTIAN
MERV13>=Rough 4/2/2020 Approved BRIAN CHRISTIAN
Rough-Elec/Plmb/HVAC 4/2/2020 Approved BRIAN CHRISTIAN
Verify Sprinkler Sign Off 4/2/2020 Approved BRIAN CHRISTIAN
Insulation 4/6/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 4/10/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/10/2020 Approved EUGENE CASSIDY
Gas Test 5/20/2020 Approved BRIAN CHRISTIAN
Sewer 5/20/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 9/25/2020 Approved EUGENE CASSIDY
Service/Power Release 9/25/2020 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 9/28/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 9/28/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 10/26/2020 Approved EUGENE CASSIDY
Final 10/26/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 10/26/2020 Approved EUGENE CASSIDY
HVAC-Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/26/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 10/26/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 10/26/2020 Approved EUGENE CASSIDY
Final 10/30/2020 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 10/30/2020 Approved EUGENE CASSIDY
Service/Power Release 10/30/2020 Not Ready for Inspection EUGENE CASSIDY
Final 11/6/2020 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 11/6/2020 Approved EUGENE CASSIDY
PLUMBING-Final 11/6/2020 Approved EUGENE CASSIDY
Service/Power Release 11/6/2020 Approved EUGENE CASSIDY